Table Error! No text of specified style in document..1 Verification Surveys<br />
Item<br />
Frequency of Survey<br />
Stormwater drainage<br />
One level per 10 m and at every structure.<br />
Sub-grade<br />
One level per 20 m<br />
Finished pavement levels<br />
One level per 20 m<br />
A copy of the survey reports shall be provided to the Superintendent within seven (7) days of<br />
completion of the survey. The survey reports shall clearly indicate whether the works are within<br />
tolerance and if not areas that are outside of the tolerance.<br />
If the survey indicates the work out of tolerance, unless approved by the Superintendent, the<br />
Contractor shall rectify the works and arrange re-survey.<br />
1.4.4 As-Built Survey<br />
The Contractor shall provide an “As-built” survey in ACAD and PDF format detailing the relevant<br />
information on the following items (as a minimum):<br />
• Earthwork levels, in a grid suitable to give a true representation of the finished surface (invert of<br />
basins, top and toe of batters, finished surface level of cut and fill zones etc)<br />
• Stormwater drainage – pipe size, drainage structures, invert levels, horizontal and vertical<br />
alignment<br />
• Kerbing – horizontal and vertical alignment<br />
• Pavement – finished surface level including crown and grade changes<br />
• Linemarking and signs<br />
• Other infrastructure as required by local service authorities.<br />
1.5 Environmental Management and Protection<br />
The Contractor shall take all measures necessary to ensure minimum disturbance to the existing<br />
environment by its operations.<br />
The Contractor shall observe all environmental management rules, regulations and codes of practice<br />
and shall comply with all notices and instructions issued by the Superintendent in relation to such<br />
Rules and Regulations.<br />
When flammable or combustible materials are to be stored or used, the Contractor shall adhere<br />
strictly to relevant standards or codes of practice.<br />
1.5.1 Environmental Control During Construction<br />
The Contractor shall carry out the work with reference to the EPA Codes of Practice listed at the end<br />
of this specification clause.<br />
The Contractor shall ensure that pollutants such as dust, sediment, litter and wash down water do<br />
not leave the site during construction of the works. Prior to construction commencing, the<br />
Contractor shall prepare a Soil Erosion and Drainage Management Plan (SEDMP) showing how this<br />
is to be achieved. The Plan shall include a site layout together with a written manual. These shall<br />
include all aspects of site management including:<br />
• site access from public or private roads;<br />
• access around the site;<br />
• areas of earthworks, stockpiles, loading areas;<br />
Ref No. 20120236SA1 <strong>Kingscote</strong> <strong>Streets</strong> <strong>Upgrades</strong> Technical Specification 2