21.01.2015 Views

Final Adopted IDP - KZN Development Planning

Final Adopted IDP - KZN Development Planning

Final Adopted IDP - KZN Development Planning

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

ELECTRICITY PROVISION<br />

There are two electricity distribution service providers within the area of jurisdiction<br />

of the Ulundi Municipality (the Municipality itself and Eskom), each having a distribution<br />

licence issued by the National Electricity Regulator of South Africa (NERSA). Provision<br />

of electricity within the Ulundi municipal area is sourced from four substations:<br />

• The newly built Nkonyeni substation was commissioned in 2010 and is now<br />

operational. It is a 88/22Kv; 20 Mva substation that is fed from the Umfolozi<br />

Transmission substation. Overhead distribution lines (22Kv) are in the process of<br />

being constructed from the Nkonyeni substation into the Ulundi municipal area;<br />

this multi-million Rand project will provide a backbone from which communities<br />

across the extent of the municipal area are able to access an electricity service.<br />

Once the backbone has been completed access will be constrained only by the<br />

availability of funding to connect households to the supply network. Wards that<br />

will benefit initially from electrification along the route of this line are Ward 1;<br />

Ward 2; Ward 3; Ward 4; Ward 5; Ward 6; part of Ward 7; part of Ward 8;<br />

Ward 9, Ward 10, Ward 11; Ward 14 and Ward 15.<br />

• The Mtonjaneni substation is a 88/22Kv; 40 Mva substation fed from the<br />

Umfolozi Transmission substation. There is an existing 22 Kv line from the<br />

Mtonjaneni substation running along the Vryheid Road and into the Ulundi<br />

municipal area; it also branches off toward Babanango, where it meets up with a<br />

22 Kv line from the St. James substation. The existing line is being extended<br />

towards the Quarry and the Ulundi Water Treatment Works. This extension will<br />

benefit the communities in Ward 12, Ward 19, Ward 20, Ward 21, Ward 23 and<br />

the southern part of Ward 16.<br />

• A 22 Kv line from the Vryheid substation feeds into Ward 13; an interlink between<br />

this line and the Mtonjaneni 22 Kv line was planned. It was subsequently<br />

established that the line from the Vryheid substation does not have additional<br />

capacity which affects the electrification possibilities in Ward 13 and the<br />

northern part of Ward 16.<br />

• When the Nkonyeni substation lines have been constructed and converted to 22<br />

Kv, the existing high voltage lines through Ward 8 and Ward 14 will be fed from<br />

the Unit D substation and initially operated on 11 Kv. On the western border of<br />

the Ulundi Municipality an interlink will be built between the two feeders which<br />

will provide access to the electrification of communities in some parts of Ward 8,<br />

Ward 14, Ward 15 and Ward 24. This interlink is expected to be completed within<br />

three years. The next phase, to be commenced in September 2012 will connect<br />

these two networks to the Okhuku substation and be operated on 22 Kv. The<br />

34

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!