Final Environmental Impact Report - Whittier Bridge/I-95 ...

Final Environmental Impact Report - Whittier Bridge/I-95 ... Final Environmental Impact Report - Whittier Bridge/I-95 ...

mhd.state.ma.us
from mhd.state.ma.us More from this publisher
27.01.2015 Views

Whittier Bridge/I-95 Improvement Project FEIR Chapter 3.0: Mitigation and Commitments Exit 57 Newburyport Park-and-Ride lot through to the Ghost Trail in Salisbury (which connects to U.S. Route 1): Providing for the eventual hub connection to the Amesbury Powow Riverwalk and Salisbury Point Ghost Trail; Providing connections to existing and planned trails; and Improving access to and interconnections between Moseley Woods and Maudslay State Park and other regional recreational resources. The incorporation of the Shared-Use Path will be consistent with the USDOT Policy Statement on Bicycle and Pedestrian Accommodation Regulations and Recommendations (March 15, 2010) and MassDOT‘s GreenDOT initiatives policy. The Shared-Use Path will be constructed during all construction stages since it is directly related to the I-95 northbound bridge and roadway approach sequencing. Cost to construct the path is expected to be $8.5 million. Schedule and Cost Permanent lighting, fendering, and a navigation buoy will be constructed during the last phase of the project when bridge work is complete. Temporary aids to navigation during in-water work (42 months) will be used as needed. The cost to provide temporary and permanent navigation aids is expected to be $100,000. 3.16.6 Section 401 Water Quality Certifications – MassDEP A combined Water Quality Certification Application for the project was prepared to include: Major Project Certification for dredging and disposal of more than 5,000 cubic yards of material within the Merrimack River (BRP WW07); a Major Project Certification for the discharge of more than 5,000 square feet of fill within Land Under Ocean of the Merrimack River; and three vegetated wetlands (Series H, I and M) north of the river (BRP WW10). Summary of Dredging Activities (BRPWW07) Dredging is associated with the installation of cofferdams around the six new permanent piers during construction, around each of the four existing Whittier Bridge piers during demolition and from construction of two temporary support structures during construction of the I-95 northbound bridge. Approximately 7,150 cubic yards of material will be dredged within Land Under the Ocean (LUO) of the Merrimack River. Dredging activities are limited to the Merrimack River and will include the entire area within the cofferdams (45,620 square feet); it does not include the removal of the existing piers (10,130 square feet outside of new pier footprints), which will be considered restoration of LUO. Work within the cofferdams, outside of the footprint of the existing and proposed piers, is considered a temporary alteration to LUO and totals 28,520 square feet. Cofferdams will be constructed at each proposed pier location to provide work access and allow work to be performed in the ―dry.‖ Avoidance and Minimization Measures to minimize the suspension of solids during dredging will include conducting all dredging activities within water tight sheet pile cofferdams. Dredging will be conducted with a clamshell excavator located on a barge moored or spudded adjacent to the cofferdam. Dredged material will be allowed to drain much of the entrained water within the confines of the cofferdam before the material is deposited on a barge for transport to an intermediate facility. No open water disposal or 3-24

Whittier Bridge/I-95 Improvement Project FEIR Chapter 3.0: Mitigation and Commitments side casting of dredged material is proposed. The barge will be surrounded with silt curtains suspended from a floating boom to minimize the spread of any sediment runoff from the barge. Mitigation Measures Mitigation measures will be performed during demolition and construction activities to minimize the impacts to water quality during the in-water portion of the work associated with the construction of new bridge piers and removal of the existing piers. Cofferdams will be installed to enclose existing and new bridge piers to eliminate impacts from resuspended sediments in the water column. Locations for the disposal of dredged material will be the responsibility of the of the design/build contractor to be selected for project construction. MassDOT will include special provisions in the contract documents to ensure proper handling and disposal of the dredged material The cost of the cofferdams is estimated at $7.5 million. Summary of Discharge of Fill Material (BRPWW10) The project will result in the discharge of approximately 22,300 square feet of fill material to LUO and vegetated wetlands. Approximately 17,100 square feet of fill will be discharged within LUO of the Merrimack River for the placement of the six new piers. The remaining 5,200 square feet of fill within vegetated wetlands north of the Merrimack River is associated with highway widening and drain line installation. Of the 5,200 square feet, approximately 1,640 square feet will be temporary alterations associated with a work zone/construction access to build a retaining wall at Wetland H and drain line crossings at Wetland M. The remaining 3,560 square feet of permanent alterations will result from the highway widening at Wetlands H and I. Temporary alterations to LUO in the Merrimack River will be approximately 28,520 square feet (excluding the footprint of the existing and proposed piers) from the installation of cofferdams around the six new permanent piers during construction, around each of the four existing Whittier Bridge piers during demolition and from construction of two (2) temporary support piers during construction of the I-95 northbound bridge. Avoidance and Minimization Where possible, the introduction of retaining walls was used to minimize the extent of fill. Mitigation Temporary impacts to Bordering Vegetated Wetland H (Amesbury), as well as to Isolated Vegetated Wetland M (Salisbury), will be mitigated on site at each wetland location by in-situ restoration. To mitigate for permanent impacts to vegetated wetlands H and I (3,560 square feet), the replication concept in Amesbury will consist of expanding Wetland H by excavating approximately 4,960 square feet of upland at its northern end within the right of way. The removal of the existing piers within the Merrimack River will restore approximately 10,130 square feet of LUO. For work occurring in upland areas, erosion and sediment controls will be employed to minimize the transport of sediment into the existing drainage system and adjacent resource areas during construction. The BMPs to manage storm water and control the discharge of pollutants will be 3-25

<strong>Whittier</strong> <strong>Bridge</strong>/I-<strong>95</strong> Improvement Project FEIR<br />

Chapter 3.0: Mitigation and Commitments<br />

side casting of dredged material is proposed. The barge will be surrounded with silt curtains<br />

suspended from a floating boom to minimize the spread of any sediment runoff from the barge.<br />

Mitigation Measures<br />

Mitigation measures will be performed during demolition and construction activities to minimize the<br />

impacts to water quality during the in-water portion of the work associated with the construction of<br />

new bridge piers and removal of the existing piers. Cofferdams will be installed to enclose existing<br />

and new bridge piers to eliminate impacts from resuspended sediments in the water column.<br />

Locations for the disposal of dredged material will be the responsibility of the of the design/build<br />

contractor to be selected for project construction. MassDOT will include special provisions in the<br />

contract documents to ensure proper handling and disposal of the dredged material<br />

The cost of the cofferdams is estimated at $7.5 million.<br />

Summary of Discharge of Fill Material (BRPWW10)<br />

The project will result in the discharge of approximately 22,300 square feet of fill material to LUO and<br />

vegetated wetlands. Approximately 17,100 square feet of fill will be discharged within LUO of the<br />

Merrimack River for the placement of the six new piers.<br />

The remaining 5,200 square feet of fill within vegetated wetlands north of the Merrimack River is<br />

associated with highway widening and drain line installation. Of the 5,200 square feet, approximately<br />

1,640 square feet will be temporary alterations associated with a work zone/construction access to<br />

build a retaining wall at Wetland H and drain line crossings at Wetland M. The remaining 3,560<br />

square feet of permanent alterations will result from the highway widening at Wetlands H and I.<br />

Temporary alterations to LUO in the Merrimack River will be approximately 28,520 square feet<br />

(excluding the footprint of the existing and proposed piers) from the installation of cofferdams around<br />

the six new permanent piers during construction, around each of the four existing <strong>Whittier</strong> <strong>Bridge</strong><br />

piers during demolition and from construction of two (2) temporary support piers during construction<br />

of the I-<strong>95</strong> northbound bridge.<br />

Avoidance and Minimization<br />

Where possible, the introduction of retaining walls was used to minimize the extent of fill.<br />

Mitigation<br />

Temporary impacts to Bordering Vegetated Wetland H (Amesbury), as well as to Isolated Vegetated<br />

Wetland M (Salisbury), will be mitigated on site at each wetland location by in-situ restoration. To<br />

mitigate for permanent impacts to vegetated wetlands H and I (3,560 square feet), the replication<br />

concept in Amesbury will consist of expanding Wetland H by excavating approximately 4,960 square<br />

feet of upland at its northern end within the right of way.<br />

The removal of the existing piers within the Merrimack River will restore approximately 10,130<br />

square feet of LUO.<br />

For work occurring in upland areas, erosion and sediment controls will be employed to minimize the<br />

transport of sediment into the existing drainage system and adjacent resource areas during<br />

construction. The BMPs to manage storm water and control the discharge of pollutants will be<br />

3-25

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!