Skidding 5% Downhill<br />
A Chinese yard had to move a<br />
Floating Production Storage and<br />
Offloading module (FPSO) across<br />
its slipway and appointed <strong>Mammoet</strong><br />
Singapore as the skidding contractor.<br />
What was special about this project<br />
was that the slipway had a downwards<br />
slope of 5%. Hence it was a<br />
real challenge to control the movement<br />
of the 5,200 ton module.<br />
Basically, we had to make sure that<br />
the module did not slide down the<br />
incline uncontrollably. After some<br />
careful experiments and adjustments<br />
to the push-pull units<br />
the multinational <strong>Mammoet</strong> crew<br />
developed an effective procedure.<br />
Even so, they could only move the<br />
module at half the normal speed.<br />
Return to Caspian Sea<br />
“ It was a real<br />
challenge to<br />
control the<br />
movement of the<br />
5,200 ton module”<br />
After the cold winter, <strong>Mammoet</strong> returned to the Caspian Sea. As the equipment<br />
<strong>Mammoet</strong> had left on site had been specially treated for winter storage, <strong>Mammoet</strong> first<br />
had to prepare it for use.<br />
The first lift was of a module with a weight of 3,480 tons. Moving the module between<br />
the piles (which we had installed before winter), connecting it to the strand jacks and<br />
raising it up took thirteen hours. This was the fifth of a series of fourteen modules which<br />
<strong>Mammoet</strong> will be installing.<br />
<strong>Mammoet</strong> used their special containerized strand jacks for this project. Each unit<br />
consists of two containers, one with two strand jacks and the power pack, and one<br />
with drums for the wire rope. These containers are placed on the piles and then pull the<br />
modules up and hold them in position while they are welded to the piles.<br />
Offshore<br />
LOCATION: NANTONG, JIANGSU, CHINA<br />
JOB: SKIDDING A FPSO<br />
CHALLENGE: GOING DOWN AN INCLINE<br />
“ Special<br />
containerized<br />
strand jacks for<br />
this project”<br />
LOCATION: CASPIAN SEA,<br />
KAZAKHSTAN<br />
JOB: INSTALLING OFFSHORE MODULES<br />
CHALLENGE: DIFFICULT ENVIRONMENT