GOVERNMENT OF ARUNACHAL PRADESH PUBLIC WORKS DEPARTMENT ***** Gram : Chiefworks Phone : 0360–2212024, Fax: 0360-2212428 Email : boraete@gmail.com No. CEAP (EZ)/WTC-29/DONER/07-08/ Office of the Chief Engineer, Eastern Zone, PWD, Itanagar – 791111 Dated 20 th December,2007. To All Superintending Engineers, Under Eastern Zone, PWD, Arunachal Pradesh. All Executive Engineers, Under Eastern Zone, PWD, Arunachal Pradesh. Sub :- Additional Retained projects under NLCPR (2007-08) and follow-up there-of. Ref :- MDONER No.DNER/NLP/AP/3/2007 Dated 07.12.2007 In continuation of this office letter No.CEAP(EZ)/WTC-29/DONER/2007-08 dtd. 17 th / 19 th Nov. 2007, enclosed please find herewith additional list of project retained by MDONER under NLCPR for the year 2007-08 intimated vide their No.DNER/NLP/AP/3/2007 Dated 07 th December 2007 for your submission of Detailed Project Report (DPR). In this connection, the following points may be noted while preparing the DPR. DPR prepare & thereof 1) The preliminary design of geometrics and components of the road / bridge projects shall be strictly as per the relevant IRC provisions and specification of Road and Bridge works published by MORTH. (Scanned soft copies in CD on IRC/MORTH publications are available in Zone office.) 2) The history of the DPR should be properly narrated to the point, justifying the proposal and scope. (Sample of concept paper on Dhodar-Ali road, uploaded in website is a good sample to be followed.) 3) The scheme where the proposal is to be submitted within restricted scope as “Phase-I” should have detailed inventories of total scope of work and items being covered in Phase-I. The cost assessment and number of major bridges in the subsequent phases may also be highlighted.

GOVERNMENT OF ARUNACHAL PRADESH<br />

PUBLIC WORKS DEPARTMENT<br />

*****<br />

Gram : Chiefworks<br />

Phone : 0360–2212024, Fax: 0360-2212428<br />

Email : boraete@gmail.com<br />

No. CEAP (EZ)/WTC-29/DONER/07-<strong>08</strong>/<br />

Office <strong>of</strong> <strong>the</strong> Chief Engineer,<br />

Eastern Zone, PWD, Itanagar – 791111<br />

Dated 20 th December,<strong>2007</strong>.<br />

To<br />

All Superintending Engineers,<br />

Under Eastern Zone, PWD,<br />

Arunachal Pradesh.<br />

All Executive Engineers,<br />

Under Eastern Zone, PWD,<br />

Arunachal Pradesh.<br />

Sub :- Additional <strong>Retained</strong> projects under <strong>NLCPR</strong> (<strong>2007</strong>-<strong>08</strong>) and follow-up <strong>the</strong>re-<strong>of</strong>.<br />

Ref :- MDONER No.DNER/NLP/AP/3/<strong>2007</strong> Dated 07.12.<strong>2007</strong><br />

In continuation <strong>of</strong> this <strong>of</strong>fice letter No.CEAP(EZ)/WTC-29/DONER/<strong>2007</strong>-<strong>08</strong> dtd. 17 th /<br />

19 th Nov. <strong>2007</strong>, enclosed please find herewith additional list <strong>of</strong> project retained by<br />

MDONER under <strong>NLCPR</strong> <strong>for</strong> <strong>the</strong> <strong>year</strong> <strong>2007</strong>-<strong>08</strong> intimated vide <strong>the</strong>ir<br />

No.DNER/NLP/AP/3/<strong>2007</strong> Dated 07 th December <strong>2007</strong> <strong>for</strong> your submission <strong>of</strong> Detailed<br />

Project Report (DPR). In this connection, <strong>the</strong> following points may be noted while<br />

preparing <strong>the</strong> DPR.<br />

DPR prepare & <strong>the</strong>re<strong>of</strong><br />

1) The preliminary design <strong>of</strong> geometrics and components <strong>of</strong> <strong>the</strong> road / bridge projects<br />

shall be strictly as per <strong>the</strong> relevant IRC provisions and specification <strong>of</strong> Road and<br />

Bridge works published by MORTH. (Scanned s<strong>of</strong>t copies in CD on IRC/MORTH<br />

publications are available in Zone <strong>of</strong>fice.)<br />

2) The history <strong>of</strong> <strong>the</strong> DPR should be properly narrated to <strong>the</strong> point, justifying <strong>the</strong> proposal<br />

and scope. (Sample <strong>of</strong> concept paper on Dhodar-Ali road, uploaded in website is a<br />

good sample to be followed.)<br />

3) The scheme where <strong>the</strong> proposal is to be submitted within restricted scope as “Phase-I”<br />

should have detailed inventories <strong>of</strong> total scope <strong>of</strong> work and items being covered in<br />

Phase-I. The cost assessment and number <strong>of</strong> major bridges in <strong>the</strong> subsequent phases<br />

may also be highlighted.


4) No lumpsum provisions without justifications be included in <strong>the</strong> DPR.<br />

5) The s<strong>of</strong>t copy <strong>of</strong> <strong>the</strong> DPR should invariably be enclosed in CD.<br />

Immediately after <strong>the</strong> submission <strong>of</strong> estimate <strong>the</strong> following activities shall follow which<br />

must be ensured by <strong>the</strong> respective Superintending Engineer’s incharge <strong>of</strong> <strong>the</strong> work.<br />

1) Detailed design and quantities estimate <strong>of</strong> <strong>the</strong> project <strong>for</strong> accord <strong>of</strong> Technical Sanction.<br />

2) Draft NIT <strong>for</strong> approval <strong>of</strong> competent authority on finance concurrence, so that tenders<br />

are called immediately on receipt <strong>of</strong> sanction.<br />

Tendering<br />

Re<strong>for</strong>m initiatives taken by Government <strong>of</strong> Arunachal Pradesh to streamline <strong>the</strong><br />

implementation <strong>of</strong> <strong>the</strong> project through Tendering must be publicized among <strong>the</strong> Citizens.<br />

Government will also action <strong>for</strong> enlistment <strong>of</strong> contractors to build up <strong>the</strong> Contract Industry<br />

in <strong>the</strong> State. The Draft Rule has since been vetted by Law Department and all deck<br />

cleared <strong>for</strong> <strong>for</strong>mal Govt. approval. The s<strong>of</strong>t copy <strong>of</strong> <strong>the</strong> draft rule has since been uploaded<br />

in website and Superintending Engineers and Executive Engineers are requested to take go<br />

through and also conduct training/workshop among staff and also involve enterisig<br />

contractors.<br />

(Bora Ete)<br />

Chief Engineer (EZ),<br />

PWD, AP, Itanagar.<br />

Copy to :-<br />

1) The Commissioner(PWD), Govt. <strong>of</strong> Arunachal Pradesh, Itanagar <strong>for</strong> in<strong>for</strong>mation.<br />

2) The Secretary (Planning), Govt. <strong>of</strong> Arunachal Pradesh, Itanagar <strong>for</strong> in<strong>for</strong>mation.<br />

3) The Chief Engineer(WZ), PWD, AP, Itanagar <strong>for</strong> in<strong>for</strong>mation.<br />

4) The Chief Engineer(D&P), PWD, AP, Itanagar <strong>for</strong> in<strong>for</strong>mation.<br />

5) The Chief Engineer(S&I), PWD, AP, Itanagar <strong>for</strong> in<strong>for</strong>mation.<br />

(Bora Ete)<br />

Chief Engineer (EZ),<br />

PWD, AP, Itanagar.


In continuation to my DO letter <strong>of</strong> even number dated 07.11.<strong>2007</strong><br />

regarding retention <strong>of</strong> 8 projects with an estimated cost <strong>of</strong> Rs. 115.79 crore from<br />

Priority <strong>List</strong> <strong>of</strong> projects (<strong>2007</strong>-<strong>08</strong>) it is to in<strong>for</strong>m you that <strong>the</strong> <strong>2007</strong>-<strong>08</strong> Priority <strong>List</strong><br />

<strong>of</strong> Arunachal Pradesh has been reconsidered and following 12 additional projects<br />

at a total estimated cost <strong>of</strong> Rs. 117.86 crore have been retained under <strong>the</strong><br />

<strong>NLCPR</strong> scheme <strong>for</strong> fur<strong>the</strong>r techno-economic examination.<br />

Sl.<br />

Name <strong>of</strong> <strong>the</strong> Project<br />

No.<br />

1. Construction <strong>of</strong> Tamen-Tali road via Yirkoum (60 Km)<br />

– Phase-I (Total estimated cost Rs. 30.00 Crore)<br />

2. Construction <strong>of</strong> road from Kheti to Dadam (21 Km) –<br />

Total estimated cost <strong>of</strong> Rs. 22.00 crore<br />

3. Construction <strong>of</strong> Satnaguri to Longding road via<br />

Kanubari, Banfera, Wanu and Zedua (Phase-I) – Total<br />

estimated cost Rs. 32.27 crore<br />

4. Construction <strong>of</strong> Wak-Liromoba road (78 Km) –<br />

Phase-I (total estimated cost Rs. 39.00 crore)<br />

5. Construction <strong>of</strong> road from Sangram to Phassang –<br />

Pallang via Nyapin (SDO HQ) – Phase-I<br />

Estimated Cost<br />

(Rs. in crore)<br />

10.00<br />

11.00<br />

5.00<br />

10.00<br />

10.00<br />

6. Construction <strong>of</strong> Gacham-Morsing Road (27 Km) 23.00<br />

7. Construction <strong>of</strong> Bailey suspension motorable bridge<br />

over Siyom river to connect left bank at Paya<br />

(Span 122 mtr.)<br />

10.50<br />

8. Construction <strong>of</strong> Single lane bailey bridge (span 40<br />

mtr) over Tasing river in between Borduli village<br />

and Seram in East Siang District.<br />

2.80<br />

9. Construction <strong>of</strong> Steel bridge over Pakke river. 2.33<br />

10. Construction <strong>of</strong> road <strong>for</strong>m 80 Km point on Kimin-Ziro<br />

BRTF road to Krishi Vigyan Kendra at Yachuli<br />

(5.00 Km)<br />

8.03<br />

11. Improvement & Extension <strong>of</strong> Dosing, Pareng, Sine,<br />

Yibuk, Liging road (Phase-I) – total estimated cost<br />

Rs. 30.00 crore<br />

12. Construction <strong>of</strong> an Auditorium at Rajiv Gandhi<br />

University, Rono Hills, Arunachal Pradesh.<br />

15.00<br />

10.00<br />

Total 117.66


2<br />

We would request you to send <strong>the</strong> duly prepared Detailed Project<br />

Report (DPRs) <strong>for</strong> <strong>the</strong> above projects to this Ministry <strong>for</strong> examination and fur<strong>the</strong>r<br />

necessary action within two months from <strong>the</strong> date <strong>of</strong> issue <strong>of</strong> this letter. While<br />

sending <strong>the</strong> DPRs it may be ensured that <strong>the</strong> cost <strong>of</strong> <strong>the</strong> projects is in <strong>the</strong> vicinity<br />

<strong>of</strong> what has been indicated in <strong>the</strong> Priority <strong>List</strong>.<br />

Yours sincerely,<br />

Shri Tabom Bam,<br />

Chief Secretary,<br />

Government <strong>of</strong> Arunachal Pradesh,<br />

Itanagar – 791 111<br />

Fax No. 0360-2215719, 2212446<br />

(Hari Krishna)<br />

Copy to:<br />

1. All concern <strong>for</strong> immediate necessary action.<br />

2. website www.arunachalpwd.org <strong>for</strong> general in<strong>for</strong>mation <strong>of</strong> citizens.<br />

Chief Engineer, (EZ)<br />

PWD, Itanagar.<br />