<strong>COUNCIL</strong> MINUTES<br />
TUESDAY 27 NOVEMBER 2012<br />
Stage 1 A: Total $2,000,000<br />
Design Element<br />
Amount<br />
Preliminaries $237,200<br />
New toilet facilities $225,000<br />
New front <strong>of</strong> house facilities $328,030<br />
Extension <strong>of</strong> upper seating $ 95,000<br />
New control room $191,970<br />
Sewer and water upgrade $346,000<br />
Contingencies, escalation, project management and pr<strong>of</strong>essional fees $576,800<br />
Total $2,000,000<br />
Stage 2: Total $2,850,000<br />
Design Element<br />
Amount<br />
Preliminaries $182,930<br />
New fixed seating $291,600<br />
New aisle north and centre $ 66,600<br />
Lift $180,000<br />
New paths and connections $906,000<br />
Picnic area $373,729<br />
Contingencies, escalation, project management and pr<strong>of</strong>essional fees $849,141<br />
Total $2,850,000<br />
These budgets exclude any substantial car parking improvements and presume temporary<br />
verge parking under a management plan would suffice in peak periods. Significant costs<br />
would be incurred to increase the sealed car park capacity adjoining the existing car parks.<br />
Increased seating capacity should not be considered without providing necessary car park<br />
facility.<br />
POLICY/STATUTORY IMPLICATIONS:<br />
Nil<br />
FINANCIAL IMPLICATIONS:<br />
An amount <strong>of</strong> $384,000 was carried forward in this year's budget to undertake various<br />
capital items. A balance <strong>of</strong> approximately $276,000 is remaining.<br />
An amount <strong>of</strong> approximately $6 million is required to complete the master plan works that<br />
can be broken into distinct stages:- Stage 1: $1,150,000, Stage 1A: $2,000,000 and Stage 2:<br />
$2,850,000.<br />
The <strong>Town</strong> is already committed to a number <strong>of</strong> major projects including the Wembley Sports<br />
Park, City <strong>of</strong> Perth Surf Club and Commercial Development, the Bold Park Aquatic Centre<br />
and Wembley Golf Course Hospitality. No funding sources have yet been identified for the<br />
Quarry Amphitheatre Master Plan works.<br />
There are limited sources <strong>of</strong> funds for the major capital works to upgrade the Quarry, as<br />
identified in this report. The major source <strong>of</strong> funding is the Endowment Lands Account which<br />
is already committed to some other major projects as highlighted above.<br />
Other sources include, user fees, sponsorship for naming rights and grant funds.<br />
H:\CEO\GOV\<strong>COUNCIL</strong> MINUTES\12 MINUTES\NOVEMBER 2012\C CR.DOCX 158