27.01.2015 Views

Final Environmental Impact Report - Whittier Bridge/I-95 ...

Final Environmental Impact Report - Whittier Bridge/I-95 ...

Final Environmental Impact Report - Whittier Bridge/I-95 ...

SHOW MORE
SHOW LESS
  • No tags were found...

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Whittier</strong> <strong>Bridge</strong>/I-<strong>95</strong> Improvement Project FEIR<br />

Chapter 2.0: Response to Comments on the <strong>Environmental</strong> Assessment/Draft <strong>Environmental</strong> <strong>Impact</strong> <strong>Report</strong><br />

(within the Zone A) complies with 310 CMR 22.20B and C, and with applicable stormwater regulatory standards<br />

specified at 310 CMR 10.05(6)(k)(l10) and 314 CMR 9.06(6)(a)(l-10). MassDOT intends to use the road for<br />

inspection and maintenance of the City of Newburyport's drinking water supply lines from the Bartlett Spring<br />

Treatment Plant.<br />

Response: The existing City of Newburyport drinking water lines would be impacted by the project<br />

and require relocation. The gravel utility road within the RFA will follow the route of the relocated<br />

water supply lines from the water treatment plant at Bartlett Spring Pond and will be used solely by<br />

the water department for maintenance and inspection of the relocated water lines. No public vehicles<br />

will be allowed to use the roadway and very minimal water department traffic is anticipated, on the<br />

order of several trips per month on average.<br />

The provisions of the Drinking Water Regulations at 310 CMR 22.20C(2)(l) prohibit within the Zone A<br />

of Bartlett Springs Pond ―land uses that result in the rendering impervious of more than 15%, or<br />

more than 20% with artificial recharge, or 2500 square feet of any lot, whichever is greater.‖ The<br />

proposed access road will be comprised of either crushed stone or open course gravel and is not<br />

considered to be an impervious surface, thus meeting that standard and applicable stormwater<br />

standards.<br />

EEA-24: I have received a number of comments requesting that MassDOT provide mitigation from noise impacts to<br />

residential receptors. The FEIR should respond to these comments from receptors who will impacted by future noise<br />

conditions.<br />

Response: The traffic-noise mitigation analysis was completed in accordance with updated FHWA<br />

and MassDOT policy. The Traffic Noise Model was used to evaluate the noise reduction<br />

performance and cost-effectiveness of numerous candidate noise barriers. Although a number of<br />

receptors have been identified as impacted by existing and future noise conditions, no noise barriers<br />

can be justified as being ―feasible‖ and ―reasonable‖ in accordance with the MassDOT policy; not<br />

enough receptors benefit from the noise reduction to meet the ―per benefitted receptor‖ cost basis.<br />

Consequently, noise barriers will not be included in the project.<br />

EEA-25: The FEIR should evaluate the feasibility of increasing the height and extending the length of the existing<br />

articulated barrier adjacent to the Laurel Road neighborhood.<br />

Response: Two receptors on Laurel Road were impacted by existing and future traffic noise.<br />

Dozens of alternatives for a noise barrier in the Laurel Road area were evaluated (Noise Barrier No.<br />

2). The optimal barrier height and length for noise reduction resulted in a cost effectiveness index<br />

(CEI) twice the acceptable CEI limit. An inadequate shorter length barrier built on top of the existing<br />

barrier (i.e., less expensive) was also evaluated, but the CEI value still exceeded the limit. Therefore,<br />

in accordance with the MassDOT Noise Policy, a longer and taller noise barrier in this location is not<br />

feasible and reasonable and cannot be constructed for the project. The project will relocate the<br />

existing articulated noise barrier within the limits of the I-<strong>95</strong> ROW in order to accommodate the<br />

construction of the Shared-Use Path.<br />

2-9

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!