<strong>BANYULE</strong> <strong>COUNCIL</strong><br />

<strong>Guidelines</strong> <strong>for</strong> <strong>the</strong> <strong>Civil</strong> <strong>Infrastructure</strong> <strong>Works</strong> associated<br />

with<br />

Residential, Commercial and Industrial Developments<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 1 of 32: Infovision Ref Last Amended: 14/07/2007


Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 2 of 32: Infovision Ref Last Amended: 14/07/2007


Table of Contents<br />

1 INTRODUCTION 4<br />

1.1 Scope 4<br />

2 ROAD CONSTRUCTION 5<br />

2.1 Road Reserve Widths 5<br />

2.2 Pavement Widths 5<br />

2.3 Pavement Depths 5<br />

2.4 Longitudinal Grading 5<br />

2.5 Horizontal Alignment 6<br />

2.6 Pavement Cross Falls 6<br />

2.7 Kerb and Channel 6<br />

2.8 Footpaths 6<br />

2.9 Rights of Way 7<br />

2.10 Street Lighting 7<br />

2.11 Boundary Fences 7<br />

3 VEHICLE CROSSINGS 8<br />

3.1 Location 8<br />

3.2 Additional Crossing 8<br />

3.3 Standard Crossings 8<br />

3.4 Commercial and Industrial Crossings 8<br />

3.5 Asphalt Crossing Specifications 8<br />

3.6 Access to Rights of Way 8<br />

4 TRAFFIC MANAGEMENT 9<br />

5 DRAINAGE 10<br />

5.1 Drainage Design 10<br />

5.2 Internal Drainage 10<br />

5.3 Detention Systems 11<br />

5.4 Construction Detail 11<br />

5.5 Ownership of Drainage 12<br />

6 INTERNAL PAVING 13<br />

7 PLANS AND SPECIFICATIONS 14<br />

7.1 Plans General 14<br />

7.2 Layout Plans 14<br />

7.3 Longitudinal Sections 15<br />

7.4 Cross Sections 16<br />

7.5 Drainage Plan 16<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 3 of 32: Infovision Ref Last Amended: 14/07/2007


7.6 Services Plan 16<br />

8 ADMINISTRATION 17<br />

8.1 Plans to be Submitted <strong>for</strong> Approval 17<br />

8.2 Memorandum of Consent <strong>for</strong> <strong>Works</strong> 17<br />

8.3 Temporary Bench Marks 17<br />

8.4 As Constructed Plans 17<br />

8.5 Certified Fill Plans 17<br />

8.6 Inspections 17<br />

8.7 Maintenance Period 18<br />

8.8 Fur<strong>the</strong>r In<strong>for</strong>mation 18<br />

8.9 Notification of Affected Parties 18<br />

8.10 Standard Conditions of Approval 18<br />

8.11 Fees 18<br />

9 APPENDIX A – CONSTRUCTION REQUIREMENTS FOR VEHICLE CROSSINGS 19<br />

10 APPENDIX B – CONDITIONS OF APPROVAL 21<br />

11 APPENDIX C – STANDARD NOTES 23<br />

12 APPENDIX D – TURNING MOVEMENT TEMPLATE 25<br />

13 APPENDIX E – STANDARD DRAWINGS 26<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 4 of 32: Infovision Ref Last Amended: 14/07/2007


1 INTRODUCTION<br />

Many planning permits require developers to provide civil infrastructure as part of <strong>the</strong>ir<br />

development. To ensure that a satisfactory standard of development is maintained, endorsed<br />

plans <strong>for</strong> civil works are required and <strong>for</strong>m an integral part of <strong>the</strong> Planning Permit. These plans<br />

specify <strong>the</strong> civil works required to satisfy <strong>the</strong> development requirements of <strong>the</strong> permit.<br />

The following <strong>Guidelines</strong> have been prepared by <strong>the</strong> Engineering Services Department of<br />

Banyule Council to facilitate <strong>the</strong> preparation of civil works construction plans <strong>for</strong> new<br />

developments within Banyule.<br />

It is intended that <strong>the</strong>se <strong>Guidelines</strong> will provide <strong>the</strong> minimum requirement <strong>for</strong> in<strong>for</strong>mation to be<br />

included in plans to be lodged with Council <strong>for</strong> approval to comply with <strong>the</strong> planning approval<br />

process. After approval from <strong>the</strong> Engineering Services Department, <strong>the</strong> plans will be returned to<br />

<strong>the</strong> Planning Department to be endorsed as part of <strong>the</strong> Planning Permit <strong>for</strong> <strong>the</strong> development.<br />

The use of <strong>the</strong>se <strong>Guidelines</strong> is not intended to preclude contact with <strong>the</strong> Engineering Services<br />

Department where <strong>the</strong>re is uncertainty or if <strong>the</strong> required in<strong>for</strong>mation is not contained within<br />

<strong>the</strong>se <strong>Guidelines</strong>.<br />

1.1 Scope<br />

These <strong>Guidelines</strong> shall extend and apply to all residential, commercial and industrial<br />

developments within Banyule City Council as appropriate.<br />

Council reserves <strong>the</strong> right to alter this document at any time without notice.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 5 of 32: Infovision Ref Last Amended: 14/07/2007


2 ROAD CONSTRUCTION<br />

2.1 Road Reserve Widths<br />

Road reserve widths shall generally be in accordance with ResCode and Councils Road<br />

Management Plan, however <strong>the</strong> following represents typical requirements: -<br />

Access Place (Level 4)<br />

12m – 16m<br />

Access Street (Level 3)<br />

16m – 18m<br />

Collector Street (Level 2) 18m – 20.2m<br />

2.2 Pavement Widths<br />

The minimum requirements <strong>for</strong> road pavement widths are: -<br />

Access Place (0 < 300 vpd)<br />

7.6m between kerb inverts<br />

Access Street (0 < 1,000 vpd)<br />

7.6m between kerb inverts<br />

Access Street (1,000 < 2,000 vpd) 8.6m between kerb inverts.<br />

Minor Collector Street (2,000 < 5,000 vpd) 8.6m – 10.2m between kerb inverts<br />

Major Collector Street (5,000 < 10,000vpd) 10.2m minimum between kerb inverts<br />

A wider road pavement to that suggested above must be provided to allow <strong>for</strong> on-street<br />

parking, particularly where <strong>the</strong>re may be a high demand <strong>for</strong> on street parking (e.g. near schools,<br />

shops, future developments etc.) or, if Council considers that new pavement widths should<br />

match <strong>the</strong> width of existing pavements leading to <strong>the</strong> site.<br />

Pavement widths at intersections are to be increased to allow <strong>the</strong> movements of a design<br />

Service Vehicle (SV) without encroaching <strong>the</strong> opposite side of <strong>the</strong> road or overhanging kerbs or<br />

islands.<br />

Court bowls are to have a minimum radius of 10.5m or 13.1m where parking is required.<br />

Hammerhead treatments are to comply with MFB Planning <strong>Guidelines</strong> <strong>for</strong> Emergency Vehicle<br />

Access and have vehicle crossings placed so as to preclude parking in <strong>the</strong> manoeuvre areas. The<br />

hammerhead treatment is to be widened if on-street parking is to be permitted in <strong>the</strong><br />

hammerhead.<br />

One parking space per allotment is to be provided on-street unless a higher demand <strong>for</strong> parking<br />

is determined by Council.<br />

Nature strip widths must allow <strong>for</strong> provision of adequate sight distance from intersections.<br />

2.3 Pavement Depths<br />

Developers are to undertake soil investigations and design road pavements to approved ESA’s<br />

accordingly. However <strong>the</strong> minimum pavement depth shall be 260mm and be comprised as<br />

follows: -<br />

Wearing Course<br />

25mm depth of type L or N 10mm asphalt.<br />

Base Course<br />

35mm depth of type N 14mm asphalt.<br />

Crushed Rock Base<br />

100mm depth of class 1 - 20mm wet mixed FCR.<br />

Crushed Rock Sub-base<br />

100mm depth of class 2 - 20mm wet mixed F.C.R<br />

Asphalt types must comply with VicRoads Standard Specification Section 407 – Hot Mix Asphalt.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 6 of 32: Infovision Ref Last Amended: 14/07/2007


2.4 Longitudinal Grading<br />

Roads should be designed to suit existing building lines. Kerbs may be graded individually but<br />

within <strong>the</strong> limits determined by <strong>the</strong> rate of change of cross fall. Grading must take into account<br />

existing flood levels.<br />

Generally, <strong>the</strong> minimum longitudinal grade shall be 0.4%.<br />

The following are <strong>the</strong> maximum grades to be used: -<br />

Access Place 12%<br />

Access Street 8% desirable (absolute max 11%)<br />

Collector Street 6–7% desirable (absolute max 8%)<br />

The maximum desirable longitudinal grade shall be 12.0%, but in exceptional circumstances<br />

may be increased <strong>for</strong> short lengths with Council approval.<br />

Vertical curves are required where grade change is in excess of: -<br />

0.5% where grades signs are <strong>the</strong> same, and<br />

1 % or greater where grade signs are different.<br />

Minimum length VC <strong>for</strong> change in grade greater than 1% is 15m.<br />

Longitudinal grading must be extended along <strong>the</strong> centre line of <strong>the</strong> existing road to adequately<br />

display <strong>the</strong> transition from existing to new pavement.<br />

Sight distance provision along subdivision roads shall be based on a design speed of 65km/h in<br />

accordance with current VicRoads practice.<br />

2.5 Horizontal Alignment<br />

Roads should be designed to comply with “AUSTROADS: Design Vehicles and Turning Path<br />

Templates”. Movements at court bowls and intersections must cater <strong>for</strong> Councils 9.8m recycling<br />

trucks. (<strong>for</strong> Turning Movement Template see Appendix D). T-head style courts are favoured <strong>for</strong><br />

this purpose. Reference should also be made to VicRoads ‘Trucks on Roads’ Design Guide and<br />

Metropolitan Fire Brigades Development <strong>Guidelines</strong>.<br />

2.6 Pavement Cross Falls<br />

Road pavements are to be designed, wherever possible, with a central crown and cross fall of<br />

between 1 in 30 and 1 in 36. The absolute minimum is 1 in 50.<br />

In areas where <strong>the</strong> topography suggests that kerbs should be constructed at different levels, a<br />

maximum cross fall of 1 in 25 is permitted.<br />

The maximum rate of change of cross fall shall be 1% per 10m.<br />

Subject to Council approval an offset crown may be used in areas where <strong>the</strong> road cross fall<br />

across <strong>the</strong> road reserve is considered steep. The minimum offset of <strong>the</strong> crown from <strong>the</strong> lip of<br />

kerb shall be 1.5 metres.<br />

Superelevation is generally not required on distributor, collector or access streets, however<br />

where site conditions indicate that it is required <strong>the</strong> maximum cross fall shall be 1 in 15.<br />

Care shall be taken to avoid excessive rates of change of cross fall or excessive rates of change<br />

of footpath level above top of kerb.<br />

Footpath cross falls shall be between 1 in 30 and 1 in 50.<br />

Reverse fall footpaths (i.e. falling toward allotments) will not be approved, unless absolutely<br />

necessary.<br />

Batter slope to be 1 in 4.0 max. in cut, and 1 in 5 max. in fill.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 7 of 32: Infovision Ref Last Amended: 14/07/2007


Vehicular access shall be provided to all allotments as per Australian Standard AS 2890.1:2004<br />

2.7 Kerb and Channel<br />

Generally use 600mm Barrier Kerb (Standard Drawing B001 – B2). The use of mountable kerbs<br />

is not permitted unless Council considers that <strong>the</strong> new kerb should match that of existing<br />

pavements leading to <strong>the</strong> site.<br />

2.8 Footpaths<br />

Footpath shall be provided as follows: -<br />

Access Place<br />

1.5m wide footpath on one side of road.<br />

Access Street<br />

1.5m wide footpaths on both sides of road.<br />

Collector Street<br />

1.5m wide footpath on both sides of road.<br />

Shared bicycle/pedestrian path 3m wide.<br />

Industrial Areas 1.5m wide x 150mm thick 25MPa concrete<br />

rein<strong>for</strong>ced with F72 mesh<br />

Footpaths must fall away from allotments unless approved o<strong>the</strong>rwise.<br />

Footpaths, o<strong>the</strong>r than those in industrial areas, are to be constructed of 100mm minimum<br />

thickness 25 MPa concrete on 50mm compacted depth of Class 2 FCR bedding.<br />

Footpaths in industrial areas, are to be constructed of 100mm minimum thickness 25 MPa<br />

concrete rein<strong>for</strong>ced with SL72 mesh, on 50mm compacted depth of Class 2 FCR bedding.<br />

All kerb ramps are to comply with <strong>the</strong> Disability Discrimination Act 1992, Australian Standard<br />

AS1428.4 and VicRoads Road Design Note 9-15 “<strong>Guidelines</strong> <strong>for</strong> <strong>the</strong> placement of Tactile Ground<br />

Surface Indicators”. Kerb ramps are to be flush with <strong>the</strong> road surface.<br />

Construction joints are to be spaced not greater than 900mm apart with expansion joints spaced<br />

not greater than 9m apart.<br />

2.9 Rights of Way<br />

Where <strong>the</strong> construction of a Rights of Way is required as part of a development <strong>the</strong> pavement is<br />

to be 200mm thick 25 MPa rein<strong>for</strong>ced concrete rein<strong>for</strong>ced with F72 mesh laid on a 50mm<br />

compacted depth of Class 2 FCR bedding, or a Council approved asphalt pavement with a depth<br />

as per clause 2.3 is to be used.<br />

Underground drainage, as per section 5, with pits to capture surface runoff shall be provided.<br />

2.10 Street Lighting<br />

Street lighting including supply is to be installed within <strong>the</strong> subdivision according plans, designed<br />

in accordance with <strong>the</strong> relevant standards and approved by Council<br />

Clearance to lighting poles from back of kerb and vehicle crossings must accord with VicRoads<br />

recommended clear zone widths. The use of Impact Absorbing frangible poles may be used<br />

where clear zone widths cannot be achieved.<br />

The use of non-standard lighting within subdivisions throughout <strong>the</strong> City of Banyule may be<br />

considered, subject to: -<br />

Pole type, fitting, and colour being approved by Council. Council’s preference is Heritage<br />

Green Bourke Hill Series poles.<br />

Lighting must be in accordance with VESI Non Standard Public Lighting <strong>Guidelines</strong>.<br />

The initial cost of poles and fittings <strong>for</strong> installation within <strong>the</strong> estate is to be borne by <strong>the</strong><br />

developer.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 8 of 32: Infovision Ref Last Amended: 14/07/2007


The relevant power company is to install <strong>the</strong> lanterns and poles complete with wiring.<br />

Light fittings are to be approved VESI standard. The relevant power company is to<br />

agree to maintain <strong>the</strong> light pole and fittings under <strong>the</strong> normal maintenance agreement<br />

with Council. Council will accept liability <strong>for</strong> <strong>the</strong> annual lighting tariff at a level similar to<br />

local power authority standard lights.<br />

Prior to <strong>the</strong> issue of <strong>the</strong> Statement of Compliance, <strong>the</strong> developer shall lodge with Council<br />

a maintenance contribution equivalent to <strong>the</strong> current cost of supplying one pole and one<br />

lantern, or 10% of <strong>the</strong> cost of supplying <strong>the</strong> number of poles and lanterns within <strong>the</strong><br />

subdivision, which ever is <strong>the</strong> greater.<br />

2.11 Boundary Fences<br />

Permanent fences must be constructed along all boundaries at extents of subdivision.<br />

Council may require that permanent fences be constructed along all allotment boundaries within<br />

<strong>the</strong> subdivision to ensure building activities are confined to individual allotments.<br />

Alternatively, payment of a non-refundable contribution <strong>for</strong> on-going infrastructure repairs<br />

during building activities within allotments may be considered.<br />

3 VEHICLE CROSSINGS<br />

3.1 Location<br />

Vehicle crossings <strong>for</strong> each allotment must be constructed as part of <strong>the</strong> subdivisional works.<br />

Crossings are to be located clear of easements.<br />

On corner lots, <strong>the</strong> crossing must be a minimum of 10.0m from <strong>the</strong> extension of <strong>the</strong> kerb line of<br />

<strong>the</strong> intersecting street unless o<strong>the</strong>rwise approved by Council’s Engineering Department.<br />

If <strong>the</strong> proposed crossing location is obstructed by street trees, drainage pits, electricity supply<br />

poles, public authority valves, pits or manholes or any o<strong>the</strong>r obstruction, <strong>the</strong>n arrangements must<br />

be made with <strong>the</strong> appropriate Authority <strong>for</strong> <strong>the</strong> relocation of such obstructions prior to applying to<br />

Council <strong>for</strong> <strong>the</strong> issue of a Memorandum of Consent <strong>for</strong> Work (MOC).<br />

3.2 Additional Crossing<br />

Separate approval is required from Council’s Engineering Department <strong>for</strong> <strong>the</strong> construction of an<br />

additional vehicle crossing. On heavily trafficked roads or in streets where <strong>the</strong>re is a shortage of<br />

on-street parking Council may not approve <strong>the</strong> construction of additional vehicle crossings.<br />

3.3 Standard Crossings<br />

The crossing shall consist of 150mm thick concrete having a 25 MPa 28 day test value, rein<strong>for</strong>ced<br />

with F72 mesh placed on a 50mm compacted thickness of fine crushed rock. The total excavation<br />

depth required is 200mm.<br />

The crossing shall extend from kerb to building line and shall comply in all aspects with Council's<br />

standard drawings. The minimum acceptable width is 3.0m and <strong>the</strong> maximum width is 7.60m.<br />

Where <strong>the</strong> maximum width at <strong>the</strong> building line is to exceed 7.60mm, written approval must be<br />

obtained from <strong>the</strong> Construction Department.<br />

3.4 Commercial and Industrial Crossings<br />

Commercial and Industrial crossings shall consist of 200mm thick concrete having a 25 MPa 28 day<br />

test value, rein<strong>for</strong>ced with F72 placed on a 50mm compacted thickness of fine crushed rock. The<br />

total excavation depth required is 250m.<br />

3.5 Asphalt Crossing Specifications<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 9 of 32: Infovision Ref Last Amended: 14/07/2007


The asphalt is to be 35mm depth or greater of type L or N 10mm asphalt and shall be laid on a<br />

base of 200mm minimum thickness of compacted crushed rock. The total excavation depth<br />

required is 235mm.<br />

3.6 Access to Rights of Way<br />

Where <strong>the</strong> vehicle crossing provides access to a Rights of Way <strong>the</strong>n <strong>the</strong> construction of <strong>the</strong><br />

crossing shall consist of 200mm thick concrete having a 25 MPa 28 day test value rein<strong>for</strong>ced<br />

with F72 mesh placed on a 50mm compacted thickness of fine crushed rock. The total<br />

excavation depth required is 250mm.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 10 of 32: Infovision Ref Last Amended: 14/07/2007


4 TRAFFIC MANAGEMENT<br />

Design of subdivisional roads must minimise <strong>the</strong> potential <strong>for</strong> speeding and maximise amenity<br />

<strong>for</strong> residents. Traffic Management devices (e.g. roundabouts; traffic islands; raised pavements;<br />

parking, regulatory or warning signs) will be required to control vehicle speeds and traffic<br />

movements within <strong>the</strong> subdivision. Traffic management devices may also be required in streets<br />

external to <strong>the</strong> subdivision.<br />

Reference should also be made to VicRoads ‘Trucks on Roads’ Design Guide.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 11 of 32: Infovision Ref Last Amended: 14/07/2007


5 DRAINAGE<br />

5.1 Drainage Design<br />

Council supports <strong>the</strong> principles of Water Sensitive Urban Design and requires <strong>the</strong> drainage<br />

design to incorporate <strong>the</strong>se principles wherever practicable.<br />

A suitably qualified Engineer shall design all outfall and easement drainage.<br />

Council requires <strong>the</strong> discharge from <strong>the</strong> site to be limited to that of or <strong>the</strong> equivalent to <strong>the</strong> predevelopment<br />

conditions. The use of retarding basins (large subdivisions only) and/or on site<br />

detention systems will be required to restrict peak stormwater discharge from <strong>the</strong> site.<br />

Council’s Engineering Department will nominate a Point of Discharge <strong>for</strong> stormwater drainage<br />

generated by <strong>the</strong> development. Generally, this point of discharge shall be <strong>the</strong> nearest Council<br />

underground drain, with sufficient capacity to accept <strong>the</strong> allowable stormwater discharge<br />

generated by <strong>the</strong> development. This may require <strong>the</strong> construction (at <strong>the</strong> developers cost) of an<br />

outfall drain through an easement or drainage reserve or along <strong>the</strong> road reserve. For dual<br />

occupancies, if <strong>the</strong> length of this outfall is greater than 150m, o<strong>the</strong>r options may be considered.<br />

The design <strong>for</strong> storm water drains shall be based on not less than a 1 in 10 year ARI (Average<br />

Recurrence Interval) storm event. Where <strong>the</strong> property is in a low point situation <strong>the</strong> design shall<br />

be based on a storm event with an ARI of not less than 1 in 20. Allowance <strong>for</strong> overland flows<br />

(flood ways) are to be incorporated in <strong>the</strong> design and are to cater <strong>for</strong> a 1 in 100 year ARI storm<br />

event.<br />

External catchments must be considered in <strong>the</strong> design, and if applicable, additional underground<br />

storm water drains or open catch drains on <strong>the</strong> high side of <strong>the</strong> subdivision must be installed as<br />

part of <strong>the</strong> subdivision works to ensure new allotments on <strong>the</strong> subdivision are not adversely<br />

affected by stormwater runoff/discharge onto <strong>the</strong> site from existing properties.<br />

The minimum coefficient of run off shall be: -<br />

0.30 <strong>for</strong> grassed/landscaped (pervious) areas<br />

0.90 <strong>for</strong> road pavement and o<strong>the</strong>r paved (impervious) areas<br />

0.65 <strong>for</strong> residential allotments<br />

0.85 <strong>for</strong> commercial and industrial areas<br />

Hydraulic design shall be based on Manning’s <strong>for</strong>mulae and shall allow <strong>for</strong> all hydraulic losses,<br />

e.g. velocity head, curve losses, pit losses etc.<br />

The drainage system shall be self-cleansing.<br />

The pipe roughness coefficient shall be 0.013 <strong>for</strong> R.C. pipe, and 0.011 <strong>for</strong> UPVC or FRC pipes.<br />

The initial time of concentration to be adopted shall not exceed 6.0 minutes.<br />

Velocity in pipes should be between 1 and 6 metres per second.<br />

The maximum number of lots to drain to a 150mm diameter pipe shall be 3 (where pipe<br />

capacity exceeds proposed discharge).<br />

The minimum pipe diameter shall be 300mm diameter under roadways, 225mm longitudinal to<br />

road, and 150mm within easements.<br />

5.2 Internal Drainage<br />

All stormwater from <strong>the</strong> site, including run off from paved areas, is to be directed to <strong>the</strong><br />

nominated point of discharge.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 12 of 32: Infovision Ref Last Amended: 14/07/2007


Generally, unless o<strong>the</strong>rwise required, only one outlet from <strong>the</strong> lowest point of each property will<br />

be permitted.<br />

Plans are to show <strong>the</strong> means of drainage of existing dwelling and/or outbuildings as applicable.<br />

A grated entry pit and underground drainage outlet at all low points shall be provided in<br />

individual yards.<br />

Trench grates shall be a minimum of 150mm wide x 225mm deep and have transverse bar<br />

‘Gatic’ grates or an approved alternative.<br />

The minimum size pipe required <strong>for</strong> drains collecting surface water through gratings, from paved<br />

or landscaped areas is 150mm diameter. The minimum size pipe required beneath trafficked<br />

areas is 150mm diameter.<br />

Pits are to be provided along pipes at all changes of direction and all changes in grade. Pit lids<br />

must be able to be opened easily with no proprietary tools required.<br />

The type of construction of all drainage pits is to be pecified. The minimum dimensions of pits<br />

within allotments is to be 450mm x 450mm. These may be reduced to 300mm x 300mm in<br />

minor landscaped or paved areas where <strong>the</strong> contributing area is less than 25m 2 .<br />

Minimum cover requirements are: -<br />

For non-trafficked areas<br />

90mm, 100mm and 150mm diam pipes 225mm clear cover<br />

225mm diam pipes and larger 300mm clear cover<br />

For trafficked areas<br />

450mm clear cover<br />

For easements and nature strips<br />

For road reserves<br />

5.3 Detention Systems<br />

450mm clear cover<br />

600mm clear cover<br />

Where an ‘On-Site Detention System’ is required, <strong>the</strong> system must not be sited on land to be<br />

maintained by Council. The system must be designed in accordance with <strong>the</strong> following<br />

requirements and <strong>the</strong> computations of <strong>the</strong> proposed system must be submitted <strong>for</strong> approval.<br />

A.R.I. = 10 years (<strong>for</strong> discharge control and storage)<br />

C (pre-dev) = 0.35 or as determined (Pervious – 0.3 Impervious – 0.9)<br />

C (post-dev) = as determined (Pervious – 0.3 Impervious – 0.9)<br />

An ‘orifice plate’ type control pit, SVC Multi-Cell device, or o<strong>the</strong>r approved flow restriction device<br />

is to be used. Where <strong>the</strong> control orifice is less than 90mm in diameter, an approved mesh<br />

screen must be installed to prevent blockages. The minimum orifice size is to be 63mm.<br />

Overflow from <strong>the</strong> flow restriction device must be taken into account when designing <strong>the</strong> outlet<br />

pipe, t o allow <strong>for</strong> blockages etc.<br />

5.4 Construction Detail<br />

The minimum life expectancy <strong>for</strong> all materials used shall not be less than 100 years.<br />

Where modified type semi-mountable kerb and channel is used all pits shall, where practicable,<br />

be side entry type and incorporate precast lintels.<br />

Unless pipe is continued through to <strong>for</strong>m pit invert, all pits should have at least 50mm fall<br />

through <strong>the</strong>m <strong>for</strong> dry wea<strong>the</strong>r flow.<br />

Straight pipes laid in an arc will not be permitted unless <strong>the</strong> pipe diameter exceeds 600mm.<br />

Minimum radius of arc to be not less than 10 times <strong>the</strong> diameter.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 13 of 32: Infovision Ref Last Amended: 14/07/2007


Pipe diameter cannot be reduced downstream.<br />

All pits shall con<strong>for</strong>m in all respects to Banyule City Council standard drawings, and are to be<br />

specified in <strong>the</strong> Pit Schedule.<br />

Pits should not be located on kerb returns and care should be taken to locate pits clear of<br />

driveways.<br />

Changes of pipe direction at pits are to be no greater than 45 degrees wherever possible and<br />

never greater than 90 degrees.<br />

A house drain connection is to be provided <strong>for</strong> each lot in accordance with Banyule City Council<br />

standard drawings.<br />

Rubber ring jointed pipes are to be used where <strong>the</strong> pipe diameter is smaller or equal to 375mm<br />

and <strong>for</strong> all pipes in fill areas.<br />

All PVC pipes shall be sewer quality.<br />

Only rein<strong>for</strong>ced concrete pipes are to be used under roadways.<br />

Anchor blocks are to be installed as per Standard Drawing B042, where <strong>the</strong> pipe grade is<br />

steeper than 1 in 10.<br />

Pipes should be well aligned vertically.<br />

House drains shall not be connected directly into a drain smaller than 225mm diameter unless a<br />

pit is provided.<br />

Step irons are to be used where depth of pits exceeded 1m.<br />

Drainage pipes are not permitted to be constructed directly in line with and underneath <strong>the</strong> kerb<br />

and channel.<br />

Drainage pipes should be located outside <strong>the</strong> road pavement.<br />

Agricultural drains to be provided under all kerbing, as per Standard Drawing B041.<br />

Minimum clear cover requirements: -<br />

450mm in nature strips and easements<br />

600mm under road pavement<br />

Kerb and Channel deflectors are to be used where grades of kerb exceeds 1 in 6.<br />

5.5 Ownership of Drainage<br />

Subject to agreement by Council drainage constructed within easements or road reserves, will<br />

be handed over to Council <strong>for</strong> future care and maintenance and control after <strong>the</strong> expiry of <strong>the</strong><br />

contractors maintenance period.<br />

Drainage constructed outside an easement or within private/common property shall remain <strong>the</strong><br />

property of <strong>the</strong> owner/body corporate and <strong>the</strong> responsibility <strong>for</strong> <strong>the</strong> future care and maintenance<br />

of <strong>the</strong> drain shall rest with <strong>the</strong> owner/body corporate.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 14 of 32: Infovision Ref Last Amended: 14/07/2007


6 INTERNAL PAVING<br />

Show <strong>the</strong> extent of all existing and/or proposed internal driveways and means of drainage<br />

<strong>the</strong>reof on <strong>the</strong> plans.<br />

Driveways shall be aligned so as to provide effective access to carports and/or garages.<br />

Minimum internal radius <strong>for</strong> domestic vehicles is 3.0m.<br />

Council recommends that driveways be constructed of ei<strong>the</strong>r concrete, asphalt, brick paving or<br />

similar sealed pavement.<br />

Pavement depth shall be in accordance with relevant standards and manufacturer’s guidelines<br />

however <strong>the</strong> minimum depth shall be as follows: -<br />

‣ For concrete driveways<br />

Up to 2 dwellings<br />

100mm rein<strong>for</strong>ced with F72 mesh<br />

From 3 to 6 dwellings 125mm rein<strong>for</strong>ced with F72 mesh<br />

For 7 and over dwellings 150mm rein<strong>for</strong>ced with F72 mesh<br />

All concrete driveways are to be constructed of concrete having a 25 MPa 28 day test<br />

value placed on a 50mm compacted depth of class 2 FCR bedding.<br />

‣ For asphalt driveways<br />

Up to 2 dwellings<br />

150mm class 2 FCR with 35mm Asphalt wearing Course<br />

From 3 to 6 dwellings 175mm class 2 FCR with 35mm Asphalt wearing Course<br />

For 7 and over dwellings 200mm class 2 FCR with 35mm Asphalt wearing Course<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 15 of 32: Infovision Ref Last Amended: 14/07/2007


7 PLANS AND SPECIFICATIONS<br />

7.1 Plans General<br />

Council’s standard detail drawings <strong>for</strong> road and drainage works shall be used.<br />

Sheet size shall be A1.<br />

Council’s Standard Notes (see appendix C) are to be incorporated in <strong>the</strong> plans.<br />

Scales may be varied to suit <strong>the</strong> sheet size but should generally con<strong>for</strong>m to <strong>the</strong> following: -<br />

Layout Plan<br />

1:1000 on large areas<br />

1:500 on small areas<br />

1:100<br />

Longitudinal Section 1:500 horizontally & 1:50 vertically<br />

Cross Sections 1:100 horizontally & 1:25 vertically<br />

Intersection Details 1:100 to 1:200<br />

Drainage<br />

1:500 horizontally & 1:50 vertically<br />

1:100 horizontally & 1: 50 vertically<br />

7.2 Layout Plans<br />

The layout plan shall show <strong>the</strong> following: -<br />

Entire subdivision (where practicable) on one sheet, orientated with North to <strong>the</strong> top of<br />

<strong>the</strong> sheet.<br />

Streets/roads to be constructed.<br />

Lots facing on to such streets/roads.<br />

Numbers, dimensions and bearings on all lots.<br />

Existing and proposed levels (to AHD) on allotment corners, and at ridges, gullies, etc.<br />

Easements and <strong>the</strong>ir descriptions and widths.<br />

Drainage in streets and easements.<br />

Drainage pits and <strong>the</strong>ir numbers.<br />

Offset to drain centre line from building line.<br />

House drains under nature strips and property inlets in easements – <strong>the</strong>se should be<br />

located to control drainage from all parts of allotment.<br />

Engineering Services<br />

Bench marks and reduced levels (All levels to AHD).<br />

The limits of extensive filling with contour lines. These should be cross-hatched <strong>for</strong><br />

clarity. Existing and proposed final levels along areas of fill must be shown (where depth<br />

of fill is greater than 300mm).<br />

Set out details of traverse lines.<br />

Extent and details of flood levels if applicable.<br />

Trees to be retained/removed (in accordance with Planning Permit Requirements).<br />

The full extent of work to be done. This will include kerb and channel, pavements,<br />

footpaths, driveways, street drainage and pits, signage and line marking etc.<br />

Chainage at all tangent points, pits, side boundaries and positions where cross sections<br />

are given.<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 16 of 32: Infovision Ref Last Amended: 14/07/2007


Engineering Services<br />

Minimum kerb radius of 8m should be used <strong>for</strong> all curves and radials.<br />

Kerb levels at tangent, quarter and mid points.<br />

Grades of existing kerbing in adjoining streets.<br />

Location and extent of retaining walls<br />

Spot levels on road and an indication of crown line. In certain cases it may be necessary<br />

to show contours (<strong>for</strong> intersections of proposed streets, and intersections of proposed<br />

streets with existing streets).<br />

Kerb ramps<br />

Location of existing services, poles, etc.<br />

Levels at back of footpath and building line.<br />

Sufficient dimensions to fix all points and features.<br />

Traffic treatments where applicable.<br />

Location and type of all proposed signs and line marking<br />

7.3 Longitudinal Sections<br />

The longitudinal section shall be a continuous plot, set out as follows: -<br />

Datum RL<br />

North (or West) Building Line<br />

North (or West) Proposed Top of Kerb<br />

Centreline Existing<br />

Centreline Proposed<br />

South (or East) Proposed Top of Kerb<br />

South (or East) Building Line<br />

Chainage in Metres<br />

The longitudinal sectional shall show: -<br />

All grade lines<br />

All vertical curve details<br />

The location, level and surface of existing driveways<br />

The existing conditions <strong>for</strong> a minimum distance of 80m at ei<strong>the</strong>r end of <strong>the</strong> proposed<br />

construction<br />

Location of existing services<br />

Chainage and design kerb levels shall be shown at: -<br />

All tangent points<br />

All cross sections<br />

All changes or grade<br />

All low points and crests<br />

20m intervals on straight grades<br />

5m maximum intervals on vertical curves<br />

At beginning and end of vertical curves.<br />

No drainage longitudinal section shall be superimposed on <strong>the</strong> roadway plot.<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 17 of 32: Infovision Ref Last Amended: 14/07/2007


It is desirable that <strong>the</strong> longitudinal section and <strong>the</strong> corresponding plan be drawn on one sheet<br />

<strong>for</strong> ease of supervision.<br />

7.4 Cross Sections<br />

Plans of cross sections should show <strong>the</strong> following: -<br />

Chainage<br />

Offset and level at back and front of footpath(s)<br />

Offset and level of top of each kerb<br />

Offset and level of crown line<br />

Existing natural surface levels at each building line.<br />

Plot of existing surface and proposed design profile<br />

Offset and level of batters into allotments where applicable.<br />

The typical cross sections should show <strong>the</strong> composition and thickness of <strong>the</strong> road pavement,<br />

offset and level of all services, and sub grade (which must extend 150mm past back of kerb).<br />

7.5 Drainage Plans<br />

A copy of drainage computations and catchment plan including any catchment area extending<br />

beyond <strong>the</strong> site shall be submitted, toge<strong>the</strong>r with longitudinal sections <strong>for</strong> all drains which<br />

should show: -<br />

Pipe size and type<br />

Invert level of pipe<br />

Pipe Grade<br />

Chainage<br />

Levels of any existing or proposed underground services<br />

Natural surface levels and finished surface levels<br />

Pit locations and type, pit numbers and chainage of pits<br />

Pit Schedule.<br />

Allotment dimensions.<br />

All allotments along alignment of drain.<br />

Existing and proposed buildings.<br />

Streets.<br />

Existing drainage.<br />

Existing services (water, gas, sewer, telephone, poles, etc).<br />

Existing driveway crossings.<br />

Existing features such as kerb and channel, car parking, footpath, trees, etc.<br />

Stormwater flow through pipes (actual and capacity) and flow velocity.<br />

All levels shall be to A.H.D.<br />

Pavement levels with cross fall shown.<br />

7.6 Services Plan<br />

The Service Plan should show locations and extent of all services including depths to AHD and<br />

offsets from building line.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 18 of 32: Infovision Ref Last Amended: 14/07/2007


Scale to be not less than 1:500.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 19 of 32: Infovision Ref Last Amended: 14/07/2007


8 ADMINISTRATION<br />

8.1 Plans to be Submitted <strong>for</strong> Approval<br />

For all developments five (5) copies of <strong>the</strong> plan(s) are to be submitted to Council <strong>for</strong> approval.<br />

A digital copy in AutoCAD .dwg or .dxf <strong>for</strong>mat is also required. This digital copy, in <strong>the</strong> required<br />

<strong>for</strong>mat, must be submitted be<strong>for</strong>e Council will approve <strong>the</strong> plans.<br />

Council is able to convert plans to digital <strong>for</strong>mat, however, applicants wishing to use this service<br />

will be charged $50 per sheet.<br />

For subdivisions with road and drainage works, a <strong>Works</strong> Specification and Cost Schedule <strong>for</strong><br />

road and drainage works is to be provided when final civil works plans are lodged <strong>for</strong> approval.<br />

All works are to be carried out in accordance with <strong>the</strong> approved plans and specifications and no<br />

deviation to <strong>the</strong>se plans shall be made without <strong>the</strong> prior approval of <strong>the</strong> Engineering Services<br />

Department.<br />

8.2 Memorandum of Consent <strong>for</strong> <strong>Works</strong><br />

A Memorandum of Consent <strong>for</strong> <strong>Works</strong> (MOC) must be obtained be<strong>for</strong>e any works are carried out in<br />

a road reserve, reserve or easement. The cost of <strong>the</strong> consent is <strong>for</strong> supervision only. Consent will<br />

only be issued to a Contractor who has a $10 million current public liability insurance policy,<br />

provides Council with a satisfactory traffic management plan complying to Australian and<br />

VicRoads standards, and o<strong>the</strong>r documents as may be requested by Council as evidence of<br />

contractors experience in executing similar works.<br />

If, during construction, damage occurs to Council, Public Authority or private assets, <strong>the</strong> contractor<br />

will be responsible <strong>for</strong> <strong>the</strong> full reinstatement of such assets as directed by <strong>the</strong> Construction<br />

Supervisor.<br />

The MOC holder may be requested to lodge a bond <strong>for</strong> reinstatement of Council’s assets. The<br />

MOC holder is liable and will be charged <strong>for</strong> any additional costs in excess of <strong>the</strong> amount of<br />

bond being held in trust. Accordingly, if <strong>the</strong> MOC holder carries out reinstatement works in<br />

compliance with Council’s regulations, <strong>the</strong> bond will be refunded in full.<br />

8.3 Temporary Bench Marks<br />

A temporary benchmark (eg. spike in pole) shall be established in <strong>the</strong> vicinity of <strong>the</strong> proposed<br />

works and all levels <strong>for</strong> such works related to this T.B.M. All levels are to be to AHD.<br />

8.4 As Constructed Plans<br />

Upon completion of construction, a full set of transparencies and computer disk marked up with<br />

any as-constructed details, must be provided <strong>for</strong> permanent Council records.<br />

8.5 Certified Fill Plan<br />

A certified fill plan, which includes natural and final surface levels and maximum depth of fill at<br />

all relevant locations, must be provided where <strong>the</strong> depth of fill exceeds 300mm.<br />

8.6 Inspections<br />

The relevant Building Surveyor is responsible <strong>for</strong> all buildings, internal site works, paving and<br />

drainage within <strong>the</strong> property. An inspection certificate must be provided to Council’s<br />

Construction Department at completion of <strong>the</strong> works<br />

Inspections of all external site works (i.e. Construction of vehicle crossings, outfall drainage, on<br />

site detention systems and connection of internal drainage to Council’s drainage system within<br />

<strong>the</strong> road reserve or easements) must be carried out by Council’s Construction Section under a<br />

MOC.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 20 of 32: Infovision Ref Last Amended: 14/07/2007


Under no circumstances will an inspection be carried out without evidence of <strong>the</strong> relevant<br />

consent first having been obtained. A copy of <strong>the</strong> MOC should be kept and made available to <strong>the</strong><br />

inspector on request.<br />

It is important that Council’s inspection procedures be adhered to at all times. The relevant<br />

inspections must be carried out at <strong>the</strong> appropriate stages of <strong>the</strong> development. Failure to comply<br />

may result in delays in completion of <strong>the</strong> works and may ultimately affect <strong>the</strong> economic potential<br />

of <strong>the</strong> development.<br />

All inspections are to be booked through Customer Service on 9490 4222<br />

24-hour prior notice of <strong>the</strong> inspection must be given and inspection will be carried out between <strong>the</strong><br />

hours of 9:00am – 12:00 noon and 1:00pm – 3:00pm.<br />

8.7 Maintenance Period<br />

The Maintenance Period <strong>for</strong> <strong>the</strong> works shall be twelve (12) months.<br />

8.8 Fur<strong>the</strong>r In<strong>for</strong>mation<br />

Any queries should be directed to Banyule City Council’s Developments Engineer on <strong>the</strong> above<br />

phone numbers.<br />

8.9 Notification of Affected Parties<br />

If <strong>the</strong> design of <strong>the</strong> outfall drain necessitates utilising drainage easements on adjoining<br />

properties, <strong>the</strong>n letters of advice in<strong>for</strong>ming that works will be occurring and consent from <strong>the</strong><br />

adjoining property owners must be submitted with <strong>the</strong> drainage plan.<br />

If <strong>the</strong> design of <strong>the</strong> outfall drain necessitates utilising Council’s roads, right-of-ways or drainage<br />

reserves, <strong>the</strong> developer shall be required to give adjoining property owners at least two weeks<br />

written notice of his intention to construct <strong>the</strong> drain.<br />

8.10 Standard Conditions of Approval<br />

Approval <strong>for</strong> <strong>the</strong> construction of road works and outfall drainage is at all times subject to<br />

Council’s Standard Conditions of Approval, a copy of which is available on request.<br />

8.11 Fees<br />

‣ The following fees <strong>for</strong> subdivisional developments are payable prior to issue of <strong>the</strong><br />

Statement of Compliance: -<br />

Supervision fee<br />

2.5% of <strong>the</strong> cost of in ground works<br />

Memorandum of Consent <strong>for</strong> <strong>Works</strong> as determined<br />

Plan checking fee<br />

0.75% of <strong>the</strong> cost of in ground works<br />

Maintenance bond<br />

10% of <strong>the</strong> cost of in ground works<br />

Non Standard Lighting fee (if applicable) Refer Section 2 -10<br />

Street Nameplate(s)<br />

To be installed as part of works<br />

Street tree contribution<br />

To be confirmed with Council’s Planning<br />

Department<br />

Public open space contribution (and any o<strong>the</strong>r planning fees) as per planning<br />

requirements.<br />

‣ The following unit development fees are payable prior to <strong>the</strong> approval of <strong>the</strong> plans<br />

Plan checking fee Up to 2 units $49.50<br />

3 units & over $99.00<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 21 of 32: Infovision Ref Last Amended: 14/07/2007


Memorandum of Consent <strong>for</strong> <strong>Works</strong><br />

Industrial and Commercial $99.00<br />

as determined<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 22 of 32: Infovision Ref Last Amended: 14/07/2007


9 APPENDIX A – CONSTRUCTION REQUIREMENTS FOR VEHICLE CROSSINGS<br />

9.1 Maintenance and Reinstatement<br />

If it is necessary <strong>for</strong> Council, or any o<strong>the</strong>r Authority, to lay mains or carry out any work,<br />

necessitating breaking up or trenching, through or under a non-standard crossing, <strong>the</strong> property<br />

owner is required to bear any cost over and above that of <strong>the</strong> reinstatement of a standard<br />

concrete crossing.<br />

For a standard crossing, in <strong>the</strong> above situation, Council or <strong>the</strong> appropriate Authority will reinstate<br />

<strong>the</strong> vehicle crossing at no cost to <strong>the</strong> property owner.<br />

The property owner is responsible <strong>for</strong> <strong>the</strong> maintenance and replacement of both standard and non<br />

-standard crossings arising from normal wear and tear.<br />

9.2 Removal of Existing Paving and Kerb and Channel<br />

Existing footpaths, considered by Council to be in good order, may be left in tact to <strong>for</strong>m part of <strong>the</strong><br />

vehicle crossing. If <strong>the</strong> path thickness is less than 150mm at <strong>the</strong> crossing, <strong>the</strong> property owner will<br />

be advised that it is sub-standard. However, <strong>the</strong> path may be retained on <strong>the</strong> understanding that<br />

should this section be damaged, <strong>the</strong> owner will be held responsible <strong>for</strong> <strong>the</strong> cost of reinstatement.<br />

Where any path is damaged within <strong>the</strong> cross over, it must be broken out to an existing joint and<br />

replaced with 150mm thick concrete.<br />

Where <strong>the</strong>re is no layback, all kerb and channel must be removed to <strong>the</strong> nearest joint.<br />

Alternatively, with <strong>the</strong> approval of Council’s Supervising Officer, <strong>the</strong> complete kerb and channel may<br />

be cut through neatly so as to leave no section of kerb and channel less than 1.5m long. Care<br />

should be taken when breaking out kerb and channel so that <strong>the</strong> asphalt edge of roadway is not<br />

damaged. Should roadway damage occur, <strong>the</strong> property owner would be charged with subsequent<br />

costs <strong>for</strong> Council to reinstate.<br />

Where an existing kerb layback is not used <strong>for</strong> <strong>the</strong> crossing, it must be removed and reinstated in<br />

kerb and channel.<br />

9.3 Crossing Inspections<br />

After obtaining a MOC, <strong>the</strong> work may proceed to <strong>the</strong> stage where all excavation and <strong>for</strong>mwork is<br />

set up. At this stage <strong>the</strong> Contractor must obtain approval from <strong>the</strong> Construction Supervisor be<strong>for</strong>e<br />

pouring concrete. 24 hours prior notice is required to arrange an inspection. Please call Council’s<br />

Customer Service Centre on 9490 4222.<br />

Once all works are completed, arrangements <strong>for</strong> a final inspection should be made. The<br />

Construction Supervisor retains <strong>the</strong> right to order <strong>the</strong> demolition of <strong>the</strong> cross over if it does not<br />

con<strong>for</strong>m to Council’s specifications.<br />

9.4 Preparation of Sub-Base<br />

Any filling and <strong>the</strong> entire sub-base area must be thoroughly compacted using sufficient moisture<br />

content to obtain a uni<strong>for</strong>mly hard even surface.<br />

Any soft or spongy areas within <strong>the</strong> sub-base course will be rejected, as will any areas not showing<br />

<strong>the</strong> required minimum depth.<br />

In summer, <strong>the</strong> base course should be well watered prior to pouring concrete.<br />

9.5 Pouring Against Existing Concrete<br />

All concrete surfaces abutting new concrete should be thoroughly cleaned and watered immediately<br />

be<strong>for</strong>e pouring.<br />

The poured concrete should be densely compacted. In all instances, surface density should be<br />

obtained by heavy floating. Construction joints must be straight. The configuration shall con<strong>for</strong>m<br />

to Council's Standard drawings.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 23 of 32: Infovision Ref Last Amended: 14/07/2007


A first class standard of finishing and jointing is required to give a uni<strong>for</strong>m medium-rough textured<br />

surface with a steel trowel finish.<br />

If it is in <strong>the</strong> opinion of <strong>the</strong> Construction Supervisor that excessive damage has occurred due to<br />

rain, footprints, cracking or any o<strong>the</strong>r blemishes; he may order <strong>the</strong> removal of <strong>the</strong> crossing.<br />

9.6 Curing of New Concrete<br />

At temperatures above 25°C <strong>the</strong> Contractor must keep <strong>the</strong> concrete moist and green <strong>for</strong> seven (7)<br />

days and may use such methods as frequent watering, Poly<strong>the</strong>ne, Hessian sheet covering, or damp<br />

sand. Prematurely dried concrete, showing surface crazing, or shrinkage cracks <strong>the</strong> Construction<br />

Supervisor may order <strong>the</strong> removal of <strong>the</strong> crossing.<br />

9.7 Protection of <strong>Works</strong><br />

The contractor must erect sufficient barricades and lighting and carry out such cleaning up of<br />

debris to fully protect vehicular and pedestrian traffic. Any breach of this requirement will result in<br />

Council carrying out this work at <strong>the</strong> contractor's expense.<br />

9.8 Cleaning of <strong>the</strong> Site<br />

On completion of <strong>the</strong> crossing, <strong>the</strong> adjacent nature strips shall be neatly trimmed to match new<br />

crossing and left in a safe condition. All excavation material, broken concrete, <strong>for</strong>mwork etc., shall<br />

be removed from <strong>the</strong> site and <strong>the</strong> whole site shall be left in a neat and tidy condition.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 24 of 32: Infovision Ref Last Amended: 14/07/2007


10 APPENDIX B - CONDITIONS OF CONSTRUCTION OF THE CIVIL WORKS<br />

ASSOCIATED WITH DEVELOPMENTS<br />

10.1 The manager, Construction, shall be <strong>the</strong> Manager, Construction (Rosanna Office) of <strong>the</strong><br />

Banyule City Council, or his representative.<br />

10.2 All works are to be carried out in accordance with <strong>the</strong> approved plans and specifications and<br />

no alterations shall be made without <strong>the</strong> prior approval of <strong>the</strong> Engineering Services Department.<br />

10.3 Seven (7) days notice in writing must be given to <strong>the</strong> Manager, Construction by <strong>the</strong><br />

developer (or his agent) of his intention to commence works on <strong>the</strong> site. Failure to do so will result<br />

in <strong>the</strong> refusal to accept work done without Council’s knowledge and supervision.<br />

10.4 Prior to Commencement of works <strong>the</strong> developer shall submit <strong>the</strong> following in<strong>for</strong>mation to<br />

<strong>the</strong> Manager, Construction<br />

‣ The program of operations including <strong>the</strong> probable dates of completion of various<br />

sections of <strong>the</strong> work and <strong>the</strong> various areas where works will be carried on<br />

simultaneously.<br />

‣ A 24 hour 7 days a week telephone number <strong>for</strong> <strong>the</strong> contractor, <strong>the</strong> Engineer<br />

supervising <strong>the</strong> contractor and <strong>the</strong> Developer.<br />

‣ The Developer’s address <strong>for</strong> <strong>the</strong> service of notices and <strong>the</strong> name of <strong>the</strong> officer in<br />

charge of <strong>the</strong> works.<br />

10.5 Prior to <strong>the</strong> commencement of works <strong>the</strong> developer shall lodge with Council a deposit to<br />

cover <strong>the</strong> cost of any work carried out by Council under clauses 10.10 and 10.11. The lodging of<br />

this deposit does not imply any limit on <strong>the</strong> developers liability and <strong>the</strong> developer shall be charged<br />

<strong>the</strong> actual cost of any works carried out<br />

10.6 The engineering supervising <strong>the</strong> contract shall not permit <strong>the</strong> contractor to carry out work<br />

outside normal working hours prior to obtaining <strong>the</strong> permission of <strong>the</strong> Manager Construction.<br />

10.7 Any existing construction which is to be removed and which is deemed by <strong>the</strong> manager<br />

Construction to be <strong>the</strong> property of <strong>the</strong> Council is to be salvaged and delivered free of charge to <strong>the</strong><br />

Council Depot in Waterdale Road if so desired<br />

10.8 All works shall be adequately protected and lighted <strong>for</strong> <strong>the</strong> protection of <strong>the</strong> general public<br />

and <strong>the</strong> developer shall indemnify Council against claims arising from any injury to <strong>the</strong> public and<br />

or private property and <strong>for</strong> all damage to services of public authorities and private persons and any<br />

injuries arising from such damage resulting from <strong>the</strong> execution of <strong>the</strong> works.<br />

10.9 If at any time <strong>the</strong> Manager Construction is satisfied that <strong>the</strong> works have been left in an<br />

unsafe condition he may <strong>for</strong>thwith rectify such unsafe condition as he thinks fit and charge <strong>the</strong> cost<br />

of this work to <strong>the</strong> developer. The cost of such work shall include <strong>the</strong> cost of repairs or<br />

replacement of any lights barricades signs etc provided by Council and damaged or lost while on<br />

site.<br />

10.10 If at any time <strong>the</strong> Manager Construction is satisfied that any area outside <strong>the</strong> new<br />

development has been adversely affected during <strong>the</strong>se works and has not been reinstated to<br />

original condition he shall notify <strong>the</strong> developer accordingly. If <strong>the</strong> necessary reinstatement is not<br />

carried out within fourteen (14) days of such notice <strong>the</strong> manager construction may carry out such<br />

reinstatement and charge <strong>the</strong> cost of this work to <strong>the</strong> developer.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 25 of 32: Infovision Ref Last Amended: 14/07/2007


10.11 The whole of <strong>the</strong> works shall be carried out in such a way as to cause <strong>the</strong> least<br />

inconvenience to residents of <strong>the</strong> area.<br />

The developer shall ensure that any specific directions given by <strong>the</strong> manager construction to<br />

reduce any such inconvenience caused by dust excess noise blasting, construction work outside<br />

<strong>the</strong> area of development, movement of vehicles on existing council roads, discharge of<br />

stormwater runoff ei<strong>the</strong>r on to or from <strong>the</strong> area of <strong>the</strong> works or any o<strong>the</strong>r aspect of <strong>the</strong><br />

construction is promptly complied with. Work on busily trafficked roads is restricted to between<br />

9:00am and 3:30pm unless satisfactory arrangements <strong>for</strong> <strong>the</strong> contrary have been made with <strong>the</strong><br />

Manager Construction.<br />

10.12 After <strong>the</strong> works have been completed <strong>the</strong> developer shall supply Council with one set of<br />

transparencies of <strong>the</strong> as constructed plans<br />

10.13 Prior to <strong>the</strong> works being taken over by Council <strong>the</strong> developer shall pay (or cause to be<br />

paid) to Council any charges made <strong>for</strong> <strong>the</strong> following items: -<br />

‣ Supervision fees as provided <strong>for</strong> in <strong>the</strong> subdivision act<br />

‣ Future planting of street trees by Council<br />

‣ Any street name signs to be supplied or supplied and erected by Council<br />

‣ Any STOP signs or o<strong>the</strong>r traffic direction signs erected by Council including Line<br />

marking<br />

‣ Any accounts rendered in connection with Clauses 10.10 and 10.11 above<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 26 of 32: Infovision Ref Last Amended: 14/07/2007


11 APPENDIX C – STANDARD NOTES<br />

Where applicable and not covered elsewhere, <strong>the</strong> following notes are to be included on <strong>the</strong><br />

plans.<br />

GENERAL<br />

1 All levels to A.H.D.<br />

2 All workmanship and materials shall be to <strong>the</strong> approval of Council’s Construction Supervisor<br />

3 The Contractor shall take all care to preserve existing trees.<br />

4 The Contractor shall notify Council 7 days prior to commencement of any works.<br />

5 The Contractor is responsible <strong>for</strong> locating existing services and any damage caused to such<br />

services whe<strong>the</strong>r shown on <strong>the</strong> drawings or not.<br />

6 All excess spoil is to be disposed of off-site.<br />

7 The topsoil from cut and fill areas shall be stripped and stockpiled and spread to a minimum<br />

depth of 75mm over excavated and filled areas.<br />

8 All works are to be carried out to <strong>the</strong> standards and specifications of <strong>the</strong> Banyule City<br />

Council.<br />

9 Permanent survey marks are to be located at positions indicated on <strong>the</strong> plans, or as<br />

directed by Councils Construction Supervisor or <strong>the</strong> Supervising Engineer.<br />

10 Unused dams are to be breached, de-sludged and cleaned out to a firm foundation and<br />

filled as per note 34.<br />

11 The Contractor is to make provision <strong>for</strong> <strong>the</strong> safety of pedestrian and vehicular traffic during<br />

<strong>the</strong> currency of works to <strong>the</strong> satisfaction of Council’s Construction Supervisor according to a<br />

Council approved Traffic Management Plan.<br />

12 Any footpaths, driveways, roadways, kerbs, right-of-ways or existing features disturbed,<br />

broken or affected by <strong>the</strong> works are to be reinstated to <strong>the</strong> complete satisfaction of<br />

Council’s Construction Supervisor.<br />

13 All concrete is to be saw cut and broken out to nearest joint.<br />

14 No tree root shall be cut without <strong>the</strong> specific permission of Council’s Construction<br />

Supervisor.<br />

15 All nature strips and disturbed lawn areas within private property to be reinstated with<br />

topsoil and seeded.<br />

16 The Contractor is to verify <strong>the</strong> location of existing services prior to commencing works.<br />

17 The Contractor is to contact Construction Department on 9457 9888 at least 24 hours prior<br />

to commencing any works on site to arrange <strong>for</strong> Council supervision.<br />

DRAINAGE<br />

18 All drainage pipes shall be Rein<strong>for</strong>ced Concrete Class 2, or approved alternative and are to<br />

be laid in accordance with manufacturer’s specifications.<br />

19 Junction pits are to be in accordance with BCC Standard Drawing No. B023.<br />

20 Side entry pits are to be in accordance with BCC Standard Drawing No. B025.<br />

21 All trenches under roadways are to be backfilled with 20mm Class 2 F.C.R. compacted in<br />

150mm layers.<br />

22 Asphalt pavement joints over trenches in roadways are to be at a width of 150mm greater<br />

than <strong>the</strong> trench edges.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 27 of 32: Infovision Ref Last Amended: 14/07/2007


23 Bedding and backfilling <strong>for</strong> concrete pipe drains as per Standard Drawing B041. Bedding<br />

and backfill <strong>for</strong> o<strong>the</strong>r pipe types is to be as per manufacturer’s specifications.<br />

24 All easements are drainage and sewerage easements and are 3 metres wide unless shown<br />

o<strong>the</strong>rwise.<br />

25 Property inlets are to be located 1.0m from side or rear boundaries unless shown o<strong>the</strong>rwise.<br />

26 House drains are to be located as shown on plans, generally 6.0m from low side<br />

boundaries. Location of drains to be marked on <strong>the</strong> kerb and channel and end of pipe to be<br />

capped.<br />

27 All pipe centre-lines within allotments are to be offset one metre from <strong>the</strong> title boundary<br />

unless shown o<strong>the</strong>rwise.<br />

28 All lots are to fall at a minimum grade of 1 in 150 to drainage outlet.<br />

29 The floors of all drainage pits shall be shaped as per <strong>the</strong> standard drawings to ensure good<br />

streamlining and correctly sloped to move debris into <strong>the</strong> stream.<br />

30 Trenches shall be water compacted as directed by Council’s Supervising Engineer.<br />

31 All existing house drains terminating within an easement or kerb and channel along <strong>the</strong><br />

alignment of <strong>the</strong> new outfall drain shall be connected to <strong>the</strong> outfall drain.<br />

ROADWORKS<br />

32 65mm diameter ‘Agroflex’ AG drain to be installed directly under all kerbing, with 14mm<br />

screenings.<br />

33 Unless o<strong>the</strong>rwise noted all vegetation shall be stripped to a minimum depth of 150mm<br />

under all pavements and fill areas.<br />

34 All filling shall be of approved material compacted in 150mm layers to 95% A.S. modified<br />

compaction.<br />

35 All concrete to have 25 MPa strength at 28 days.<br />

36 All cross road service conduits to be laid at a minimum grade of 1 in 100 and extend 0.30m<br />

behind <strong>the</strong> kerb, and must accord with <strong>the</strong> relevant authorities requirements.<br />

Conduits are to be located in <strong>the</strong> positions shown on <strong>the</strong> plan or as close as practicable.<br />

Both ends of <strong>the</strong> conduit are to be capped and <strong>the</strong>ir location and purpose marked on <strong>the</strong><br />

kerb and channel.<br />

37 Fire hydrant locations are to be clearly marked on site in accordance with relevant<br />

Australian Standard.<br />

38 Concrete vehicular crossings shall be provided to each allotment as directed by Councils<br />

Construction Supervisor. Crossings are to be 150mm deep, rein<strong>for</strong>ced with F72 mesh.<br />

39 Where SM2 rollover kerb is used, a 30mm layback (from top of kerb) is to be provided at<br />

vehicle crossings.<br />

40 Vehicular access shall be provided to all allotments at a grade no greater than 1 in 6.<br />

RESERVES<br />

41 Provide gas, water and electricity conduits to serve all Council reserves as required and<br />

provide water conduit and service.<br />

42 Provide vehicular access to Council Reserves located in <strong>the</strong> subdivision, including a vehicular<br />

crossing and if necessary a concrete ramp of maximum grade 1 in 6 into <strong>the</strong> reserve.<br />

43 All Reserves are to be cleared of debris, old fences, sheds, stumps, blackberries, noxious<br />

weeds etc., and <strong>the</strong> Reserve levelled and top-dressed all to <strong>the</strong> satisfaction of Council’s<br />

Construction Supervisor.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 28 of 32: Infovision Ref Last Amended: 14/07/2007


44 A Memorandum of Consent <strong>for</strong> <strong>Works</strong> is to be obtained from Council <strong>for</strong> works within an<br />

existing easement, drainage reserve or road reservation.<br />

45 Footpaths within Reserves must be constructed with 100mm thick concrete rein<strong>for</strong>ced with<br />

F72 mesh, on 50mm compacted depth of 20mm nominal size Class 2 F.C.R.<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />

(edited).doc<br />

Page 29 of 32: Infovision Ref Last Amended: 14/07/2007


Engineering Services 10061 Development <strong>Guidelines</strong> Page 30 of 32: Infovision Ref Last Amended: 14/07/2007<br />

(edited).doc


13 APPENDIX E – STANDARD DRAWINGS<br />

Drg No Description<br />

Kerb and Channel<br />

B001 Kerb Profiles<br />

B002 Former Heidelberg Eltham and Diamond Valley Profiles<br />

B003 Open Invert Channels<br />

B004 Pitcher Kerbs<br />

B005 Two Pitcher Tray Kerb & Channel at Crossing<br />

B006 House Drain Kerb Adaptors<br />

B021<br />

B022<br />

B023<br />

B024<br />

B025<br />

B026<br />

B027<br />

B028<br />

B029<br />

B030<br />

Pit Details<br />

Step Irons<br />

Pit Covers<br />

Junction Pit<br />

Precast Lintels <strong>for</strong> SEP's<br />

Side Entry Pit – B Type Kerb<br />

Side Entry Pit – SM Type Kerb<br />

Grated Side Entry Pit<br />

Extended Throat Side Entry Pit<br />

Footpath Grated Pit<br />

Combination Grate and Side Entry Pit<br />

B041<br />

B042<br />

B043<br />

B044<br />

B045<br />

Drainage Details<br />

Bedding & Backfilling <strong>for</strong> Concrete Pipe Drains<br />

Anchor Block<br />

Sub-Surface Drain and Service Conduit Details<br />

House Drain Connections<br />

Property Gully Inlet<br />

Crossings<br />

B051 Vehicle Crossing<br />

B052 Pam Crossing<br />

RDN 9-15 VicRoads – <strong>Guidelines</strong> <strong>for</strong> <strong>the</strong> placement of Tactile Ground Surface Indicators<br />

B061<br />

B062<br />

Retaining Walls<br />

Low side Stone Retaining Wall<br />

High Side Stone Retaining Wall<br />

Miscellaneous<br />

Engineering Services 10061 Development <strong>Guidelines</strong> Page 31 of 32: Infovision Ref Last Amended: 14/07/2007<br />

(edited).doc


TC-1200 VicRoads Standard Drawings <strong>for</strong> Traffic Signals – “Foundation <strong>for</strong> Pedestals”<br />

Engineering Services<br />

10061 Development <strong>Guidelines</strong><br />