• Material, which, after compaction, contains large particles, which may lead to difficulties in the<br />
excavation of trenches for footings or services etc.<br />
• Single-sized or gap-graded gravels or rock fill that will not break down on compaction, leaving<br />
voids into which finer material may subsequently migrate.<br />
• Saline, chemically aggressive or polluted soils, and carbonate soils where acid disposal may<br />
occur.<br />
• Potential acid sulphate soils.<br />
• Materials that cannot be tested to demonstrate compliance with the specification<br />
3.2.3 Imported Fill Materials<br />
Material that is to be imported to the site and is not a quarry product, shall be assessed and<br />
recommended as being suitable for use on the site by an approved Environmental Consultant in<br />
accordance with the National Environmental Protection (Assessment of Site Contamination)<br />
Measure, and the recommendation must be supported by the Superintendent.<br />
No fill material may be brought into site without written approval from the Superintendent and<br />
appropriate accompanied documentation. Material imported on site that does not meet the<br />
requirement of the National Environmental Protection (Assessment of Site Contamination) Measure<br />
shall be removed from site at the cost of the Contractor.<br />
3.2.4 Unsuitable materials<br />
Unsuitable materials shall be site won materials unable to be compacted to for the construction of<br />
structural fill including:<br />
• organic soil (topsoil)<br />
• fill contaminated through past site usage which contain toxic substances or soluble compounds<br />
• fill containing deleterious materials including, metal, wood, plastic, rubbish, vegetation<br />
• other materials deemed unsuitable by the Superintendent.<br />
3.2.5 Backfilling Sand<br />
Backfilling sand shall be Type D Sand in accordance with DTEI Specification Sa-D.<br />
3.2.6 Garden Loam<br />
Garden Loam shall be an approved sand-loam blend in which all material passes a 2.36 mm sieve.<br />
The material shall be free from weeds, roots, clay lumps and other foreign material, and shall be<br />
suitable for growing lawns and plants.<br />
The total salt content shall not exceed 0.2% by dry weight and the linear shrinkage shall not exceed<br />
10%.<br />
3.3 Construction and Workmanship – Site Preparation and Earthworks<br />
3.3.1 Geotechnical Inspection and Testing Authority (GITA)<br />
The Contractor shall engage a suitably qualified independent Geotechnical Inspection and Testing<br />
Authority (GITA) to undertake inspections and testing as required in accordance with AS 3798 –<br />
Guidelines on Earthworks for Commercial and Residential Developments.<br />
3.3.2 Site Clearance<br />
The site shall be cleared only in those parts on which the specified construction works are to be<br />
carried out, or as otherwise shown on the drawings.<br />
All materials resulting from the site preparation shall be removed from the site and disposed of by<br />
the Contractor at his expense.<br />
Ref No. 20120236SA1 <strong>Kingscote</strong> <strong>Streets</strong> <strong>Upgrades</strong> Technical Specification 4