EXHIBIT B<br />
DIABLO VISTA PUMPING PLANT REPLACEMENT PROJECT<br />
MITIGATION MONITORING AND REPORTING PROGRAM<br />
Mitigation Measures<br />
AETHESTICS/VISUAL QUALITY<br />
Mitigation Measure AES-2: EBMUD will require the construction contractor to ensure<br />
that the construction site is clean by storing building materials and equipment within the<br />
proposed staging areas or in areas removed from public view where feasible, and by<br />
promptly removing trash and construction debris that will not be reused on site.<br />
Construction phasing will be organized to minimize equipment storage on site.<br />
Impact being Mitigated<br />
Impact AES-1: Project<br />
construction could generate visual<br />
impacts experienced in the shortterm<br />
from nearby areas during<br />
construction.<br />
Timing<br />
Requirement<br />
During<br />
Construction<br />
Responsibility for<br />
Implementation<br />
EBMUD Contractor<br />
Responsibility<br />
for<br />
Monitoring<br />
EBMUD Construction<br />
Inspector<br />
Design Phase<br />
Check Box<br />
Completed by<br />
Date<br />
Construction Phase<br />
Check Box<br />
Completed by<br />
Date<br />
Post-Construction<br />
Phase<br />
Check Box<br />
NA<br />
Mitigation Measure AES-2:<br />
« During the detailed design phase, EBMUD will prepare a detailed Architecture<br />
Landscape Plan for the Diablo Vista Pumping Plant Replacement Project property<br />
consistent with the 2012 Landscape Plan. Landscape vegetation, including trees,<br />
removed as a result of the Proposed Project will be replaced based on the Architectural<br />
Landscape Plan that will be implemented. Drought tolerant plants and native species<br />
identified in the Contra Costa County Fire Protection <strong>District</strong>'s Suggested Fire Smart<br />
Plant List and approved City of Lafayette Planting list will be incorporated into the<br />
Landscape Plan as practicable.<br />
• EBMUD will incorporate aesthetic/architectural design details for the new Diablo Vista<br />
Pumping Plant structure, fencing, and related site improvements consistent with the<br />
2012 Architecture Plan.<br />
• EBMUD will require its construction contractor to provide a warranty for new<br />
plantings for 1 year after Project completion.<br />
• A five-year tree monitoring program will be implemented. A performance standard of<br />
not less than 75 percent survival rate of replacement tree plantings and a requirement<br />
that trees are evaluated as self-sustaining at the end of five years.<br />
Impact AES-2: Project<br />
construction could alter the site's<br />
appearance and long-term visual<br />
effects.<br />
Design /<br />
Construction<br />
Design Engineer /<br />
Construction<br />
Inspection<br />
Design Project Manager/<br />
EBMUD Construction<br />
Inspector / EBMUD<br />
Maintenance<br />
Completed by<br />
Date<br />
Completed by<br />
Date<br />
NA<br />
AIR QUALITY<br />
Mitigation Measure AtR-1: The BAAQMD "Basic Construction Mitigation Measures"<br />
will be incorporated by EBMUD into the contract specifications;<br />
• All exposed surfaces (e.g., parking areas, staging areas, soil piles, graded areas, and<br />
unpaved access roads) would be rocked and/or watered or soil stabilizers (nontoxic)<br />
would be applied as necessitated by soil and air conditions.<br />
• All land clearing, grubbing, scraping, excavation, land leveling, grading, cut and fill,<br />
and demolition activities will be effectively controlled for fugitive dust emissions<br />
utilizing application of water or presoaking.<br />
• Ail haul trucks transporting soil, sand, or other loose material off-site would be covered<br />
or require all trucks to maintain at least two feet of freeboard.<br />
• All visible mud or dirt tracked-out onto adjacent public roads would be removed using<br />
wet power vacuum street sweepers at least once per day. The use of dry power<br />
sweeping is prohibited.<br />
« All vehicle speeds on unpaved roads would be limited to 15 mph.<br />
• Idling times would be minimized either by shutting equipment off when not in use or<br />
reducing the maximum idling time to 5 minutes (as required by the California airborne<br />
toxics control measure Title 13. Section 2485 of California Code of Regulations<br />
ICCRJ).<br />
• AH construction equipment would be maintained and properly tuned, in accordance<br />
with manufacturer's specifications. All equipment would be checked by a certified<br />
mechanic and determined to be running in proper condition prior to operation.<br />
Impact AIR-1: Construction<br />
activities would generate exhaust<br />
emissions from vehicles/equipment<br />
and fugitive dust particles that<br />
could affect air quality.<br />
Construction<br />
EBMUD contractor<br />
EBMUD Construction<br />
Inspector<br />
Completed by<br />
Date<br />
Completed by<br />
Date<br />
NA