21.01.2015 Views

Staff Reports - East Bay Municipal Utility District

Staff Reports - East Bay Municipal Utility District

Staff Reports - East Bay Municipal Utility District

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Board of Directors<br />

Monthly Report - February 2013<br />

Page 4<br />

The first of two major aqueduct shutdowns was completed on the Mokelumne Aqueducts<br />

Interconnection Project on February 4. Mokelumne Aqueducts Nos. 1 and 2 were returned to<br />

service on February 11. Shutdown of Mokelumne Aqueduct No. 3 began on February 23 and is<br />

scheduled to end on March 29. The contractor is performing tie-in work on Aqueduct No. 3.<br />

The Mokelumne Aqueduct temperature anchor upgrade was completed on February 26.<br />

Work on the final anchor to maintain the stability and integrity of Aqueduct Nos. 1 and 2 was<br />

completed during the recent shutdown of the aqueducts.<br />

Operational testing at the Walnut Creek Raw Water Pumping Plant resumed on<br />

February 21. Testing of the six refurbished raw water pumps and switchgear for Walnut Creek<br />

Pumping Plant Nos. 1 and 2 will be completed in mid-March.<br />

Annual open-cut dam safety inspections were completed on January 28, February 7 and<br />

February 9. The inspections are performed annually in conjunction with the Division of Safety<br />

of Dams to ensure there are no safety issues and the dams are operated in accordance with state<br />

licensing requirements. Additional safety inspections included the exercising of valves on three<br />

of the inlet-outlet pipelines. The inspections confirmed that the dams are operating satisfactorily.<br />

<strong>Staff</strong> submitted a grant application to the Department of Water Resources (DWR) on<br />

February 1 requesting $5 million in Proposition IE funds to go toward the Chabot Dam<br />

Seismic Upgrade project. Pursuant to the Disaster Preparedness and Flood Prevention Bond Act<br />

of 2006, DWR is authorized to issue grants to public agencies and non-profit organizations to<br />

manage stormwater runoff to reduce flood damages. Chabot dam is operated to provide flood<br />

protection to the residents downstream of the dam.<br />

Main Wastewater Treatment Plant influent screen replacement project. <strong>Staff</strong> completed the<br />

final design to replace the existing %-inch influent screens at the MWWTP with new ^-inch fine<br />

screens. This project will improve the capture of rags, plastics and other debris entering the plant.<br />

Improved bar screen performance will reduce the impact of rags and solids deposition in<br />

downstream treatment processes, increasing usable digester capacity. The equipment will be<br />

installed during the 2013 and 2014 dry weather seasons.<br />

Solar Turbines is manufacturing higher BTU biogas fuel injectors to resolve injector<br />

damage. Solar Turbines has informed the <strong>District</strong> that they are in production of a medium BTU<br />

injector that will potentially eliminate future fuel injector damage. These medium BTU injectors<br />

will be installed in April 2013. In the interim, Solar will install re-tipped injectors to ensure that<br />

the turbine can continue to operate with negligible risk of injector failure.<br />

Paving. 9,212 square feet of permanent paving was completed on Davenport Avenue in Oakland<br />

in two days by three <strong>District</strong> paving crews.<br />

Pipeline. On February 9, <strong>District</strong> staff began installing 1,830 feet of 16-inch steel water pipe on<br />

Pleasant Hill Road in Pleasant Hill. On February 1 st , <strong>District</strong> staff began working on three streets

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!