<strong>COUNCIL</strong> MINUTES<br />

TUESDAY 27 NOVEMBER 2012<br />

August 2011 June 2012<br />

Project Duration: 13 Years (2012-2025) 13 Years (2012-2025)<br />

No <strong>of</strong> Lots: 2,310 2,351<br />

Gross Income: $669.5 million $674.3 million<br />

Development Costs: $357.6 million $366.1 million<br />

Net Pr<strong>of</strong>it: $311.9 million $308.2 million<br />

<strong>Town</strong> <strong>of</strong> <strong>Cambridge</strong> Share*: $26 million $26 million<br />

* This is not the net present value.<br />

The first few years <strong>of</strong> the project cashflow produces the following cash outflows/inflows,<br />

which allow Owner’s capital and pr<strong>of</strong>it distributions to commence:-<br />

2012 2013 2014 2015<br />

Cumulative net inflow/(outflow) -$12.6 million -$0.9 million $7.1 million $14.9 million<br />

Capital Distribution* $7.0 million $6.3 million<br />

Pr<strong>of</strong>it Distribution<br />

$8.7 million<br />

<strong>Town</strong> <strong>of</strong> <strong>Cambridge</strong> share $585,000 $1.25 million<br />

* Note, the owners have injected initial equity into the project from the proceeds from an agreement with the State<br />

Government, which returned developable land to the State for ‘Bush Forever’.<br />

DETAILS:<br />

Business Report<br />

The meeting <strong>of</strong> the TPRC noted the progress on lot creation with a brief outline <strong>of</strong> civil works<br />

components to date;<br />

Civil Works<br />

Stage Status Lots Titles Issued<br />

Neerabup Rd 95% complete n/a n/a<br />

intersection<br />

Stage 2<br />

Practical<br />

38 October 2012<br />

Completion<br />

Stage 3 85% Complete 43 November 2012<br />

Stage 4 20% Complete 48 February 2013<br />

Stage 6A 90% Complete 8 December 2012<br />

Bulk Earthworks<br />

Stage<br />

Status<br />

Stage 5<br />

15% Complete<br />

Stage 7<br />

Delayed<br />

Landscaping Works<br />

Stage<br />

Status<br />

Drainage Basin &<br />

Neerabup Rd<br />

Works delayed 2<br />

weeks<br />

Lot 1 Entry Works deferred<br />

Statement<br />

Stage 1b POS Works delayed 2<br />

weeks<br />

Clearances for Stage 1B comprising 11 cottage lots have been obtained and titles are<br />

expected to be issued shortly.<br />

Clearances for Stage 2 comprising 38 lots have been obtained and titles are expected to be<br />

issued shortly.<br />

H:\CEO\GOV\<strong>COUNCIL</strong> MINUTES\12 MINUTES\NOVEMBER 2012\C CR.DOCX 189