ARTICLE 5<br />

PAYMENT PROCEDURES<br />

5.1 Payment terms will be net forty-five (45) days. Terms not consistent with this<br />

provision are not acceptable and may be caused for rejection. <strong>FGUA</strong> will pay the<br />

Contractor within forty-five (45) days after the receipt of a correct invoice for<br />

reasonable work allocable to the contract requirements, whichever event occurs<br />

later. Payment(s) are considered effective on the date payment is mailed.<br />

5.2 The cost of all materials and/or equipment provided in the performance of the<br />

work is to be reimbursed to the Contractor in the following manner:<br />

5.2.1 The <strong>FGUA</strong> shall reimburse the Contractor, on completion and acceptance<br />

of each assigned job, only for those materials and/or equipment actually<br />

used in the performance of the work that are supported by invoices issued<br />

by the suppliers of the Contractor describing the quantity of the materials<br />

purchased and/or equipment rented.<br />

ARTICLE 6<br />

TERMINATION OF AGREEMENT<br />

6.1 <strong>FGUA</strong> may terminate or cancel this Agreement at its discretion and said<br />

termination shall be effective, with or without cause, after written notice has<br />

been provided to the Contractor.<br />

6.2 Following termination, <strong>FGUA</strong> shall make a settlement with the Contractor upon a<br />

pro rata basis as determined by <strong>FGUA</strong>, which shall fix the value of the Goods<br />

and/or Services performed by the Contractor prior to the termination or<br />

cancellation of this Agreement.<br />

ARTICLE 7<br />

CONTRACTOR’S REPRESENTATIONS<br />

In order to induce <strong>FGUA</strong> to enter into the Agreement, Contractor makes the following<br />

representations:<br />

7.1 Contractor has familiarized itself with the nature and extent of the Contract<br />

Documents, Work, site, locality and all local conditions, laws and regulations that<br />

in any manner may affect cost, progress, performance, or furnishing of the<br />

Work.<br />

7.2 Contractor understands the estimate of quantities of the various items of work<br />

and materials, if set forth in information provided by <strong>FGUA</strong>, is approximate only.<br />

The quantities actually required to complete the work may be less or more than<br />

estimates. The <strong>FGUA</strong> further serves the rights to vary the quantities in any<br />

amount.