Final Environmental Impact Report - Whittier Bridge/I-95 ...
Final Environmental Impact Report - Whittier Bridge/I-95 ... Final Environmental Impact Report - Whittier Bridge/I-95 ...
Street Culvert. The City of Amesbury and the Commonwealth of Massachusetts have invested millions of dollars in the infrastructure of Elm Street and Route 110 including upgrading ofculverts at these locations in the last ten years. The design ofthese culverts did not incorporate additional flow from an expanded 1-95. 2. Massachusetts Department of Environmental Protection (MADEP) has indicated to the Amesbury Conservation Commission that a significant wet meadow is present within the Golden Triangle area adjacent to the 1-95 corridor between Exit 58 (Route 110) and the Intersection of 1-495 and 1-95. The city requests that the applicant provide additional information on possible impacts to the wet meadow from the increase ofthe pre-development watershed water volume to the post development watershed water volume and the subsequent decrease ofpeak flow to this area. The change in duration and quantity offlooding over time could have a detrimental effect on the conditions of the wet meadow. Reportedly, MADEP has indicated that this type of wet meadow is becoming increasingly rare within the Commonwealth. , , 3. While the storm water management plan will attenuate the peak runoff flows for the drainage system that runs through the Golden Triangle area, will the addition to the overall volume of water within the watershed, due to the increased duration of the water flow, be significant enough to cause a shift in the characteristics of the existing intermittent stream If the volume ofwater were to cause the intermittent stream to be reclassified as a perennial stream, then the Golden Triangle area would become significantly less viable for development potential. 4. Within the DEIR, the applicant indicates that two storm water basins (Basins 3A and 3B) are to be constructed directly behind Martignetti Enterprises, Inc., at 32 Merrill Street Extension. The ground surface behind the building appears to be sloping down from 1-95 to the back of the existing building. Basin 3B is proposed to be an extended detention basin and Basin 3A is proposed to be an infiltration basin. Has the applicant given thought as to what effects these basins may have on the Martignetti property during construction and with the operation and maintenance of the basins Given that the area is shallow to bedrock they are likely to be detrimentally impacted by the increased groundwater. 5. The DEIR indicates that there will be a Wetlands Mitigation Area constructed in the upland area just north ofWetlands H (located just south ofthe Salisbury off-ramp to Route Ilo-Exit 58). The excavated 4,950 SF of soil appears to create a significant slope adjacent to the location where the Shared Use Path starts to veer off to the Old Merrill Street access point and also where the modifications to the existing Exit 58 off-ramp are proposed. The city requests that the applicant review the slope soil conditions for possible stability issues during and after construction, whether or not the mitigation area is going to provide additional storm water storage, and what effects this mitigation/storage area will have (ifany) on the abutting private property. 6. The DEIR indicates that Wetland I may be hydraulically linked to a larger wetland system on the east side of Merrill Street, however no apparent connection was observed (Page 4-47 of DEIR). The wetland to the east ofMerrill Street is tidally influenced and ifthe two wetlands
are connected are there any other precautions that need to be taken to protect the wetland, the retaining walls to be constructed, or to maintain the wetlands after construction 7. The operations and maintenance of the proposed stormwater system is a significant concern to the city as most ofthe storm water basins and outlets appear to be difficult to access from areas other than the highway itself. Has an appropriate Stormwater Operation and Maintenance Manual been developed for the entire project and will they be provided to the abutting communities 8. In the DEIR, MassDOT indicates that the Route 15O-Hillside and Sparhawk Roadway Reconstruction Project, the Hines Bridge and Route 110 Widening Projects are to be completed prior to the commencement ofconstruction on the Whittier Bridge. MassDOT has not provided to the city project completion timelines for the Route 110 Widening and the Hines Bridge Construction. Additionally, the Reconstruction of Route 15O-Hillside and Sparhawk Streets has been shifted in the Merrimack Valley Planning Commissitm Transportation Improvement Program and is scheduled for construction in 2015. Knowing that the Whittier Bridge project needs to be completed by the end of 2016, has MassDOT reviewed the traffic impacts that could arise if these other projects are not completed in a timely manner 9. The DEIR indicates there will be no offsite traffic impacts on neighboring roadways or arterials and that all traffic will remain within the existing corridor. The DEIR references the use of signage to direct motorists to roadway detours during construction, indicating that traffic may be diverted to other routes. It is a concern that traffic will seek alternate routes resulting from backups during construction as speeds are reduced in the construction zones and drivers must make lane shifts as the project construction is phased. This could cause traffic impacts to other roads such as Route 110 in Amesbury and Salisbury and Route 1 in Newburyport and Salisbury. Thank you for your consideration ofthese matters. ~ iN'.r--;;;- Thatcher W. Kezer III Mayor Enclosure
- Page 177 and 178: EEA#14427 DEIR Certificate December
- Page 179 and 180: EEA#I4427 DEIR Certificate December
- Page 181 and 182: EEA#I4427 DEIR Certificate December
- Page 183 and 184: EEA#I4427 DEIR Certificate December
- Page 185 and 186: EEA#14427 DEIR Certificate December
- Page 187 and 188: EEA#I4427 DEIR Certificate December
- Page 189: EEA#I4427 DEIR Certificate December
- Page 192 and 193: Thank you for the opportunity to co
- Page 194 and 195: Thank you for the opportunity to co
- Page 196 and 197: ESSEX NATIONAL HERITAGE COMMISSION
- Page 198 and 199: In the period leading up to the sub
- Page 200 and 201: construction is not adequate to ens
- Page 202 and 203: to limit turbidity impact from dewa
- Page 204 and 205: For infiltration basin and trench s
- Page 206 and 207: not acceptable to meet regulatory r
- Page 208 and 209: ide lot that is also being expanded
- Page 210 and 211: MassWi/d/ile December 20, 2011 Comm
- Page 212 and 213: Patel, Purvi {_E_EA .... } _ From:
- Page 214 and 215: process. Ifthe project avoids simul
- Page 216 and 217: THE COMMONWEALTH OF MASSACHUSETTS E
- Page 218: imack Valley ning Commission plan *
- Page 227: Mayor Thatcher w. Kezer III Town Ha
- Page 231 and 232: Revised 12/19/11 Town ofSalisbury's
- Page 233 and 234: Neil J. Harrington Town Manager Tow
- Page 235 and 236: Secretary Richard K. Sullivan, Jr.
- Page 237 and 238: Coastal Trails Coalition December 2
- Page 240 and 241: Patel. Purvi~ _ From: Sent: To: Cc:
- Page 242 and 243: 1. The Whittier Bridge Replacement
- Page 244 and 245: Whittier Bridge and 1-95 reconstruc
- Page 246 and 247: forested and open character, though
- Page 248: Thank you for the opportunity to co
- Page 252 and 253: On the cost front, we are in an eco
- Page 254 and 255: 42 Prospect Street Newburyport, Mas
- Page 256 and 257: 12-~:TII ~~.. MASSACHUSETTSHIGHWAYD
- Page 258 and 259: Patel. Purvi~ _ From: Sent: To: Cc:
- Page 260 and 261: argument or disagreement. We have p
- Page 262 and 263: Patel. Purvi (.... E_EA .... ) _ Fr
- Page 264 and 265: TO: Pamela S. Stephensen, Division
- Page 266 and 267: Patel, Purvi ~ ...... _ From: Sent:
- Page 268 and 269: TO: Pamela S. Stephenson, Division
- Page 272 and 273: PUBLIC MEETING WEDNESDAY, DECEMBER
- Page 274 and 275: 3 SPEAKER INDEX Name Page Karen Eme
- Page 276 and 277: 5 1 2 3 4 5 6 7 8 9 10 11 12 13 14
are connected are there any other precautions that need to be taken to protect the wetland, the<br />
retaining walls to be constructed, or to maintain the wetlands after construction<br />
7. The operations and maintenance of the proposed stormwater system is a significant concern<br />
to the city as most ofthe storm water basins and outlets appear to be difficult to access from<br />
areas other than the highway itself. Has an appropriate Stormwater Operation and<br />
Maintenance Manual been developed for the entire project and will they be provided to the<br />
abutting communities<br />
8. In the DEIR, MassDOT indicates that the Route 15O-Hillside and Sparhawk Roadway<br />
Reconstruction Project, the Hines <strong>Bridge</strong> and Route 110 Widening Projects are to be<br />
completed prior to the commencement ofconstruction on the <strong>Whittier</strong> <strong>Bridge</strong>. MassDOT has<br />
not provided to the city project completion timelines for the Route 110 Widening and the<br />
Hines <strong>Bridge</strong> Construction. Additionally, the Reconstruction of Route 15O-Hillside and<br />
Sparhawk Streets has been shifted in the Merrimack Valley Planning Commissitm<br />
Transportation Improvement Program and is scheduled for construction in 2015. Knowing<br />
that the <strong>Whittier</strong> <strong>Bridge</strong> project needs to be completed by the end of 2016, has MassDOT<br />
reviewed the traffic impacts that could arise if these other projects are not completed in a<br />
timely manner<br />
9. The DEIR indicates there will be no offsite traffic impacts on neighboring roadways or<br />
arterials and that all traffic will remain within the existing corridor. The DEIR references the<br />
use of signage to direct motorists to roadway detours during construction, indicating that<br />
traffic may be diverted to other routes. It is a concern that traffic will seek alternate routes<br />
resulting from backups during construction as speeds are reduced in the construction zones<br />
and drivers must make lane shifts as the project construction is phased. This could cause<br />
traffic impacts to other roads such as Route 110 in Amesbury and Salisbury and Route 1 in<br />
Newburyport and Salisbury.<br />
Thank you for your consideration ofthese matters.<br />
~ iN'.r--;;;-<br />
Thatcher W. Kezer III<br />
Mayor<br />
Enclosure