You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Record for <strong>Mammoet</strong> Dubai<br />
Turnaround at Leuna<br />
After two years of planning, the refinery in Leuna was shut<br />
down in May 2008 for a turnaround and expansion, involving<br />
3,300 people working on the site. <strong>Mammoet</strong> Germany provided<br />
no fewer than 70 cranes, from its own fleet, another<br />
German crane company and from <strong>Mammoet</strong> in the<br />
Netherlands. <strong>Mammoet</strong> Germany managed this project using<br />
the dedicated <strong>Mammoet</strong> Shutdown Concept. This involved a<br />
LOCATION: LEUNA, GERMANY<br />
JOB: SUPPORTING A TURNAROUND<br />
CHALLENGE: SCALE OF THE PROJECT<br />
“The project went<br />
smoothly thanks<br />
to the thorough<br />
preparation and<br />
good cooperation”<br />
<strong>Mammoet</strong> Dubai transported its heaviest item<br />
ever, a 1,605 ton xylene column with a length<br />
of almost 100 meters. It was transported four<br />
kilometers from Sohar Port to an Aromatics Plant<br />
in Sohar Industrial Area in the Sultanate of Oman.<br />
The contract covered a total of 43 items which<br />
were transported by SPMTs. Because of the size<br />
of the loads, traffic signs and lampposts had to<br />
be removed along the route. Later <strong>Mammoet</strong><br />
has re-positioned the xylene column under the<br />
gantry for final installation. The whole project was<br />
completed successfully and safely.<br />
great deal of coordination with the site operator and the<br />
contractors working on the site. <strong>Mammoet</strong> was on site for<br />
several weeks and the project went smoothly thanks to the<br />
thorough preparation and good cooperation between the<br />
German and Dutch crews. The highest lift was the replacement<br />
of a 5.5 ton flare top at a height of 145 meters.<br />
Brazilian Record With<br />
MSG-80 Configuration<br />
<strong>Mammoet</strong> spent four months on a site in Brazil, with up to fifteen of<br />
their people from branches throughout the world. <strong>Mammoet</strong> had to<br />
install three towers: two of 60 meters and 250 tons and one of 110<br />
meters and 700 tons.<br />
The real challenge was to install the 110 meter polypropylene tower<br />
after it had been fitted with all the platforms, stairs, risers, pipes,<br />
insulation etc. <strong>Mammoet</strong> decided to use their MSG-80 II and the<br />
Dracula Tail Frame. Given the needs of the job <strong>Mammoet</strong> had to rig<br />
it with a 92.6 meter main boom and 42.9 meter jib. As the tower was<br />
resting on six saddles supported by concrete blocks <strong>Mammoet</strong> first<br />
had jack it up 2.5 meters to remove the saddles and to install the tail<br />
frame on the skirt. <strong>Mammoet</strong> set the record for the tallest lift by a<br />
single crane in Brazil.<br />
Petrochemical<br />
LOCATION: SOHAR, OMAN<br />
JOB: TRANSPORTING HEAVY COLUMNS<br />
CHALLENGE: WEIGHT OF THE LOAD<br />
“ <strong>Mammoet</strong> set<br />
the record for<br />
the tallest lift”<br />
LOCATION: PAULINIA, BRAZIL<br />
JOB: INSTALLING TOWERS<br />
CHALLENGE: TALLEST SINGLE<br />
LIFT IN BRAZIL