<strong>COUNCIL</strong> MINUTES<br />
TUESDAY 27 NOVEMBER 2012<br />
Recommended Design Elements<br />
Early in the review, it was agreed that the need to get the seating plan and sight lines right<br />
was a critical driver <strong>of</strong> the overall approach to the design.<br />
Several seating plan options were investigated and tested against the stage centre line and<br />
site lines. The investigations revealed the importance <strong>of</strong> re-orientation <strong>of</strong> the stage to align<br />
the stage centre line with the centre line <strong>of</strong> the auditorium, thereby achieving optimal<br />
sightlines.<br />
The recommended seating plan can be undertaken in stages and involves:<br />
• Redevelopment <strong>of</strong> lower seating ( Stage 1);<br />
• Extension <strong>of</strong> upper seating (Stage 1a); and<br />
• New fixed seating (Stage 2).<br />
The recommended concept master plan was supported by Elected Members at the 9<br />
October 2012 Council Forum and by a number <strong>of</strong> key stakeholders at subsequent<br />
consultation meetings. Although no concerns were raised in relation to the actual master<br />
plan design, a concern was raised by key stakeholders in relation to possible significant<br />
increase in hire charges.<br />
Cost Estimates and Staged Construction<br />
A detailed capital cost estimate was undertaken by a Quantity Surveyor (QS) and was<br />
reviewed by Director Projects. Some necessary cost elements were missing from the QS<br />
cost plan which have now been included in this report.<br />
The overall cost <strong>of</strong> the Concept Master Plan is approximately $6 million that is broken down<br />
into stages. A summary is outlined below:-<br />
It is important that Council notes that the staging and cost plan is predicated on works being<br />
undertaken during a full 26 week "<strong>of</strong>f" season (April to September). There is insufficient time<br />
to fund, design, tender, award and undertake works to commence in April 2013. Depending<br />
on Council decisions, a smaller scope <strong>of</strong> works could be undertaken in the period up to<br />
September 2013, however, the possibility <strong>of</strong> meeting this timeframe has not been confirmed.<br />
This would change the cost plan accordingly.<br />
Stage 1: Total $1,150,000<br />
Design Element<br />
Amount<br />
Preliminaries $101,600<br />
Defects rectification, rock face remediation works, strengthening <strong>of</strong> concrete slab, and<br />
protection system from falling debris at top <strong>of</strong> quarry $143,030<br />
Re-orientate stage and redevelop stage floor $179,460<br />
New lower seating $ 55,200<br />
Off stage storage $ 20,000<br />
New southern Aisle and new exits $ 73,440<br />
New temporary toilet facilities $ 40,000<br />
New lighting towers and gantry; new audio equipment, and modifications to electrical $166,200<br />
infrastructure<br />
Contingencies, escalation, project management and pr<strong>of</strong>essional fees $371,070<br />
Total $1,150,000<br />