SOCIAL AND ECONOMIC DEVELOPMENT<br />

Focus Area Objective Performance Target Key Performance Indicators<br />

Housing<br />

To address the demand<br />

for housing within the<br />

Ulundi municipal area<br />

Completion of construction of 200 housing units<br />

at the Ekushumayeleni Rural Housing Project by<br />

30 June 2013<br />

‣ Monitoring of construction milestones<br />

through regular recorded site visits (input)<br />

‣ Review of milestone based invoices<br />

submitted by appointed contractor (input)<br />

‣ Verify the completion of 200 housing units<br />

by 30 June 2012 (output)<br />

Obtain finality on the continued existence of the<br />

Nsukazi Housing Project<br />

‣ Obtain details of new beneficiaries to<br />

benefit from this project (input)<br />

‣ Review status of project with Department of<br />

Human Settlements officials (process)<br />

Obtain finality on the continued existence of the<br />

Nsabekhuluma Housing Project<br />

‣ Obtain details of new beneficiaries to<br />

benefit from this project<br />

‣ Review status of project with Department of<br />

Human Settlements officials (process)<br />

Completion of construction of100 housing units<br />

at the Ekudubekeni Rural Housing Project by 30<br />

June 2013<br />

‣ Monitoring of construction milestones<br />

through regular recorded site visits (input)<br />

‣ Review of milestone based invoices<br />

submitted by appointed contractor (input)<br />

‣ Verify the completion of 100 housing units<br />

by 30 June 2013 (output)<br />