Kingscote Streets Upgrades - Kangaroo Island Council
Kingscote Streets Upgrades - Kangaroo Island Council
Kingscote Streets Upgrades - Kangaroo Island Council
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Table 4.2 Compaction requirements for Stormwater Drainage<br />
Layer<br />
Minimum Compaction Requirements<br />
Backfill to springing line 92% of MDD modified compaction AS 1289 5.2.1<br />
Backfill to 300 mm above pipe 92% of MDD modified compaction AS 1289 5.2.1<br />
Backfill to basecourse - Pavements 96% of MDD modified compaction AS 1289 5.2.1<br />
Backfill to surface reinstatement - other 92% of MDD modified compaction AS 1289 5.2.1<br />
4.3.3 Removal of Redundant Drainage Structures<br />
The Contractor shall excavate, remove and backfill existing pipelines, culverts and drainage<br />
structures and / or seal existing pipes with concrete where identified on the drawings.<br />
4.3.4 Inspection after Excavation<br />
After the excavation has been completed the Contractor shall notify the Superintendent and no<br />
concrete or drain structure shall be placed until the Superintendent has approved the depth and size<br />
of the excavation and the character of the foundation material.<br />
4.3.5 Pipe Bedding – Dry Ground<br />
The bottom of all excavations for pipe work shall be trimmed to the grades and levels necessary to<br />
achieve the invert design levels, shown on the drawings. Pipe bedding shall comply in all respects<br />
with the requirements for Type H2 support as defined in AS 3725-1989 Loads on Buried Concrete<br />
Pipes and shall consist of 75 mm compacted thickness of pipe bedding sand compacted as<br />
specified below.<br />
The method of bedding shall not be altered without the prior written approval of the Superintendent.<br />
Where, in the opinion of the Superintendent, the material after excavation is unsuitable as<br />
foundation for the pipe bedding, the Contractor shall remove and replace the unsuitable material or<br />
carry out such other procedures as may be required by the Superintendent. Should the existing<br />
foundation be unsuitable and such measures be required, payment will be made for the cost of any<br />
additional work as an extra to the Contract. The payment shall be made subject to the submission<br />
of a fully documented claim as to labour, plant and materials used, checked and certified by the<br />
Superintendent. Prior approval in writing by the Superintendent must be obtained in all cases,<br />
otherwise no claim will be entertained.<br />
No pipe laying shall commence until the bedding has been inspected and approved by the<br />
Superintendent.<br />
4.3.6 Pipe Bedding – Wet Ground<br />
In locations where groundwater is encountered and de-watering is necessary, pipes shall be laid on<br />
an aggregate bed of a depth between 75 and 150 mm. Where the excavation is in soft clays, sand<br />
or other unstable material, geotextile fabric shall be placed over the full width of the floor of the<br />
trench and up the sides to the level of the underside of the pipe, before placement of the bedding<br />
aggregate.<br />
4.3.7 Pipe Laying<br />
Pipes shall be laid commencing at the lowest elevation unless approved by the Superintendent.<br />
Pipes shall be laid on the prepared bedding as specified above to the lines, levels and grades as<br />
shown on the drawings.<br />
Blocks, bricks and other point supports shall not be permitted and where spigot and faucet pipes are<br />
used, the bedding material shall be shaped in such a way that no load is transmitted to the collar of<br />
the pipe, but that the pipe is uniformly supported along the length of the barrel.<br />
Ref No. 20120236SA1 <strong>Kingscote</strong> <strong>Streets</strong> <strong>Upgrades</strong> Technical Specification 15