5 Pavement Subgrade<br />

This section of the specification details the requirements for preparation of the pavement subgrade<br />

and shall be read in conjunction with the earthworks section of this specification and the pavement<br />

design schedule as detailed on the drawings.<br />

The subgrade shall include the top 200 mm of the formation directly under the pavement.<br />

5.1 Construction and Workmanship<br />

5.1.1 General<br />

Preparation of the sub-grade shall follow formation of the earthworks, as detailed in the Site<br />

Preparation and Earthworks section of this specification.<br />

5.1.2 Subgrade Preparation<br />

Following the earthworks formation the subgrade shall be trimmed to produce a tight dense surface<br />

to the tolerances specified.<br />

The subgrade shall be systematically compacted to the full width with appropriate compaction<br />

equipment to the specified compaction as detailed in the pavement design of the subgrade.<br />

Where required the subgrade shall be moisture conditioned and compacted as detailed on the<br />

pavement design schedule. Moisture conditioning may include tyning of the subgrade and aeration<br />

to reduce the moisture content, prior to spreading and recompaction. Care shall be taken to ensure<br />

the subgrade is not affected by inclement weather during moisture conditioning process.<br />

Trafficking of the subgrade by construction activities shall be kept to a minimum to reduce “pumping”<br />

of moisture from lower layers into the subgrade.<br />

Subgrades shall be finished with adequate drainage to ensure the water runoff without ponding.<br />

5.1.3 Maintenance of Subgrade<br />

The Contractor shall maintain the subgrade to ensure that the shape and degree of compaction<br />

immediately prior to the placement of the first pavement course conforms to the requirements of the<br />

specification.<br />

Trafficking of the subgrade by construction activities shall be kept to a minimum.<br />

Subgrade that area affected by moisture subsequent to achieving the specified requirements shall<br />

be re-worked as required to achieve the specified requirements.<br />

5.1.4 Proof Rolling<br />

The Contractor shall undertake proof rolling in the presence of the Superintendent by moving a<br />

heavy vehicle over the subgrade to identifying unsuitable material. Proof Rolling shall be carried out<br />

within 24 hours of completion subgrade preparation or prior to any trafficking by construction traffic<br />

of the subgrade.<br />

The Contractor shall ensure that the approved vehicle (a fully laden water cart or similar) for proof<br />

rolling is on site when required for proof. Payment will not be made for transportation of the proof<br />

roll vehicle around the site.<br />

The Superintendent will determine whether a section of subgrade shall not be proof rolled (e.g. over<br />

utility service with limited cover) and the method of proof rolling for small areas.<br />

Ref No. 20120236SA1 <strong>Kingscote</strong> <strong>Streets</strong> <strong>Upgrades</strong> Technical Specification 22