You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
LOCATION: SINGAPORE<br />
JOB: INSTALLING COLUMNS<br />
AT A PETROCHEMICAL PLANT<br />
CHALLENGE: SCALE OF THE PROJECT<br />
“The first job<br />
in Singapore<br />
for the 1600-ton<br />
PTC ring crane”<br />
“A true cultural<br />
melting pot with<br />
people of all<br />
nationalities and<br />
skills working<br />
together”<br />
LOCATION: FORT MCMURRAY,<br />
ALBERTA, CANADA<br />
JOB: HEAVY LIFTS AND TRANSPORT<br />
CHALLENGE: TEMPERATURES DOWN<br />
TO -47˚C<br />
Petrochemical<br />
Transporting and Lifting Eleven Columns<br />
First Expansion Albian Sands<br />
<strong>Mammoet</strong>’s client is expanding its Albian<br />
Sands upstream facility which processes oil<br />
sand. The main purpose of the facility is the<br />
processing of mined oil sand into a pipeline<br />
transportable liquid which is then fed to the<br />
Scotford facility near Edmonton, Alberta for<br />
refinement. <strong>Mammoet</strong> started working on<br />
this project in August 2007. The scope of<br />
the work includes transporting and erecting<br />
some 310 oversized loads ranging from<br />
tanks and pipe modules right up to 450 ton<br />
vessels. <strong>Mammoet</strong> has a range of cranes,<br />
trailers and other equipment on site to<br />
cover all the client’s needs. The highlight so<br />
far was transporting the TSRU columns<br />
with a diameter of eleven meters which,<br />
with all the equipment, had a total combined<br />
weight of 726 tons. This region of<br />
Canada is a true cultural melting pot with<br />
people of all nationalities and skills working<br />
together. Working on a project which has<br />
so many variables is a daily challenge.<br />
Throw into the mix the impending -47˚C<br />
Fort McMurray winter and you have a job<br />
which is never the same two days in a row.<br />
Over a period of 18 months, <strong>Mammoet</strong> has<br />
been busy transporting and lifting eleven<br />
large columns. <strong>Mammoet</strong> used a number<br />
of cranes (PTC I, CC 4800, two units<br />
CC 1800, CC 2400-1, LR 1350) and SPMTs.<br />
It was also the first job in Singapore for the<br />
1600-ton PTC ring crane which was fitted<br />
with a 87 meter main boom and 39.4 meter<br />
jib to erect a propylene fractionator column<br />
which stood 106 meters tall.<br />
After the PTC had been rigged we used 72<br />
lines of SPMTs to move it to the first job<br />
site. Because of heavy rain the ground on<br />
the site was very soft. To avoid taking any<br />
risks, <strong>Mammoet</strong> first tested the road<br />
by driving SPMTs loaded with superlift<br />
counterweights across it. That was<br />
just as well, as it turned out that the<br />
ground needed more preparation.<br />
<strong>Mammoet</strong> discovered that the<br />
columns were actually rather heavier<br />
than specified. In most cases this<br />
was not a problem as the equipment<br />
had plenty of spare capacity.<br />
However, the heaviest column had<br />
to be stripped of some metalwork<br />
before we could safely lift it.