GOVERNMENT OF ARUNACHAL PRADESH<br />

PUBLIC WORKS DEPARTMENT<br />

NO.CEAP(D&P)PLG-11/CRF(NORMAL)/2006-07/340-47 29 th June 2007<br />

To<br />

The Commissioner (<strong>PWD</strong>)<br />

Government <strong>of</strong> <strong>Arunachal</strong> Pradesh<br />

Itangar<br />

Sub: Tentative allocations against CRF projects.<br />

Sir,<br />

It is necessary to convey the tentative allocations against CRF projects pending<br />

finalization <strong>of</strong> AOP 2007-08 Road and Bridge sector, to facilitate preparation <strong>of</strong> work<br />

plans by Chief Engineer (EZ), Chief Engineer (WZ), and the field <strong>of</strong>ficers under them.<br />

This is also required to prevent commitment <strong>of</strong> liabilities and unregulated<br />

expenditure before actual work wise distribution <strong>of</strong> fund.<br />

I am, therefore, enclosing herewith a statement showing tentative allocations against<br />

normal CRF projects (State Category) against a tentative outlay <strong>of</strong> Rs.1622.00 lakhs<br />

under the programme as seen during the last couple <strong>of</strong> years.<br />

You may like to consult Planning Department and convey your approval <strong>of</strong> the<br />

tentative allocations so that CE (EZ) and CE (WZ) could draw their work plans,<br />

which will be restricted within 80% <strong>of</strong> the resource base.<br />

Enclo: as above<br />

Yours faithfully<br />

(Tomi Ete)<br />

Chief Engineer (D&P)<br />

Copy to:<br />

1. The Development Commissioner, Government <strong>of</strong> <strong>Arunachal</strong> Pradesh, Itangar.<br />

2. The Secretary (Planning), Government <strong>of</strong> <strong>Arunachal</strong> Pradesh, Itanagar along<br />

with the statement.<br />

3. The PS to Minister (<strong>PWD</strong>&UD), AP, Itanagar for kind information <strong>of</strong> Hon’ble<br />

Minister please.<br />

4. The PS to Minister (Finance & Planning), AP, Itanagar for kind information <strong>of</strong><br />

Hon’ble Minister please.<br />

5. The Chief Engineer (EZ), <strong>PWD</strong>, AP, Itanagar.<br />

6. The Chief Engineer (WZ), <strong>PWD</strong>, AP, Itanagar.<br />

7. The Director (Planning), Government <strong>of</strong> <strong>Arunachal</strong> Pradesh, Itanagar.


CRF


STATEMENT SHOWING BALANCE FUND REQUIREMENT AND TENTATIVE ALLOCATION UNDER CRF DURING 2007-08<br />

(Rupees in lakhs)<br />

Page - 1<br />

Sl. No.<br />

Name <strong>of</strong> the Scheme<br />

Sanctioned<br />

Cost<br />

Technical<br />

Sanction Cost<br />

Achivement up<br />

to March 2007<br />

Balance<br />

Proposed<br />

allocation<br />

2007-08<br />

Remarks<br />

A<br />

1 2 3 4 5 6 7 8<br />

Schemes fully funded by the Govt. <strong>of</strong> India<br />

1 Approach road to V.K.V. school at Along (6.00Km) 98.88 98.85 105.35 Nil 0.00 Completed<br />

2 Improvement <strong>of</strong> Jirdin V.K.V. road to 152.48 158.57 174.01 Nil 0.00 Completed<br />

J.N.V. School on Taso-Mobuk(7.75Km)<br />

3 Patum Rumgong Road (22.00Km) 719.00 762.30 788.93 Nil 0.00 Completed<br />

4 C/o Along - Kaying BRTF road to Donyi Polo 42.68 42.68 42.68 Nil 0.00 Completed<br />

Degree College at Kamki<br />

5 Construction <strong>of</strong> Steel bridge over River Sigen 184.78 183.76 164.76 19.00 0.00 Completed<br />

6 Extension and Resurfacing <strong>of</strong> Basar Township Road 244.80 257.00 124.69 132.31 100.00 In progress<br />

7 Improvement/construction <strong>of</strong> Puchigeko to 325.07 325.07 93.62 231.45 100.00 In progress<br />

Sikiputu via Anglomodak, Pegalomdak and Gichi<br />

8 Construction <strong>of</strong> Mebo-Dholla road(36.70 Km) 1005.50 1081.00 795.64 285.36 100.00 In progress<br />

9 Construction <strong>of</strong> Mebo-Dholla road (Ph-II) 345.18 363.35 171.40 191.95 100.00 In progress<br />

(36.70 Km)<br />

10 Improvement <strong>of</strong> Yingkiong Township road 230.00 227.49 230.00 Nil 0.00 Completed<br />

(20.00 km)<br />

11 C/o PSC girder and RCC slab composite bridge 305.88 334.05 150.71 183.34 125.00 In progress<br />

over river Buri - Dihing (Span – 120.00 mtr).<br />

E:\crf-07-08


STATEMENT SHOWING BALANCE FUND REQUIREMENT AND TENTATIVE ALLOCATION UNDER CRF DURING 2007-08<br />

(Rupees in lakhs)<br />

Page - 2<br />

Sl. No.<br />

Name <strong>of</strong> the Scheme<br />

Sanctioned<br />

Cost<br />

Technical<br />

Sanction Cost<br />

Achivement up<br />

to March 2007<br />

Balance<br />

Proposed<br />

allocation<br />

2007-08<br />

Remarks<br />

1 2 3 4 5 6 7 8<br />

12 Steel truss girder bridge over river Dibang 434.88 442.00 474.92 Nil 4.00 Pending<br />

(Span:150m)<br />

errection <strong>of</strong><br />

decking to be<br />

completed<br />

13 C/o Chowkham -Tezu road via Alubari & Digaru 208.54 208.54 187.75 21.00 21.00 Decking to be<br />

hut( C/o RCC Bridge over river Bereng)(span:80m)<br />

completed<br />

14 Roing - Shantipur Road 482.50 528.76 528.76 Nil 0.00 Completed<br />

15 By pass road to Roing township 288.45 288.45 308.78 Nil 0.00 Completed<br />

16 Re-surfacing <strong>of</strong> Road at Itanagar under 147.81 147.81 147.52 Nil 0.00 Completed<br />

Division A & B<br />

17 C/o Bailey Bridge over river Konko Nallah 120.23 132.31 132.52 Nil 0.00 Completed<br />

(20 mtr span) including approach and rain etc. <strong>of</strong><br />

the approach road to Sangge Lhaden Sports Shool<br />

Complex (1.10 Km) at Chimpu, Itanagar.<br />

18 Parking space near R.K. Mission Hospital Itanagar 9.36 9.36 9.36 Nil 0.00 Completed<br />

on NH-52 'A'<br />

19 C/o road from Bat on Ita-Jotte road to Chimi 396.39 400.00 300.00 100.00 58.00 In progress<br />

via Muglipop (7.50 km) (Ph-I)<br />

20 Improvement <strong>of</strong> Naharlagun Township roads. 292.72 320.61 320.61 Nil 0.00 Completed<br />

21 C/o Double lane approach road to <strong>Arunachal</strong> 117.95 117.89 117.89 Nil 0.00 Completed<br />

University at Rono Hill, Doimukh<br />

22 Approach road to DC Office at Yupia (Ph-I) 89.40 93.87 93.87 Nil 0.00 Completed<br />

E:\crf-07-08


STATEMENT SHOWING BALANCE FUND REQUIREMENT AND TENTATIVE ALLOCATION UNDER CRF DURING 2007-08<br />

(Rupees in lakhs)<br />

Page - 3<br />

Sl. No.<br />

Name <strong>of</strong> the Scheme<br />

Sanctioned<br />

Cost<br />

Technical<br />

Sanction Cost<br />

Achivement up<br />

to March 2007<br />

Balance<br />

Proposed<br />

allocation<br />

2007-08<br />

Remarks<br />

1 2 3 4 5 6 7 8<br />

23 C/o Double lane road to <strong>Arunachal</strong> University at 114.56 134.57 124.56 10.01 10.00<br />

Rono Hill, Doimukh (Pavement & Supplementary<br />

Works = 2.36 km)<br />

24 Improvement/Extension <strong>of</strong> Sagalee Township 528.58 528.58 115.00 413.58 150.00 In progress<br />

Road (5.975 Km)<br />

25 Improvement <strong>of</strong> road from Dha Hill on 839.23 827.13 364.78 462.35 275.00 In progress<br />

Tamen-Tali road to Gangte (13.10 km).<br />

26 C/O Bypass Road from BRTF Road to VKV School 286.10 286.10 60.00 226.10 95.00 In progress<br />

Via General Ground,SSB Colony and HS School<br />

at Koloriang<br />

27 C/o Road from Khenewa C.O. Hq. To Seppa- 581.00 581.00 315.00 266.00 95.00 In progress<br />

Chayangtajo via Purdung and Pakke village<br />

(15 km) (Scope : Widening 0.00 to 11.00 km,<br />

SMC, Slab Culverts, Minor bridges, R&B wall,<br />

Side drain & Traffic signs)<br />

28 Bypass road to Bomdila township from BRTF 314.75 314.75 313.91 0.84 6.00 To be completed<br />

road via New Bomdila<br />

29 Improvement <strong>of</strong> road from Dirang -Tawang road 327.39 313.46 275.71 37.75 38.00 To be completed<br />

to Gonpache to connect National Yak Research<br />

Centre<br />

30 Impvt. & upgradation <strong>of</strong> bypass for Bomdir on 188.79 188.79 188.85 Nil 0.00 Completed<br />

BRTF road to District Headquater at Tawang<br />

31 Improvement <strong>of</strong> Road from De-delo to Leporianf (10 Km)<br />

in the State <strong>of</strong> <strong>Arunachal</strong> Pradesh<br />

628.60 -- 0.00 628.60 90.00 New sanction<br />

E:\crf-07-08


STATEMENT SHOWING BALANCE FUND REQUIREMENT AND TENTATIVE ALLOCATION UNDER CRF DURING 2007-08<br />

(Rupees in lakhs)<br />

Page - 4<br />

Sl. No.<br />

Name <strong>of</strong> the Scheme<br />

Sanctioned<br />

Cost<br />

Technical<br />

Sanction Cost<br />

Achivement up<br />

to March 2007<br />

Balance<br />

Proposed<br />

allocation<br />

2007-08<br />

Remarks<br />

1 2 3 4 5 6 7 8<br />

32 Construction <strong>of</strong> approach road to V.K.V. at Dobi in Lower<br />

Subansiri District, Ziro (length = 2025 mtr) in the State <strong>of</strong><br />

<strong>Arunachal</strong> Pradesh.<br />

33 Improvement and up-gradation <strong>of</strong> Road network Lumla<br />

Township road (15.095 Km) in the State <strong>of</strong> <strong>Arunachal</strong><br />

Pradesh.<br />

34 Construction <strong>of</strong> Road from Pai to Pinegroove (20.00 Km)<br />

Phase-I (0.00 - 5.00 Km) in the State <strong>of</strong> <strong>Arunachal</strong><br />

Pradesh.<br />

35 Improvement <strong>of</strong> Naharlagun Township Road Phase-II in<br />

the State <strong>of</strong> <strong>Arunachal</strong> Pradesh.<br />

65.46 -- 0.00 65.46 35.00 New sanction<br />

600.00 -- 0.00 600.00 60.00 New sanction<br />

500.00 -- 0.00 500.00 50.00 New sanction<br />

500.00 -- 0.00 500.00 50.00 New sanction<br />

36 C/o Rima Motongsa road (18.00 km) Ph-I 0.00 to 7.00<br />

km.<br />

500.00 -- 0.00 500.00 60.00 New sanction<br />

Total: 12216.94 9698.10 7221.58 5375.10 1622.00<br />

E:\crf-07-08


STATEMENT SHOWING BALANCE FUND REQUIREMENT AND TENTATIVE ALLOCATION UNDER CRF DURING 2007-08<br />

(Rupees in lakhs)<br />

Page - 5<br />

Sl. No.<br />

Name <strong>of</strong> the Scheme<br />

Sanctioned<br />

Cost<br />

Technical<br />

Sanction Cost<br />

Achivement up<br />

to March 2007<br />

Balance<br />

Proposed<br />

allocation<br />

2007-08<br />

Remarks<br />

1 2 3 4 5 6 7 8<br />

B Schemes Under EI<br />

1) C/o road from Dirang-dzong to Namthung via Sanlum<br />

(19.215km)<br />

50% N/S<br />

50% C/S 544.98 1089.53 52.14 492.84<br />

2) By pass road from Papu Nalla to Itanagar via Donyi Polo Vidya<br />

Bhawan (7.50km) in Papum Pare Dist.<br />

50%S/S<br />

50%C/S 388.58 827.72 120.00 268.58<br />

Total: 933.56 1917.25 172.14 761.42<br />

Grand Total 13150.50 11615.35 7393.72 6136.52<br />

Chief Engineer (D&P)<br />

<strong>PWD</strong>, AP, Itanagar<br />