Findings: The project would result in maximum daily emissions levels that are below<br />
BAAQMD thresholds. Therefore, the project's impact related to construction-period<br />
criteria pollutant emissions is Less than Significant. However, BAAQMD recommends<br />
implementation of construction mitigation measures to reduce construction-related<br />
emissions for all projects, regardless of the significance level of construction-period<br />
impacts. These measures are identified as Mitigation Measure AIR-1 in the MND and<br />
MMRP.<br />
Construction activities can also result in fugitive dust, which contributes to particulate<br />
matter levels. While construction-period dust emissions have been estimated, BAAQMD<br />
does not have a threshold of significance for fugitive dust impacts, but instead regards<br />
fugitive dust impacts to be mitigated if appropriate management practices are<br />
implemented. BAAQMD-recommended basic construction management practices are<br />
included in Mitigation Measure AIR-1.<br />
Consistent with BAAQMD recommendations, the fugitive dust emissions presented in<br />
the MMRP have been reduced by 53 percent to reflect implementation of the measures<br />
included in Mitigation Measure AIR-1 in the MND and MMRP.<br />
Facts in Support of Findings: Measure AIR-1 incorporating the BAAQMD "Basic<br />
Construction Mitigation Measures" is hereby incorporated and imposed and shall be<br />
monitored in compliance with the MMRP. Because EBMUD has agreed to this<br />
mitigation, any air quality impacts have been avoided or will be reduced to a Less than<br />
Significant level.<br />
As a result of these project circumstances, and by employing this mitigation measure, the<br />
Project will have Less than Significant impacts to Air Quality resources.<br />
C. Biological Resources<br />
Impact: Less Than Significant with Mitigation Incorporated<br />
Findings: The Project site is within a developed urban area, and based on the archival<br />
research and field surveys undertaken by EBMUD it is unlikely that special status species<br />
occur on the Project site or that project construction and operation would interfere<br />
substantially with the movement of any resident or migratory fish or wildlife species or<br />
with established native resident or migratory corridors. Furthermore, potential impacts to<br />
candidate, sensitive, or special status species associated with the Project would be Less<br />
than Significant with implementation of the survey measures in Mitigation Measure<br />
BIO-1 identified in the MND and MMRP and employment of avoidance and mitigation<br />
measures to limit impacts as necessary.<br />
Approximately five to ten trees will be removed at the 39 th Avenue Reservoir site in order<br />
to replace the existing inlet/outlet pipeline. All other trees at the site will be preserved.<br />
The proposed tree removals are necessary to the project and will allow EBMUD to<br />
; maintain water service to the community and will not result in significant impacts