Final Environmental Impact Report - Whittier Bridge/I-95 ...
Final Environmental Impact Report - Whittier Bridge/I-95 ... Final Environmental Impact Report - Whittier Bridge/I-95 ...
Whittier Bridge/I-95 Improvement Project FEIR Chapter 3.0: Mitigation and Commitments Exit 57 Newburyport Park-and-Ride lot through to the Ghost Trail in Salisbury (which connects to U.S. Route 1): Providing for the eventual hub connection to the Amesbury Powow Riverwalk and Salisbury Point Ghost Trail; Providing connections to existing and planned trails; and Improving access to and interconnections between Moseley Woods and Maudslay State Park and other regional recreational resources. The incorporation of the Shared-Use Path will be consistent with the USDOT Policy Statement on Bicycle and Pedestrian Accommodation Regulations and Recommendations (March 15, 2010) and MassDOT‘s GreenDOT initiatives policy. The Shared-Use Path will be constructed during all construction stages since it is directly related to the I-95 northbound bridge and roadway approach sequencing. Cost to construct the path is expected to be $8.5 million. Schedule and Cost Permanent lighting, fendering, and a navigation buoy will be constructed during the last phase of the project when bridge work is complete. Temporary aids to navigation during in-water work (42 months) will be used as needed. The cost to provide temporary and permanent navigation aids is expected to be $100,000. 3.16.6 Section 401 Water Quality Certifications – MassDEP A combined Water Quality Certification Application for the project was prepared to include: Major Project Certification for dredging and disposal of more than 5,000 cubic yards of material within the Merrimack River (BRP WW07); a Major Project Certification for the discharge of more than 5,000 square feet of fill within Land Under Ocean of the Merrimack River; and three vegetated wetlands (Series H, I and M) north of the river (BRP WW10). Summary of Dredging Activities (BRPWW07) Dredging is associated with the installation of cofferdams around the six new permanent piers during construction, around each of the four existing Whittier Bridge piers during demolition and from construction of two temporary support structures during construction of the I-95 northbound bridge. Approximately 7,150 cubic yards of material will be dredged within Land Under the Ocean (LUO) of the Merrimack River. Dredging activities are limited to the Merrimack River and will include the entire area within the cofferdams (45,620 square feet); it does not include the removal of the existing piers (10,130 square feet outside of new pier footprints), which will be considered restoration of LUO. Work within the cofferdams, outside of the footprint of the existing and proposed piers, is considered a temporary alteration to LUO and totals 28,520 square feet. Cofferdams will be constructed at each proposed pier location to provide work access and allow work to be performed in the ―dry.‖ Avoidance and Minimization Measures to minimize the suspension of solids during dredging will include conducting all dredging activities within water tight sheet pile cofferdams. Dredging will be conducted with a clamshell excavator located on a barge moored or spudded adjacent to the cofferdam. Dredged material will be allowed to drain much of the entrained water within the confines of the cofferdam before the material is deposited on a barge for transport to an intermediate facility. No open water disposal or 3-24
Whittier Bridge/I-95 Improvement Project FEIR Chapter 3.0: Mitigation and Commitments side casting of dredged material is proposed. The barge will be surrounded with silt curtains suspended from a floating boom to minimize the spread of any sediment runoff from the barge. Mitigation Measures Mitigation measures will be performed during demolition and construction activities to minimize the impacts to water quality during the in-water portion of the work associated with the construction of new bridge piers and removal of the existing piers. Cofferdams will be installed to enclose existing and new bridge piers to eliminate impacts from resuspended sediments in the water column. Locations for the disposal of dredged material will be the responsibility of the of the design/build contractor to be selected for project construction. MassDOT will include special provisions in the contract documents to ensure proper handling and disposal of the dredged material The cost of the cofferdams is estimated at $7.5 million. Summary of Discharge of Fill Material (BRPWW10) The project will result in the discharge of approximately 22,300 square feet of fill material to LUO and vegetated wetlands. Approximately 17,100 square feet of fill will be discharged within LUO of the Merrimack River for the placement of the six new piers. The remaining 5,200 square feet of fill within vegetated wetlands north of the Merrimack River is associated with highway widening and drain line installation. Of the 5,200 square feet, approximately 1,640 square feet will be temporary alterations associated with a work zone/construction access to build a retaining wall at Wetland H and drain line crossings at Wetland M. The remaining 3,560 square feet of permanent alterations will result from the highway widening at Wetlands H and I. Temporary alterations to LUO in the Merrimack River will be approximately 28,520 square feet (excluding the footprint of the existing and proposed piers) from the installation of cofferdams around the six new permanent piers during construction, around each of the four existing Whittier Bridge piers during demolition and from construction of two (2) temporary support piers during construction of the I-95 northbound bridge. Avoidance and Minimization Where possible, the introduction of retaining walls was used to minimize the extent of fill. Mitigation Temporary impacts to Bordering Vegetated Wetland H (Amesbury), as well as to Isolated Vegetated Wetland M (Salisbury), will be mitigated on site at each wetland location by in-situ restoration. To mitigate for permanent impacts to vegetated wetlands H and I (3,560 square feet), the replication concept in Amesbury will consist of expanding Wetland H by excavating approximately 4,960 square feet of upland at its northern end within the right of way. The removal of the existing piers within the Merrimack River will restore approximately 10,130 square feet of LUO. For work occurring in upland areas, erosion and sediment controls will be employed to minimize the transport of sediment into the existing drainage system and adjacent resource areas during construction. The BMPs to manage storm water and control the discharge of pollutants will be 3-25
- Page 328 and 329: 57 1 2 3 4 5 6 7 8 9 10 11 12 13 14
- Page 330 and 331: 59 1 2 3 4 5 6 7 8 9 10 11 12 13 14
- Page 332 and 333: 61 1 2 3 4 5 6 7 8 9 10 11 12 13 14
- Page 334 and 335: 63 1 2 3 4 5 6 7 8 9 10 11 12 13 14
- Page 336 and 337: 65 1 2 3 4 5 6 7 8 9 10 11 12 13 14
- Page 338 and 339: 67 1 2 3 4 5 6 7 8 9 10 11 12 13 14
- Page 340 and 341: 69 1 2 3 4 5 6 7 8 9 10 11 12 13 14
- Page 342 and 343: 71 1 2 3 4 5 6 7 8 9 10 11 12 13 14
- Page 344 and 345: 73 1 2 3 4 5 6 7 8 9 10 11 12 13 14
- Page 346 and 347: 75 1 2 3 4 5 6 7 8 9 10 11 12 13 14
- Page 348 and 349: 77 1 2 3 4 5 6 7 8 9 10 11 12 13 14
- Page 350 and 351: 79 1 2 3 4 5 6 7 8 9 10 11 12 13 14
- Page 352 and 353: 81 1 2 3 4 5 6 7 8 would appreciate
- Page 355 and 356: Whittier Bridge/I-95 Improvement Pr
- Page 357 and 358: Whittier Bridge/I-95 Improvement Pr
- Page 359 and 360: Whittier Bridge/I-95 Improvement Pr
- Page 361 and 362: Whittier Bridge/I-95 Improvement Pr
- Page 363 and 364: Whittier Bridge/I-95 Improvement Pr
- Page 365 and 366: Whittier Bridge/I-95 Improvement Pr
- Page 367 and 368: Whittier Bridge/I-95 Improvement Pr
- Page 369 and 370: Whittier Bridge/I-95 Improvement Pr
- Page 371 and 372: Whittier Bridge/I-95 Improvement Pr
- Page 373 and 374: Whittier Bridge/I-95 Improvement Pr
- Page 375 and 376: Whittier Bridge/I-95 Improvement Pr
- Page 377: Whittier Bridge/I-95 Improvement Pr
- Page 381 and 382: Whittier Bridge/I-95 Improvement Pr
- Page 383 and 384: Whittier Bridge/I-95 Improvement Pr
- Page 385 and 386: Whittier Bridge/I-95 Improvement Pr
- Page 387 and 388: Whittier Bridge/I-95 Improvement Pr
- Page 389 and 390: Whittier Bridge/I-95 Improvement Pr
- Page 391 and 392: Whittier Bridge/I-95 Improvement Pr
- Page 393: Whittier Bridge/I-95 Improvement Pr
- Page 397 and 398: Whittier Bridge/I‐95 Improvement
- Page 399 and 400: Spill Prevention and Response MassD
- Page 401: Appendix: Best Management Practices
- Page 405 and 406: The Commonwealth Of Massachusetts M
- Page 407 and 408: downstream of the existing bridge w
- Page 409 and 410: Appendix 1 - Tables 1, 2, and 3 Tab
- Page 411 and 412: Table 4. Summary of Model Simulatio
- Page 413: Whittier Bridge/I-95 Improvement Pr
- Page 416 and 417: process. If the project avoids simu
- Page 418 and 419: anadromous fish including American
- Page 420 and 421: Conclusions In summary, we recommen
<strong>Whittier</strong> <strong>Bridge</strong>/I-<strong>95</strong> Improvement Project FEIR<br />
Chapter 3.0: Mitigation and Commitments<br />
side casting of dredged material is proposed. The barge will be surrounded with silt curtains<br />
suspended from a floating boom to minimize the spread of any sediment runoff from the barge.<br />
Mitigation Measures<br />
Mitigation measures will be performed during demolition and construction activities to minimize the<br />
impacts to water quality during the in-water portion of the work associated with the construction of<br />
new bridge piers and removal of the existing piers. Cofferdams will be installed to enclose existing<br />
and new bridge piers to eliminate impacts from resuspended sediments in the water column.<br />
Locations for the disposal of dredged material will be the responsibility of the of the design/build<br />
contractor to be selected for project construction. MassDOT will include special provisions in the<br />
contract documents to ensure proper handling and disposal of the dredged material<br />
The cost of the cofferdams is estimated at $7.5 million.<br />
Summary of Discharge of Fill Material (BRPWW10)<br />
The project will result in the discharge of approximately 22,300 square feet of fill material to LUO and<br />
vegetated wetlands. Approximately 17,100 square feet of fill will be discharged within LUO of the<br />
Merrimack River for the placement of the six new piers.<br />
The remaining 5,200 square feet of fill within vegetated wetlands north of the Merrimack River is<br />
associated with highway widening and drain line installation. Of the 5,200 square feet, approximately<br />
1,640 square feet will be temporary alterations associated with a work zone/construction access to<br />
build a retaining wall at Wetland H and drain line crossings at Wetland M. The remaining 3,560<br />
square feet of permanent alterations will result from the highway widening at Wetlands H and I.<br />
Temporary alterations to LUO in the Merrimack River will be approximately 28,520 square feet<br />
(excluding the footprint of the existing and proposed piers) from the installation of cofferdams around<br />
the six new permanent piers during construction, around each of the four existing <strong>Whittier</strong> <strong>Bridge</strong><br />
piers during demolition and from construction of two (2) temporary support piers during construction<br />
of the I-<strong>95</strong> northbound bridge.<br />
Avoidance and Minimization<br />
Where possible, the introduction of retaining walls was used to minimize the extent of fill.<br />
Mitigation<br />
Temporary impacts to Bordering Vegetated Wetland H (Amesbury), as well as to Isolated Vegetated<br />
Wetland M (Salisbury), will be mitigated on site at each wetland location by in-situ restoration. To<br />
mitigate for permanent impacts to vegetated wetlands H and I (3,560 square feet), the replication<br />
concept in Amesbury will consist of expanding Wetland H by excavating approximately 4,960 square<br />
feet of upland at its northern end within the right of way.<br />
The removal of the existing piers within the Merrimack River will restore approximately 10,130<br />
square feet of LUO.<br />
For work occurring in upland areas, erosion and sediment controls will be employed to minimize the<br />
transport of sediment into the existing drainage system and adjacent resource areas during<br />
construction. The BMPs to manage storm water and control the discharge of pollutants will be<br />
3-25