Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
“We combined<br />
the SPMTs with a<br />
gantry system”<br />
LOCATION: PIERREFITTE NEAR PARIS,<br />
FRANCE<br />
JOB: REPLACING A RAILWAY BRIDGE<br />
CHALLENGE: NARROW SITE, NEW<br />
SPMT/GANTRY/STRAND JACK RIG<br />
“This was the first<br />
time <strong>Mammoet</strong> had<br />
used this rig”<br />
A1 Junction Upgrade Peterborough to Blyth<br />
<strong>Mammoet</strong> installed a composite bridge<br />
deck (650 tons) as part of the A1 Junction<br />
upgrade project. This was the second<br />
bridge of four that <strong>Mammoet</strong> has been<br />
contracted to install. <strong>Mammoet</strong> first jacked<br />
the bridge up from a relatively low build<br />
position to the installation height in a laydown<br />
area adjacent to the permanent<br />
position for the bridge. Once at the correct<br />
height, the SPMTs with packing supports<br />
lifted the bridge free from the jacking<br />
towers. The period available for installation<br />
started at nine pm on Saturday and<br />
finished at twelve noon on Sunday. The<br />
bridge was installed onto the abutments at<br />
twelve midnight. <strong>Mammoet</strong> completed its<br />
South Africa will host the Soccer World<br />
Cup in 2010 and is busy upgrading and<br />
building stadiums for the tournament.<br />
The construction work is under real time<br />
pressure, especially as the country will be<br />
hosting the Confederation Cup in 2009.<br />
<strong>Mammoet</strong> Southern Africa is currently<br />
busy placing 4,215 precast concrete<br />
elements, including 1,560 seating units, in<br />
the new Green Point Stadium in Cape<br />
Town, in a joint venture with a local civil<br />
engineering contractor. The work started<br />
in December 2007 should be completed in<br />
December 2008. The work on the lowest<br />
tier was done with a crawler crane<br />
provided by the joint venture partner.<br />
The seating units in the middle tier were<br />
work ahead of schedule which allowed<br />
the road to be re-opened earlier than<br />
planned.<br />
In order to get permission for the closure<br />
of the A1, <strong>Mammoet</strong> had to reduce the<br />
requested closure time of 36 hours to 18<br />
hours. Consequently, many <strong>Mammoet</strong><br />
employees had to work double shifts.<br />
Despite a few last minute changes by the<br />
local authorities, <strong>Mammoet</strong> still managed<br />
to complete the work ahead of schedule.<br />
This was a particularly difficult operation<br />
due to the significant elevation changes<br />
along the transport route and the hydraulic<br />
stroke required for set down.<br />
In the Shadow of Table Mountain<br />
placed with an LR 1400 in a straight<br />
crawler configuration and the units in the<br />
upper tier with the LR 1400 in Super Lift<br />
configuration as the radius was as much<br />
as 64 meters. <strong>Mammoet</strong> Southern Africa<br />
also provided supervision and two rigging<br />
crews. The large number of units to be<br />
placed and the presence of many tower<br />
cranes on the site make this quite a<br />
challenging job. <strong>Mammoet</strong> Southern Africa<br />
was also contracted by the roofing<br />
contractor to lift compression ring<br />
segments with a mass of up to 23 tons<br />
at a radius of up to 84 meters. This<br />
was done with the LR 1400/2 fitted with<br />
a 56 meter main boom, 63 meter luffing<br />
jib and Super Lift.<br />
LOCATION: A1 ROAD, ENGLAND<br />
JOB: INSTALLING A BRIDGE DECK<br />
CHALLENGE: CHANGES IN ELEVATION<br />
Replacing a Railway Bridge Near Paris<br />
In August the French railway operator shut a<br />
railway line down for 82 hours to replace a<br />
bridge across the RN1 road at Pierrefitte near<br />
Paris. <strong>Mammoet</strong> started by removing the old<br />
bridge (400 tons, 29 meters) and taking it to<br />
a storage site. After that we installed two<br />
precast abutments (370 and 430 tons). Finally<br />
we installed the new precast bridge (780 tons,<br />
37 meters). We used two sets of 22 lines<br />
of SPMTs and paid special attention to<br />
synchronizing them. To handle the abutments<br />
we combined the SPMTs with a gantry<br />
system fitted with four 300-ton strand jacks.<br />
This was the first time <strong>Mammoet</strong> had used<br />
Civil<br />
this rig and it did a great job on the<br />
narrow site and within the short time<br />
available. The customer had not used<br />
this construction method before but<br />
was impressed and will use it for<br />
future projects.<br />
LOCATION: CAPE TOWN, SOUTH AFRICA<br />
JOB: PLACING 4,215 PRECAST<br />
CONCRETE ELEMENTS<br />
CHALLENGE: HIGH FREQUENCY<br />
LIFTING OPERATIONS, CONGESTED SITE