13.11.2012 Views

Download - Mammoet BV

Download - Mammoet BV

Download - Mammoet BV

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

“We combined<br />

the SPMTs with a<br />

gantry system”<br />

LOCATION: PIERREFITTE NEAR PARIS,<br />

FRANCE<br />

JOB: REPLACING A RAILWAY BRIDGE<br />

CHALLENGE: NARROW SITE, NEW<br />

SPMT/GANTRY/STRAND JACK RIG<br />

“This was the first<br />

time <strong>Mammoet</strong> had<br />

used this rig”<br />

A1 Junction Upgrade Peterborough to Blyth<br />

<strong>Mammoet</strong> installed a composite bridge<br />

deck (650 tons) as part of the A1 Junction<br />

upgrade project. This was the second<br />

bridge of four that <strong>Mammoet</strong> has been<br />

contracted to install. <strong>Mammoet</strong> first jacked<br />

the bridge up from a relatively low build<br />

position to the installation height in a laydown<br />

area adjacent to the permanent<br />

position for the bridge. Once at the correct<br />

height, the SPMTs with packing supports<br />

lifted the bridge free from the jacking<br />

towers. The period available for installation<br />

started at nine pm on Saturday and<br />

finished at twelve noon on Sunday. The<br />

bridge was installed onto the abutments at<br />

twelve midnight. <strong>Mammoet</strong> completed its<br />

South Africa will host the Soccer World<br />

Cup in 2010 and is busy upgrading and<br />

building stadiums for the tournament.<br />

The construction work is under real time<br />

pressure, especially as the country will be<br />

hosting the Confederation Cup in 2009.<br />

<strong>Mammoet</strong> Southern Africa is currently<br />

busy placing 4,215 precast concrete<br />

elements, including 1,560 seating units, in<br />

the new Green Point Stadium in Cape<br />

Town, in a joint venture with a local civil<br />

engineering contractor. The work started<br />

in December 2007 should be completed in<br />

December 2008. The work on the lowest<br />

tier was done with a crawler crane<br />

provided by the joint venture partner.<br />

The seating units in the middle tier were<br />

work ahead of schedule which allowed<br />

the road to be re-opened earlier than<br />

planned.<br />

In order to get permission for the closure<br />

of the A1, <strong>Mammoet</strong> had to reduce the<br />

requested closure time of 36 hours to 18<br />

hours. Consequently, many <strong>Mammoet</strong><br />

employees had to work double shifts.<br />

Despite a few last minute changes by the<br />

local authorities, <strong>Mammoet</strong> still managed<br />

to complete the work ahead of schedule.<br />

This was a particularly difficult operation<br />

due to the significant elevation changes<br />

along the transport route and the hydraulic<br />

stroke required for set down.<br />

In the Shadow of Table Mountain<br />

placed with an LR 1400 in a straight<br />

crawler configuration and the units in the<br />

upper tier with the LR 1400 in Super Lift<br />

configuration as the radius was as much<br />

as 64 meters. <strong>Mammoet</strong> Southern Africa<br />

also provided supervision and two rigging<br />

crews. The large number of units to be<br />

placed and the presence of many tower<br />

cranes on the site make this quite a<br />

challenging job. <strong>Mammoet</strong> Southern Africa<br />

was also contracted by the roofing<br />

contractor to lift compression ring<br />

segments with a mass of up to 23 tons<br />

at a radius of up to 84 meters. This<br />

was done with the LR 1400/2 fitted with<br />

a 56 meter main boom, 63 meter luffing<br />

jib and Super Lift.<br />

LOCATION: A1 ROAD, ENGLAND<br />

JOB: INSTALLING A BRIDGE DECK<br />

CHALLENGE: CHANGES IN ELEVATION<br />

Replacing a Railway Bridge Near Paris<br />

In August the French railway operator shut a<br />

railway line down for 82 hours to replace a<br />

bridge across the RN1 road at Pierrefitte near<br />

Paris. <strong>Mammoet</strong> started by removing the old<br />

bridge (400 tons, 29 meters) and taking it to<br />

a storage site. After that we installed two<br />

precast abutments (370 and 430 tons). Finally<br />

we installed the new precast bridge (780 tons,<br />

37 meters). We used two sets of 22 lines<br />

of SPMTs and paid special attention to<br />

synchronizing them. To handle the abutments<br />

we combined the SPMTs with a gantry<br />

system fitted with four 300-ton strand jacks.<br />

This was the first time <strong>Mammoet</strong> had used<br />

Civil<br />

this rig and it did a great job on the<br />

narrow site and within the short time<br />

available. The customer had not used<br />

this construction method before but<br />

was impressed and will use it for<br />

future projects.<br />

LOCATION: CAPE TOWN, SOUTH AFRICA<br />

JOB: PLACING 4,215 PRECAST<br />

CONCRETE ELEMENTS<br />

CHALLENGE: HIGH FREQUENCY<br />

LIFTING OPERATIONS, CONGESTED SITE

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!