CCTV Wire and Cable / Conduit (est 2300' total)<br />
CCTV Conduit & Wire Installation<br />
F&I 20' Slide Gate<br />
F&I Automatic Gate Operator, Mounting Base, SS Chain & Loop Detectors<br />
F&I Keypad & Key Card Entry with Voice Call Box to Plant Office<br />
Existing Security Fence/ Gate Modifications<br />
New Security Fence/ Gate Installation<br />
40' Slide Gate Track Concrete Work (elevated east side of track)<br />
Decorative Entrance Wall<br />
System start-up and testing<br />
B. PROJECT COST $123,820.00<br />
USW will perform the services listed above for a Lump Sum Fee of $123,820.00, which will be paid in<br />
monthly installments over a 4 month period beginning in April 2011. It is anticipated that the project will<br />
commence after the first week of March 2011. USW acknowledges that payment by the <strong>FGUA</strong> will be<br />
contingent upon receipt of ISDC related funding from the Federal Government.<br />
C. PROJECT SCHEDULE<br />
Design & Layout March 2011<br />
Mobilization March 2011<br />
Substantial Completion July 2011<br />
Final Completion August 2011<br />
Schedule for Completion is based on the cooperation of Base Personnel and the availability of<br />
existing system records and documentation.<br />
D. NOTICE/PROJECT MANAGER OF CONSULTANT<br />
USW Manager assigned to Project:<br />
Dave Schultz Jr, PE – Director of Construction<br />
(m) 813-434-5959 (f) 727-849-5467<br />
dschultzjr@uswatercorp.com<br />
Signing Authority<br />
______________________________<br />
______________________________<br />
Gary Deremer, Principal in Charge<br />
Robert E. Sheets, System Manager<br />
US Water Services Corporation<br />
Florida Governmental Utility Authority<br />
4939 Cross Bayou Blvd. 280 Wekiva Springs Road, Suite 2000<br />
New Port Richey, FL 34652 Longwood , FL 32799<br />
Certification that Sufficient Funds are Available:<br />
______________________________<br />
Heidi L. Snyder<br />
Chief Financial Officer<br />
______________________________<br />
John Pelham<br />
General Counsel<br />
Dated this ____ day of _____________, 2011<br />
USW 11-02 MacDill Work Authorization<br />
Page 2 of 2<br />