Kiewit Infrastructure South Co.<br />

Kiewit will take on the role of design-build coordinator, a position unique to Kiewit it<br />

utilizes on all its projects.<br />

Kiewit will provide the necessary communication link and information transfer between<br />

the design and construction management personnel during the initial design period.<br />

The project team will work with Islamorada staff to coordinate and finalize the design<br />

submittal process, crucial to project success as delivery of the design directly affects<br />

the critical path of the schedule.<br />

Overall, Kiewit will:<br />

• Coordinate all design, constructability and feasibility analysis for and with CPH<br />

Engineers (designer) during the design phase of the project;<br />

• Create and manage construction schedule, incorporating the designers schedule<br />

so the Village can see job progress as a whole;<br />

• Procure all material and subcontracts for project construction;<br />

• Construction work including concrete structure, utility line installation, road<br />

reconstruction, traffic maintenance;<br />

• Subcontract other work locally for paving, landscaping, signs and striping, rock<br />

trenching, sewer line and collection systems;<br />

• Inform and maintain weekly communication with community and Village over<br />

construction progress and expectations;<br />

• Provide and execute an environmental and compliance program throughout<br />

construction;<br />

• Provide and execute a construction safety plan that incorporates public safety as<br />

well as construction personnel;<br />

• Complete construction of the project within the contract duration;<br />

• Provide O&M manuals and training, and turn over the system to U.S. Water (the<br />

operator)<br />

Team Proposal Florida Governmental Utility Authority<br />