Minutes of the pre-bid Meeting
Minutes of the pre-bid Meeting
Minutes of the pre-bid Meeting
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
REPLIES TO THE PRE-BID QUARRIES<br />
Road Name :- Mangawan to MP/UP Border (NH-27)<br />
S.NO. CLAUSE OF CONTRACT/CLARIFICATION SOUGHT/QUERY REPLY OF MPRDC<br />
1 Vol. I, clause 2.1.3: The Feasibility Report <strong>of</strong> <strong>the</strong> being provided only as a<br />
<strong>pre</strong>liminary reference document by way <strong>of</strong> assistance to <strong>the</strong> Bidders who are<br />
expected to carry out <strong>the</strong>ir own surveys, investigations and o<strong>the</strong>r detailed<br />
Feasibility report is indicative. Scope <strong>of</strong> work,<br />
Specifications and standards and provisions <strong>of</strong> C.A. &<br />
schedules are final binding.<br />
examination <strong>of</strong> <strong>the</strong> Project before submitting <strong>the</strong>ir Bids. Nothing contained in <strong>the</strong><br />
Feasibility Report shall be binding on <strong>the</strong> Authority nor confer any right on <strong>the</strong><br />
Bidders, and <strong>the</strong> Authority shall have no liability whatsoever in relation to or<br />
arising out <strong>of</strong> any or all contents <strong>of</strong> <strong>the</strong> Feasibility Report.<br />
It is assumed that <strong>the</strong> contents <strong>of</strong> <strong>the</strong> feasibility report are not binding on <strong>the</strong><br />
concessionaire. Kindly clarify.<br />
2 Vol. I, clause 2.11.1: The Bidder shall submit <strong>the</strong> Bid in <strong>the</strong> format specified at Appendix 1 along with format as per part – II.<br />
Appendix – I and seal it in an envelope and mark <strong>the</strong> envelopes as “BID”.<br />
There is contradiction in <strong>the</strong> clause as <strong>the</strong> financial <strong>bid</strong> format is provided in<br />
Part – II. Kindly confirm whe<strong>the</strong>r <strong>the</strong> financial <strong>bid</strong> is to be submitted in <strong>the</strong><br />
Appendix – I or <strong>the</strong> format as per Part – II.<br />
3 Vol. I, Appendix I, clause 30: We hereby submit our Bid and <strong>of</strong>fer [a Premium in<br />
<strong>the</strong> form <strong>of</strong> ____ Percent (in words) <strong>of</strong> <strong>the</strong> gross revenues <strong>of</strong> <strong>the</strong> Project as share<br />
<strong>of</strong> <strong>the</strong> Authority/require a Grant <strong>of</strong> Rs. ____ (Rupees____Only)] (Strike out<br />
whichever is not applicable) for undertaking <strong>the</strong> aforesaid Project in accordance<br />
with <strong>the</strong> Bidding Documents and <strong>the</strong> Concession Agreement. There is<br />
contradiction in <strong>the</strong> clause as <strong>the</strong> financial <strong>bid</strong> format is provided in Part-II.<br />
Kindly confirm whe<strong>the</strong>r <strong>the</strong> financial <strong>bid</strong> is to be submitted in <strong>the</strong> Appendix-I<br />
Already clarified.
(Clause No. 30) or <strong>the</strong> format as per Part-II.<br />
4 Vol. III, clause 27.1.1: On and from <strong>the</strong> COD till <strong>the</strong> Transfer Date, <strong>the</strong><br />
Concessionaire shall have <strong>the</strong> sole and exclusive right to demand, collect and<br />
appropriate Fee from <strong>the</strong> Users subject to and in accordance with this Agreement<br />
and <strong>the</strong> National Highways Fee (Determination <strong>of</strong> Rates and Collection) Rules,<br />
2008 and amendment rules, 2010 including any fur<strong>the</strong>r amendments (<strong>the</strong> “fee<br />
Rules”);<br />
The amendments if any shall be provide for <strong>the</strong> correct assessment <strong>of</strong> <strong>the</strong><br />
<strong>bid</strong>der.<br />
5 Vol. III, clause 27.1.2: The Parties acknowledge that a notification for levy and<br />
collection <strong>of</strong> Fee shall be issued by <strong>the</strong> Government under Section 8A <strong>of</strong> <strong>the</strong> Act<br />
read with Rule 3 <strong>of</strong> <strong>the</strong> National Highways Fee (Determination <strong>of</strong> Rates and<br />
Collection) Rules, 2008 and amendment rules, 2010 including any fur<strong>the</strong>r<br />
amendments (“<strong>the</strong> Notification”) within 90 (ninety) days here<strong>of</strong>, substantially in<br />
<strong>the</strong> form set forth in Schedule-R.<br />
The amendments if any shall be provided for <strong>the</strong> correct assessment <strong>of</strong> <strong>the</strong><br />
<strong>bid</strong>der.<br />
6 Vol. III, clause 29.1.1: The Authority and <strong>the</strong> Concessionaire acknowledge that<br />
<strong>the</strong> traffic as on October 1, 2035 (<strong>the</strong> “Target Date”) is estimated to be 42349<br />
PCUs per day (<strong>the</strong> “Target Traffic”), and hereby agree that for determining <strong>the</strong><br />
modifications to <strong>the</strong> Concession Period under this Article 29, <strong>the</strong> actual traffic on<br />
<strong>the</strong> Target Date shall be derived by computing <strong>the</strong> average <strong>of</strong> <strong>the</strong> traffic as<br />
determined by traffic sampling.<br />
Kindly explain <strong>the</strong> methodology for <strong>the</strong> arriving <strong>of</strong> <strong>the</strong> Target date as<br />
October 1, 2035.<br />
Enclosed.<br />
Already clarified.<br />
It is based on <strong>the</strong> traffic projections done by MPRDC.
7 Vol. III, clause 30.1.1: Notwithstanding anything to <strong>the</strong> contrary contained in this<br />
Agreement but subject always to Clause 30.2, <strong>the</strong> Authority shall not construct,<br />
and shall procure that no Government Instrumentality shall construct or cause to<br />
be constructed, any ex<strong>pre</strong>ssway or o<strong>the</strong>r toll road between, inter alia, Mangwan<br />
and MP/UP Border i.e. km 98/2 and km 46/6 on National Highway No. 27<br />
(collectively <strong>the</strong> “Additional Tollway”) for use by traffic at any time before <strong>the</strong><br />
18 th (Eighteenth) anniversary <strong>of</strong> <strong>the</strong> Appointed Date; provided that in <strong>the</strong> event <strong>of</strong><br />
<strong>the</strong> Concession Period being reduced to 18 (eighteen) years, <strong>the</strong> Additional<br />
Tollway may be opened to traffic at any time after <strong>the</strong> 12 th (twelfth) anniversary<br />
<strong>of</strong> <strong>the</strong> Appointed Date.<br />
The significance <strong>of</strong> reduction in concession period to 18 yrs. is not<br />
understood. Kindly explain <strong>the</strong> same in detail.<br />
We understand that <strong>the</strong> concession period is <strong>of</strong> 30 yrs.<br />
8 Vol. III, clause 47.3: 47.3 Memorandum <strong>of</strong> Understanding (MOU)<br />
The Concessionaire acknowledges that it has received from <strong>the</strong> Authority a<br />
certified true copy <strong>of</strong> <strong>the</strong> agreement executed between MORTH and <strong>the</strong> State<br />
Government <strong>of</strong> Madhya Pradesh through MPRDC for providing <strong>the</strong> support and<br />
services specified <strong>the</strong>rein (<strong>the</strong> “MOU”), and <strong>the</strong> Parties hereto agree to make <strong>the</strong>ir<br />
best endeavours to procure <strong>the</strong> support <strong>of</strong> <strong>the</strong> State Government. Kindly provide<br />
<strong>the</strong> copy <strong>of</strong> MOU.<br />
9 Vol. III, Article 48: “Fee Notification” means <strong>the</strong> Notification to be issued by<br />
<strong>the</strong> Government, prior to <strong>the</strong> Appointed Date, in exercise <strong>of</strong> <strong>the</strong> powers conferred<br />
by Section 8A <strong>of</strong> <strong>the</strong> National Highways Act, 1956 read with Rule 3 <strong>of</strong> <strong>the</strong><br />
National Highways Fee (Determination <strong>of</strong> Rates and Collection) Rules, 2008, and<br />
amendment rules, 2010 including any fur<strong>the</strong>r amendments in respect <strong>of</strong> <strong>the</strong> levy<br />
words “provided that in <strong>the</strong> event <strong>of</strong> Concession<br />
Period being reduced to 18 (eighteen) years, <strong>the</strong><br />
additional tollway may be opened to traffic at any time<br />
after 12 th (twelth) anniversary <strong>of</strong> <strong>the</strong> appointed date”<br />
stands deleted.<br />
Will be supplied to <strong>the</strong> selected Concessionaire.<br />
Already clarified.
and collection <strong>of</strong> Fee during <strong>the</strong> Concession Period, substantially in <strong>the</strong> form at<br />
Schedule – R; The amendments if any shall be provided for <strong>the</strong> correct<br />
assessment <strong>of</strong> <strong>the</strong> <strong>bid</strong>der.<br />
10 Vol. IV. Appendix BIII:<br />
Details <strong>of</strong> Bypasses/ Realignment<br />
1. Bypasses<br />
Sl. No. Name <strong>of</strong> Design Chainage (Km) Length (Km)<br />
Bypass<br />
From To<br />
1 Gangave 88+100 85+000 3.100<br />
2 Gargh 77+321 73+121 4.200<br />
3 Katra 67+381 63+081 4.300<br />
4 Suhagi 54+300 52+800 1.50<br />
Total 13.100<br />
Land available in <strong>the</strong> project is 50% approximately.<br />
Land acquisition is in advance stage. Publication for<br />
3(a) is already published. Land will be made available<br />
before appointed date.<br />
Kindly provide <strong>the</strong> status <strong>of</strong> Land Acquisition i.e. issue <strong>of</strong> 3g notification<br />
necessary for <strong>the</strong> proposed Bypass construction work. As <strong>the</strong> access to <strong>the</strong> land is<br />
not available unless <strong>the</strong> payment is made.<br />
11 Vol. IV. Appendix BV:<br />
Details <strong>of</strong> ROW<br />
Existing<br />
Chainage<br />
Length<br />
Existing Row<br />
Width <strong>of</strong><br />
Existing<br />
ROW (m)<br />
Name <strong>of</strong><br />
Village along<br />
corridor<br />
Proposed<br />
ROW (m)<br />
As per above in Sr. no. 10
Kindly provide <strong>the</strong> status <strong>of</strong> Land Acquisition i.e. issue <strong>of</strong> 3g notification<br />
necessary for <strong>the</strong> proposed Four laning work. As <strong>the</strong> access to <strong>the</strong> land is not<br />
available unless <strong>the</strong> payment is made.<br />
12 Vol. IV, Schedule R<br />
Fee Notification<br />
S. No. Location <strong>of</strong> Toll Plaza Nature <strong>of</strong> Cost<br />
(Chaingae)<br />
Structure<br />
1 Chainage 51.500 Bypass (04 Nos.) 55.41 Crore<br />
As per <strong>the</strong> Fee (Determination <strong>of</strong> Rates and Collection) Rules, 2008, and<br />
amendment rules, 2010, <strong>the</strong> fees for <strong>the</strong> bypass section are computed on <strong>the</strong> basis<br />
<strong>of</strong> length ra<strong>the</strong>r than <strong>the</strong> cost <strong>of</strong> bypass. It is requested to kindly clarify <strong>the</strong> same.<br />
Kindly provide <strong>the</strong> copy <strong>of</strong> applicable toll polices.<br />
13 General: Whe<strong>the</strong>r <strong>the</strong> proposed ROW <strong>of</strong> <strong>the</strong> project passed through <strong>the</strong> forest<br />
area, if yes what is <strong>the</strong> status <strong>of</strong> clearances from <strong>the</strong> concerned authorities<br />
As per <strong>pre</strong>sent toll policy applicable mentioned in<br />
schedule „R‟ with recent amendment to <strong>the</strong> NH Fee<br />
(determination <strong>of</strong> rate and collection) Rules 2008 along<br />
with amendment rate 2010 and 2011 shall be<br />
applicable. Copies <strong>of</strong> <strong>the</strong> said rule and amendment are<br />
enclosed. Accordingly <strong>the</strong> toll rates for bypasses are<br />
based on length ra<strong>the</strong>r than cost.<br />
Total length <strong>of</strong> road including bypass is 52.07 Km and<br />
length <strong>of</strong> bypasses only is 13.10 Km.<br />
Application has been submitted to forest department<br />
for NOC.
REPLIES TO THE PRE-BID QUARRIES<br />
Road Name :- Satna to Bela Four lane Road project (NH-75)<br />
S.NO. CLAUSE OF CONTRACT/CLARIFICATION SOUGHT/QUERY REPLY OF MPRDC<br />
1 Vol. III, clause 30.1.1: Notwithstanding anything to <strong>the</strong> contrary contained in this<br />
Agreement but subject always to Clause 30.2, <strong>the</strong> Authority shall not construct,<br />
and shall procure that no Government Instrumentality shall construct or cause to<br />
be constructed, any ex<strong>pre</strong>ssway or o<strong>the</strong>r toll road between, inter alia, Satna and<br />
Bela i.e. km 155.0 and km 203.4 on National Highway No. 75 (collectively <strong>the</strong><br />
“Additional Tollway”) for use by traffic at any time before <strong>the</strong> 15 th (Fifteenth)<br />
anniversary <strong>of</strong> <strong>the</strong> Appointed Date; provided that in <strong>the</strong> event <strong>of</strong> <strong>the</strong> Concession<br />
Period being reduced to 15 (fifteen) years, <strong>the</strong> Additional Tollway may be<br />
opened to traffic at any time after <strong>the</strong> 10 th (tenth) anniversary <strong>of</strong> <strong>the</strong> Appointed<br />
Date.<br />
The significance <strong>of</strong> reduction in concession period to 15 yrs. is not<br />
understood. Kindly explain <strong>the</strong> same in detail.<br />
We understand that <strong>the</strong> concession period is <strong>of</strong> 27 yrs.<br />
words “provided that in <strong>the</strong> event <strong>of</strong> Concession<br />
Period being reduced to 15 (fifteen) years, <strong>the</strong><br />
additional tollway may be opened to traffic at any time<br />
after 10 th (tenth) anniversary <strong>of</strong> <strong>the</strong> appointed date”<br />
stands deleted.
REPLIES TO THE PRE-BID QUARRIES<br />
Road Name :- Sidhi to Singrauli Four lane Road project (NH-75E)<br />
S.NO. CLAUSE OF CONTRACT/CLARIFICATION SOUGHT/QUERY REPLY OF MPRDC<br />
1 Vol. III, clause 30.1.1: Notwithstanding anything to <strong>the</strong> contrary contained in this<br />
Agreement but subject always to Clause 30.2, <strong>the</strong> Authority shall not construct,<br />
and shall procure that no Government Instrumentality shall construct or cause to<br />
be constructed, any ex<strong>pre</strong>ssway or o<strong>the</strong>r toll road between, inter alia, sidhi and<br />
Singrauli i.e. km 83/4 and km 195/8 on National Highway No. 75E (collectively<br />
<strong>the</strong> “Additional Tollway”) for use by traffic at any time before <strong>the</strong> 18 th<br />
(Eighteenth) anniversary <strong>of</strong> <strong>the</strong> Appointed Date; provided that in <strong>the</strong> event <strong>of</strong> <strong>the</strong><br />
Concession Period being reduced to 18 (Eighteen) years, <strong>the</strong> Additional Tollway<br />
may be opened to traffic at any time after <strong>the</strong> 12 th (twelth) anniversary <strong>of</strong> <strong>the</strong><br />
Appointed Date.<br />
The significance <strong>of</strong> reduction in concession period to 18 yrs. is not<br />
understood. Kindly explain <strong>the</strong> same in detail.<br />
We understand that <strong>the</strong> concession period is <strong>of</strong> 30 yrs.<br />
words “provided that in <strong>the</strong> event <strong>of</strong> Concession<br />
Period being reduced to 18 (eighteen) years, <strong>the</strong><br />
additional tollway may be opened to traffic at any time<br />
after 12 th (twelth) anniversary <strong>of</strong> <strong>the</strong> appointed date”<br />
stands deleted.