Kingscote Streets Upgrades - Kangaroo Island Council
Kingscote Streets Upgrades - Kangaroo Island Council Kingscote Streets Upgrades - Kangaroo Island Council
Document History and Status Rev Description Author Reviewed Approved Date A Draft for comment PSC 24/5/2012 B Concrete Section Added PSC 19/11/2012 © Tonkin Consulting 2011 This document is, and shall remain, the property of Tonkin Consulting. The document may only be used for the purposes for which it was commissioned and in accordance with the Terms of Engagement for the commission. Unauthorised use of this document in any form whatsoever is prohibited. Ref No. 20120236SA1 Kingscote Streets Upgrades Technical Specification
Table of Contents 1 General Provisions 1 1.1 Public Utilities 1 1.2 Temporary Alterations to Public Utilities 1 1.3 Relevant Authorities 1 1.4 Survey 1 1.4.1 Survey Marks 1 1.4.2 Levels 1 1.4.3 Verification Surveys 1 1.4.4 As-Built Survey 2 1.5 Environmental Management and Protection 2 1.5.1 Environmental Control During Construction 2 1.5.2 References 3 1.6 Preservation of Trees and Vegetation 3 1.7 Drainage of Site During Construction 3 1.8 Matching In and Making Good 3 1.9 Cleaning Up 4 2 Demolition – Civil Works 1 2.1 General 1 2.2 Materials – Demolition 1 2.3 Salvaged Materials 1 2.4 Construction and Workmanship – Demolition 1 3 Site Preparation and Earthworks 3 3.1 General 3 3.2 Materials – Site Preparation and Earthworks 3 3.2.1 General 3 3.2.2 Suitable Materials 3 3.2.3 Imported Fill Materials 4 3.2.4 Unsuitable materials 4 3.2.5 Backfilling Sand 4 3.2.6 Garden Loam 4 3.3 Construction and Workmanship – Site Preparation and Earthworks 4 3.3.1 Geotechnical Inspection and Testing Authority (GITA) 4 3.3.2 Site Clearance 4 3.3.3 Clearance of Surface Vegetation 5 3.3.4 Removal of Trees 5 3.3.5 Removal of Rubbish 5 3.3.6 Stripping and Re-spreading of Topsoil 5 3.3.7 Excavation 5 3.3.8 Fill Construction 7 3.3.9 Backfilling of Trenches 9 3.3.10 Filling Behind Kerbs and Gutters 9 3.4 Quality Requirements – Earthworks 9 3.4.1 General 9 3.4.2 Materials 10 Ref No. 20120236SA1 Kingscote Streets Upgrades Technical Specification
- Page 1: Kingscote Streets Upgrades Technica
- Page 5 and 6: 5.2.2 Quality Testing 23 5.2.3 Tole
- Page 7 and 8: Table 4.2 Compaction requirements f
- Page 9 and 10: Table Error! No text of specified s
- Page 11 and 12: The Contractor shall be responsible
- Page 13 and 14: • Lateral supports - provide late
- Page 15 and 16: • Material, which, after compacti
- Page 17 and 18: All areas disturbed by the excavati
- Page 19 and 20: 3.3.8.2 Placing Fill The method of
- Page 21 and 22: 3.4.2 Materials Suitable materials
- Page 23 and 24: 3.4.5 Tolerances Construction Toler
- Page 25 and 26: 4.2.4 Concrete Concrete grade for d
- Page 27 and 28: 4.3.8 Pipe Surround Bedding materia
- Page 29 and 30: No pumping will be permitted during
- Page 31 and 32: All concrete work shall be in accor
- Page 33 and 34: 5 Pavement Subgrade This section of
- Page 35 and 36: 5.2.4 Acceptance Criteria Areas whe
- Page 37 and 38: 6.3.3 Compaction of Granular Paveme
- Page 39 and 40: The following test procedures shall
- Page 41 and 42: 7 Spray Seals This section of the s
- Page 43 and 44: • retains aggregate after applica
- Page 45 and 46: The application temperatures for pr
- Page 47 and 48: 7.5 Quality Requirements - Spray Se
- Page 49 and 50: 8 Kerbing This section of the speci
- Page 51 and 52: Wherever the work of placing concre
Table of Contents<br />
1 General Provisions 1<br />
1.1 Public Utilities 1<br />
1.2 Temporary Alterations to Public Utilities 1<br />
1.3 Relevant Authorities 1<br />
1.4 Survey 1<br />
1.4.1 Survey Marks 1<br />
1.4.2 Levels 1<br />
1.4.3 Verification Surveys 1<br />
1.4.4 As-Built Survey 2<br />
1.5 Environmental Management and Protection 2<br />
1.5.1 Environmental Control During Construction 2<br />
1.5.2 References 3<br />
1.6 Preservation of Trees and Vegetation 3<br />
1.7 Drainage of Site During Construction 3<br />
1.8 Matching In and Making Good 3<br />
1.9 Cleaning Up 4<br />
2 Demolition – Civil Works 1<br />
2.1 General 1<br />
2.2 Materials – Demolition 1<br />
2.3 Salvaged Materials 1<br />
2.4 Construction and Workmanship – Demolition 1<br />
3 Site Preparation and Earthworks 3<br />
3.1 General 3<br />
3.2 Materials – Site Preparation and Earthworks 3<br />
3.2.1 General 3<br />
3.2.2 Suitable Materials 3<br />
3.2.3 Imported Fill Materials 4<br />
3.2.4 Unsuitable materials 4<br />
3.2.5 Backfilling Sand 4<br />
3.2.6 Garden Loam 4<br />
3.3 Construction and Workmanship – Site Preparation and Earthworks 4<br />
3.3.1 Geotechnical Inspection and Testing Authority (GITA) 4<br />
3.3.2 Site Clearance 4<br />
3.3.3 Clearance of Surface Vegetation 5<br />
3.3.4 Removal of Trees 5<br />
3.3.5 Removal of Rubbish 5<br />
3.3.6 Stripping and Re-spreading of Topsoil 5<br />
3.3.7 Excavation 5<br />
3.3.8 Fill Construction 7<br />
3.3.9 Backfilling of Trenches 9<br />
3.3.10 Filling Behind Kerbs and Gutters 9<br />
3.4 Quality Requirements – Earthworks 9<br />
3.4.1 General 9<br />
3.4.2 Materials 10<br />
Ref No. 20120236SA1<br />
<strong>Kingscote</strong> <strong>Streets</strong> <strong>Upgrades</strong> Technical Specification