13.11.2012 Views

Download - Mammoet BV

Download - Mammoet BV

Download - Mammoet BV

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Offloading, Transporting and Positioning<br />

“<strong>Mammoet</strong> used<br />

a different route<br />

this time”<br />

LOCATION: JUBAIL, SAUDI ARABIA<br />

JOB: TRANSPORTING AND<br />

INSTALLING EVAPORATORS<br />

CHALLENGE: COMPLEXITY<br />

<strong>Mammoet</strong> was awarded four main contracts, heavy lifting,<br />

onsite heavy haul, general crane and module transport<br />

along with several sub-contracts for the expansion of<br />

the Scotford Upgrader Expansion 1 project at Fort<br />

Saskatchewan. This project will double the refinery’s<br />

upgrading capacity. <strong>Mammoet</strong>’s work included offloading,<br />

transporting and positioning ten 500 ton reactor sections<br />

so that they could be welded in pairs. We used a 750-ton<br />

J&R Lift’N’Lock unit, jack and slide equipment and 24<br />

lines of SPMTs for this. <strong>Mammoet</strong> also built a new strand<br />

jack tower gantry to erect the completed 1,000 ton reactors.<br />

These towers are based on the same design used in<br />

Houston so that all <strong>Mammoet</strong> towers in North America are<br />

interchangeable. <strong>Mammoet</strong> used the RK-8500 to erect the<br />

tower system and to tail the reactors. This project reached<br />

its peak towards the end of 2008. At peak times <strong>Mammoet</strong><br />

had over fifty cranes and some 90 of their employees on<br />

site, as well as SPMTs, Scheuerle trailers, etc.<br />

Reactors for a French Refinery<br />

<strong>Mammoet</strong> France was contracted by an oil company to offload two 308 ton reactors, transport<br />

them to the refinery and install them. <strong>Mammoet</strong> had worked at this refinery before but because<br />

of the congested site and to avoid the need to prepare roads <strong>Mammoet</strong> used a different route<br />

this time. This meant crossing a relatively weak railway bridge where <strong>Mammoet</strong> installed a<br />

temporally overbridge. <strong>Mammoet</strong> then installed the two reactors in one day with a brand new<br />

CC 2800 and a CC 2400 as the tailing crane.<br />

Desalination Plant<br />

One of <strong>Mammoet</strong>’s clients is building a desalination plant at<br />

Jubail, Saudi Arabia. The plant will include fourteen evaporators,<br />

weighing 1,520 tons each, which are fabricated in Sharjah, UAE.<br />

<strong>Mammoet</strong>’s scope of work includes: engineering and execution<br />

of load-out, design and fabrication of intermediate supports,<br />

design and fabrication of all grillage and sea fastening works,<br />

supply of marine spread, towage from UAE to Jubail, load-in,<br />

transport to site by SPMT and installation onto foundation.<br />

Despite challenges related to the weather and site restrictions<br />

the work was progressing well. The duration of the project was<br />

one year and <strong>Mammoet</strong> used 68 axle lines of SPMTs, four power<br />

pack units and a range of auxiliary equipment.<br />

Petrochemical<br />

LOCATION: FORT SASKATCHEWAN,<br />

ALBERTA, CANADA<br />

JOB: HEAVY LIFTING AND HAULING<br />

CHALLENGE: SCALE OF THE PROJECT<br />

“ Built a new<br />

strand jack<br />

tower gantry”<br />

LOCATION: PORT-JÉRÔME, FRANCE<br />

JOB: TRANSPORTING AND LIFTING TWO<br />

REACTORS<br />

CHALLENGE: WEAK BRIDGE

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!