2 Demolition – Civil Works<br />
This section includes all materials, labour, equipment, delivery and transport from site for the<br />
demolition of nominated works, in accordance with the contract drawings and construction<br />
specification.<br />
2.1 General<br />
This specification shall be read in conjunction with the following Standards and references, which<br />
are deemed to form a part of this specification.<br />
AS 2601<br />
Demolition of Structures<br />
2.2 Materials – Demolition<br />
All materials, equipment and service within the demolition area are to become the property of the<br />
Contractor except those specifically stated or shown on the drawings as remaining. The salvage<br />
value or dumping costs of these materials and equipment should be taken into consideration by the<br />
tenderer in arriving at his tender price.<br />
It is desirable to demonstrate community and environmental awareness by creating an opportunity<br />
for the reuse of valuable second-hand resources.<br />
The Contractor shall remove materials from the site in a regular and orderly manner so as to avoid<br />
excessive and unsightly accumulation of demolition materials and rubbish<br />
2.3 Salvaged Materials<br />
Unless otherwise specified and subject to the provisions of sub-clause 27.5 of the General<br />
Conditions of Contract, materials, plant, equipment and other items salvaged from the works shall<br />
become the property of the Contractor and shall be removed by him from the site.<br />
2.4 Construction and Workmanship – Demolition<br />
The contractor shall demolish all works necessary for the construction of new works including but<br />
not limited to:<br />
• asphalt, road pavement, driveways and footpaths<br />
• stormwater pipes and drainage structures<br />
• concrete kerb and gutter<br />
• minor structures.<br />
The Contractor is required to conduct a site investigation and identify and locate:<br />
• service supply mains (water, communications, electricity, gas) and connections<br />
• other services (sewerage, drainage).<br />
The Contractor is to cap and/or isolate services not required. The Contractor is to work around and<br />
not damage services to be kept live. It is the Contractors responsibility to check the status of each<br />
service as they are identified.<br />
The Contractor, during the execution of demolition works, shall consider and provide temporary<br />
support as follows:<br />
• Ground support – support excavations for demolition of underground structures.<br />
• Adjacent structures – provide supports to adjacent structures and services where necessary,<br />
sufficient to prevent damage resulting from the works.<br />
Ref No. 20120236SA1<br />
<strong>Kingscote</strong> <strong>Streets</strong> <strong>Upgrades</strong> Technical Specification