Florida Governmental Utility Authority<br />

Board <strong>Agenda</strong> Item<br />

Thursday, February 17, 2011<br />

SM 4 Approval of Amendment to the Design-Build Agreement for Waterway Estates<br />

Interconnect between <strong>FGUA</strong> and CDM Constructors, Inc.<br />

___________________________________________________________________________________<br />

Summary<br />

Provided for your review and consideration is an Amendment to the Design-Build Agreement For Waterway Estates<br />

Interconnect entered into between the Florida Governmental Utility Authority (<strong>FGUA</strong>) and CDM Constructors, Inc.,<br />

dated October 21, 2010. In accordance with the Design-Build Agreement, acceptance of the Guaranteed Maximum<br />

Price (GMP) by the <strong>FGUA</strong> Board “shall occur on or before February 17, 2011 in order for Design-Builder to meet the<br />

specified Substantial Completion Date…….” On January 18, 2011 the Design-Builder, CDM Constructors, Inc.<br />

submitted a GMP to <strong>FGUA</strong> which was well in excess of the funds budgeted for the project. Since this time, <strong>FGUA</strong><br />

staff and the Design-Builder have been actively negotiating in an attempt to reach a GMP acceptable to all parties.<br />

The Design-Builder is currently incorporating a number of value engineering alternatives into the project which<br />

hopefully will result in an acceptable GMP. In the event an acceptable GMP is not resolved by February 17, 2011 for<br />

Board approval, and negotiations are continuing, a contract amendment is required to amend the GMP (and<br />

issuance of the associated Notice to Proceed) approval date. Accordingly, we are recommending that the date for<br />

GMP acceptance be extended to March 17, 2011 (the next regularly scheduled Board meeting) with no change to<br />

the specified Substantial Completion Date. Staff has evaluated the project schedule and do not believe this will<br />

adversely affect the final completion date.<br />

Recommendation<br />

Staff recommends approval of the Amendment to the Design-Build Agreement for Waterway Estates Interconnect.<br />

Budget Impact<br />

NA<br />

Board Action<br />

Moved by: Seconded by: Action Taken: