13.11.2012 Views

Download - Mammoet BV

Download - Mammoet BV

Download - Mammoet BV

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

LOCATION: SINGAPORE<br />

JOB: INSTALLING COLUMNS<br />

AT A PETROCHEMICAL PLANT<br />

CHALLENGE: SCALE OF THE PROJECT<br />

“The first job<br />

in Singapore<br />

for the 1600-ton<br />

PTC ring crane”<br />

“A true cultural<br />

melting pot with<br />

people of all<br />

nationalities and<br />

skills working<br />

together”<br />

LOCATION: FORT MCMURRAY,<br />

ALBERTA, CANADA<br />

JOB: HEAVY LIFTS AND TRANSPORT<br />

CHALLENGE: TEMPERATURES DOWN<br />

TO -47˚C<br />

Petrochemical<br />

Transporting and Lifting Eleven Columns<br />

First Expansion Albian Sands<br />

<strong>Mammoet</strong>’s client is expanding its Albian<br />

Sands upstream facility which processes oil<br />

sand. The main purpose of the facility is the<br />

processing of mined oil sand into a pipeline<br />

transportable liquid which is then fed to the<br />

Scotford facility near Edmonton, Alberta for<br />

refinement. <strong>Mammoet</strong> started working on<br />

this project in August 2007. The scope of<br />

the work includes transporting and erecting<br />

some 310 oversized loads ranging from<br />

tanks and pipe modules right up to 450 ton<br />

vessels. <strong>Mammoet</strong> has a range of cranes,<br />

trailers and other equipment on site to<br />

cover all the client’s needs. The highlight so<br />

far was transporting the TSRU columns<br />

with a diameter of eleven meters which,<br />

with all the equipment, had a total combined<br />

weight of 726 tons. This region of<br />

Canada is a true cultural melting pot with<br />

people of all nationalities and skills working<br />

together. Working on a project which has<br />

so many variables is a daily challenge.<br />

Throw into the mix the impending -47˚C<br />

Fort McMurray winter and you have a job<br />

which is never the same two days in a row.<br />

Over a period of 18 months, <strong>Mammoet</strong> has<br />

been busy transporting and lifting eleven<br />

large columns. <strong>Mammoet</strong> used a number<br />

of cranes (PTC I, CC 4800, two units<br />

CC 1800, CC 2400-1, LR 1350) and SPMTs.<br />

It was also the first job in Singapore for the<br />

1600-ton PTC ring crane which was fitted<br />

with a 87 meter main boom and 39.4 meter<br />

jib to erect a propylene fractionator column<br />

which stood 106 meters tall.<br />

After the PTC had been rigged we used 72<br />

lines of SPMTs to move it to the first job<br />

site. Because of heavy rain the ground on<br />

the site was very soft. To avoid taking any<br />

risks, <strong>Mammoet</strong> first tested the road<br />

by driving SPMTs loaded with superlift<br />

counterweights across it. That was<br />

just as well, as it turned out that the<br />

ground needed more preparation.<br />

<strong>Mammoet</strong> discovered that the<br />

columns were actually rather heavier<br />

than specified. In most cases this<br />

was not a problem as the equipment<br />

had plenty of spare capacity.<br />

However, the heaviest column had<br />

to be stripped of some metalwork<br />

before we could safely lift it.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!