27.01.2015 Views

Final Environmental Impact Report - Whittier Bridge/I-95 ...

Final Environmental Impact Report - Whittier Bridge/I-95 ...

Final Environmental Impact Report - Whittier Bridge/I-95 ...

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Whittier</strong> <strong>Bridge</strong>/I-<strong>95</strong> Improvement Project FEIR<br />

Chapter 3.0: Mitigation and Commitments<br />

<strong>Bridge</strong> Configuration (including design standards/complexities, structural safety,<br />

constructability, context sensitive structures, maintenance and inspection and life cycle/cost);<br />

<br />

<br />

<br />

<br />

<br />

<br />

Traffic (including travel time, level of service, and capacity);<br />

Right-of-Way (including fee taking, permanent easement and temporary/construction<br />

easement);<br />

Cost (the relative cost differences of each alternative considering constructability, site access,<br />

construction staging ease/restraints, traffic management, ease of demolition, and schedule<br />

impact because of extended construction);<br />

Construction (including utility relocation, constructability/demolition of existing structures, and<br />

maintenance of traffic during construction);<br />

Schedule (the relative difference between alternatives for the estimated construction schedule<br />

duration of each alternative); and<br />

<strong>Environmental</strong> (including stormwater [ability of each alternative to meet MassDEP stormwater<br />

performance standards], drinking water quality [the degree of impact on local drinking water<br />

supply protection areas], wetlands [total estimated impact to wetland resource areas within the<br />

project area], visual/viewpoints [the level of visual impact], historic [potential impact on the<br />

historic <strong>Whittier</strong> <strong>Bridge</strong>] and navigation [potential impacts to navigation on the Merrimack River]).<br />

After a thorough evaluation of the river crossing and highway widening alternatives, the New 8-Lane<br />

East <strong>Bridge</strong> River Crossing Alternative and the Inside Widening Highway Alternative (Northern<br />

Terminus to Route 286) were identified as the Preferred Alternative. This alternative best met the<br />

purpose and need, as well as highway configuration, traffic (capacity), bridge configuration (design<br />

standards, structural safety, maintenance and inspection, and life cycle/costs), construction<br />

(constructability), ROW, and environmental criteria.<br />

3.16.5 Chapter 91 Waterways – MassDEP<br />

Construction Term Navigation<br />

During construction of the new bridge crossing, there would be barges, falsework, work platforms,<br />

staging, and/or cofferdams constructed in the waterway in conjunction with constructing the<br />

permanent bridge structures and demolishing the existing bridge. The type of temporary system will<br />

be determined by the final design of the substructure and superstructure; however, the project<br />

specifications will include provisions that the contractor must follow to ensure that navigation<br />

beneath the bridges will be maintained, except for those circumstances where limited closures will<br />

occur for public safety purposes. The directives will include: staging plans showing zones where<br />

barges and equipment will be allowed to operate during each phase of construction and demolition;<br />

locations where equipment could be moored or stored while not in use; provisions for temporary aids<br />

to navigation, including temporary lighting; establishing temporary routes for marine traffic; and, most<br />

importantly, timely notices to mariners throughout the construction and demolition duration. The<br />

contractor will be required to prepare a navigation plan for review and approval by the USCG,<br />

USACE, harbormasters, boating community, and other marine interests. The plan will address<br />

methods to minimize impacts to all mariners, management of vessel traffic and overall safety issues.<br />

Temporary closures of the waterway could be required for safety reasons; however, since there are<br />

two channels, it is anticipated that the contractor will be able to maintain one channel at all times<br />

during construction and demolition. If there are instances when both channels must be temporarily<br />

closed for safety purposes or the channel that can only accommodate a larger vessel is closed, the<br />

3-22

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!