EXHIBIT B<br />

DIABLO VISTA PUMPING PLANT REPLACEMENT PROJECT<br />

MITIGATION MONITORING AND REPORTING PROGRAM<br />

Mitigation Measures<br />

AETHESTICS/VISUAL QUALITY<br />

Mitigation Measure AES-2: EBMUD will require the construction contractor to ensure<br />

that the construction site is clean by storing building materials and equipment within the<br />

proposed staging areas or in areas removed from public view where feasible, and by<br />

promptly removing trash and construction debris that will not be reused on site.<br />

Construction phasing will be organized to minimize equipment storage on site.<br />

Impact being Mitigated<br />

Impact AES-1: Project<br />

construction could generate visual<br />

impacts experienced in the shortterm<br />

from nearby areas during<br />

construction.<br />

Timing<br />

Requirement<br />

During<br />

Construction<br />

Responsibility for<br />

Implementation<br />

EBMUD Contractor<br />

Responsibility<br />

for<br />

Monitoring<br />

EBMUD Construction<br />

Inspector<br />

Design Phase<br />

Check Box<br />

Completed by<br />

Date<br />

Construction Phase<br />

Check Box<br />

Completed by<br />

Date<br />

Post-Construction<br />

Phase<br />

Check Box<br />

NA<br />

Mitigation Measure AES-2:<br />

« During the detailed design phase, EBMUD will prepare a detailed Architecture<br />

Landscape Plan for the Diablo Vista Pumping Plant Replacement Project property<br />

consistent with the 2012 Landscape Plan. Landscape vegetation, including trees,<br />

removed as a result of the Proposed Project will be replaced based on the Architectural<br />

Landscape Plan that will be implemented. Drought tolerant plants and native species<br />

identified in the Contra Costa County Fire Protection <strong>District</strong>'s Suggested Fire Smart<br />

Plant List and approved City of Lafayette Planting list will be incorporated into the<br />

Landscape Plan as practicable.<br />

• EBMUD will incorporate aesthetic/architectural design details for the new Diablo Vista<br />

Pumping Plant structure, fencing, and related site improvements consistent with the<br />

2012 Architecture Plan.<br />

• EBMUD will require its construction contractor to provide a warranty for new<br />

plantings for 1 year after Project completion.<br />

• A five-year tree monitoring program will be implemented. A performance standard of<br />

not less than 75 percent survival rate of replacement tree plantings and a requirement<br />

that trees are evaluated as self-sustaining at the end of five years.<br />

Impact AES-2: Project<br />

construction could alter the site's<br />

appearance and long-term visual<br />

effects.<br />

Design /<br />

Construction<br />

Design Engineer /<br />

Construction<br />

Inspection<br />

Design Project Manager/<br />

EBMUD Construction<br />

Inspector / EBMUD<br />

Maintenance<br />

Completed by<br />

Date<br />

Completed by<br />

Date<br />

NA<br />

AIR QUALITY<br />

Mitigation Measure AtR-1: The BAAQMD "Basic Construction Mitigation Measures"<br />

will be incorporated by EBMUD into the contract specifications;<br />

• All exposed surfaces (e.g., parking areas, staging areas, soil piles, graded areas, and<br />

unpaved access roads) would be rocked and/or watered or soil stabilizers (nontoxic)<br />

would be applied as necessitated by soil and air conditions.<br />

• All land clearing, grubbing, scraping, excavation, land leveling, grading, cut and fill,<br />

and demolition activities will be effectively controlled for fugitive dust emissions<br />

utilizing application of water or presoaking.<br />

• Ail haul trucks transporting soil, sand, or other loose material off-site would be covered<br />

or require all trucks to maintain at least two feet of freeboard.<br />

• All visible mud or dirt tracked-out onto adjacent public roads would be removed using<br />

wet power vacuum street sweepers at least once per day. The use of dry power<br />

sweeping is prohibited.<br />

« All vehicle speeds on unpaved roads would be limited to 15 mph.<br />

• Idling times would be minimized either by shutting equipment off when not in use or<br />

reducing the maximum idling time to 5 minutes (as required by the California airborne<br />

toxics control measure Title 13. Section 2485 of California Code of Regulations<br />

ICCRJ).<br />

• AH construction equipment would be maintained and properly tuned, in accordance<br />

with manufacturer's specifications. All equipment would be checked by a certified<br />

mechanic and determined to be running in proper condition prior to operation.<br />

Impact AIR-1: Construction<br />

activities would generate exhaust<br />

emissions from vehicles/equipment<br />

and fugitive dust particles that<br />

could affect air quality.<br />

Construction<br />

EBMUD contractor<br />

EBMUD Construction<br />

Inspector<br />

Completed by<br />

Date<br />

Completed by<br />

Date<br />

NA