13.11.2012 Views

Download - Mammoet BV

Download - Mammoet BV

Download - Mammoet BV

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Record for <strong>Mammoet</strong> Dubai<br />

Turnaround at Leuna<br />

After two years of planning, the refinery in Leuna was shut<br />

down in May 2008 for a turnaround and expansion, involving<br />

3,300 people working on the site. <strong>Mammoet</strong> Germany provided<br />

no fewer than 70 cranes, from its own fleet, another<br />

German crane company and from <strong>Mammoet</strong> in the<br />

Netherlands. <strong>Mammoet</strong> Germany managed this project using<br />

the dedicated <strong>Mammoet</strong> Shutdown Concept. This involved a<br />

LOCATION: LEUNA, GERMANY<br />

JOB: SUPPORTING A TURNAROUND<br />

CHALLENGE: SCALE OF THE PROJECT<br />

“The project went<br />

smoothly thanks<br />

to the thorough<br />

preparation and<br />

good cooperation”<br />

<strong>Mammoet</strong> Dubai transported its heaviest item<br />

ever, a 1,605 ton xylene column with a length<br />

of almost 100 meters. It was transported four<br />

kilometers from Sohar Port to an Aromatics Plant<br />

in Sohar Industrial Area in the Sultanate of Oman.<br />

The contract covered a total of 43 items which<br />

were transported by SPMTs. Because of the size<br />

of the loads, traffic signs and lampposts had to<br />

be removed along the route. Later <strong>Mammoet</strong><br />

has re-positioned the xylene column under the<br />

gantry for final installation. The whole project was<br />

completed successfully and safely.<br />

great deal of coordination with the site operator and the<br />

contractors working on the site. <strong>Mammoet</strong> was on site for<br />

several weeks and the project went smoothly thanks to the<br />

thorough preparation and good cooperation between the<br />

German and Dutch crews. The highest lift was the replacement<br />

of a 5.5 ton flare top at a height of 145 meters.<br />

Brazilian Record With<br />

MSG-80 Configuration<br />

<strong>Mammoet</strong> spent four months on a site in Brazil, with up to fifteen of<br />

their people from branches throughout the world. <strong>Mammoet</strong> had to<br />

install three towers: two of 60 meters and 250 tons and one of 110<br />

meters and 700 tons.<br />

The real challenge was to install the 110 meter polypropylene tower<br />

after it had been fitted with all the platforms, stairs, risers, pipes,<br />

insulation etc. <strong>Mammoet</strong> decided to use their MSG-80 II and the<br />

Dracula Tail Frame. Given the needs of the job <strong>Mammoet</strong> had to rig<br />

it with a 92.6 meter main boom and 42.9 meter jib. As the tower was<br />

resting on six saddles supported by concrete blocks <strong>Mammoet</strong> first<br />

had jack it up 2.5 meters to remove the saddles and to install the tail<br />

frame on the skirt. <strong>Mammoet</strong> set the record for the tallest lift by a<br />

single crane in Brazil.<br />

Petrochemical<br />

LOCATION: SOHAR, OMAN<br />

JOB: TRANSPORTING HEAVY COLUMNS<br />

CHALLENGE: WEIGHT OF THE LOAD<br />

“ <strong>Mammoet</strong> set<br />

the record for<br />

the tallest lift”<br />

LOCATION: PAULINIA, BRAZIL<br />

JOB: INSTALLING TOWERS<br />

CHALLENGE: TALLEST SINGLE<br />

LIFT IN BRAZIL

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!