METROPOLITAN WATER RECLAMATION DISTRICT OF GREATER CHICAGO<br />

2009 BUDGET<br />

DESCRIPTION OF CAPITAL PROJECTS (continued)<br />

06-843-3E<br />

07-027-3S<br />

07-028-3S<br />

07-030-3D<br />

07-162-2S<br />

07-163-3M<br />

07-168-3P<br />

07-220-3P<br />

07-221-3P<br />

Switchgear Replacement at Devon & Webster Instream Aeration Stations and O'Hare CUP Reservoir<br />

& Emergency Generator Installation at LASMA and Bartlett Pumping Station<br />

Replace switchgear at Devon and Webster Instream Aeration Stations and O'Hare CUP Reservoir.<br />

Install emergency generators at Bartlett Pumping Station and LASMA.<br />

North Side Sludge Pipeline Replacement - Section 1, NSA<br />

Construction of 24 inch diameter 19,600 feet long ductile iron pipe line with cathodic protection<br />

system or high density polyethylene pipeline with 16 air relief, vacuum relief/blow off/cleanout<br />

structures and all other collateral work.<br />

Harms Road 2 Rehabilitation, NSA<br />

Rehabilitation of 9,070 foot long 4'-6" x 5' semi-elliptic sewer and 14 manhole structures in<br />

Northbrook and rehabilitation/replacement of control structure in Seegers Road, Des Plaines.<br />

North Branch of the Chicago River and North Shore Channel Restoration, NSA<br />

Project includes two-phase approach to implement the most economical remediation measure to stop<br />

the toe erosion and to stabilize the bank slopes at the North Branch of the Chicago River (NBCR)<br />

and North Shore Channel (NSC).<br />

Westdale Gardens Pumping Station & Force Main, Northwest 8A Extension A, SSA<br />

Project consists of a 6-inch diameter, 5700 ft. long force main to be installed by open cut and/or<br />

directional drilling method and a pumping station-wet well system for the Westdale Gardens<br />

Subdivision.<br />

R & D Building HVAC Improvements, SWRP<br />

Install a new air handling unit, absorption chiller, heat exchangers, pumps and Strobic fans. Replace<br />

four existing cooling towers, three chilled water pumps and two condenser water pumps. Work<br />

includes associated controls and rebalancing of the systems. The new air-handling unit will be 100<br />

percent outside air type unit, dual fan system, with carbon filters, 30 percent pre-filters & 85 percent<br />

final filters. Remove existing air handling units S-144, S-146 & S-148 and four existing Carrier<br />

supplemental ceiling mounted heaters. Install new diffusers and registers in rooms currently served<br />

by AHU-3, S-144, S-146 & S-148. Remove seventeen existing "mushroom" type exhausts fans and<br />

install a new exhaust ductwork system and four new Strobic exhaust fans on the roof of the R & D<br />

Building to exhaust rooms currently served by AHU-3, S-144, S-146 & S-148. Relocate existing<br />

Strobic fans EF-879/881. Install a new roof mounted supply ductwork system for the new Air<br />

Handling Unit to interface with the existing ductwork inside the building. Replace fume hoods used<br />

for ovens with canopy hoods in LW-103. Clean ductwork associated with new air handling unit.<br />

Scum Concentration, Post Centrifuge Building, Preliminary Tank and Elevator Improvements,<br />

SWRP, Racine Avenue Pumping Station<br />

Under this project, drain valves with associated piping and operating stems located in the scum pits<br />

in the Scum Concentration Building will be replaced. Twelve sludge/polymer transfer tanks and all<br />

suction piping on the polymer feed pumps Nos. 1-12 at the Post Digestion Building will be removed<br />

and replaced. Ten sludge boxes for the preliminary tanks will be removed and replaced. Hydraulic<br />

passenger elevators at SWRP and Racine Pumping Station will be rehabilitated.<br />

Primary Settling Tanks and Grit Removal Facilities, CWRP<br />

The improvements at the Calumet WRP include construction of eight aerated grit tanks, associated<br />

grit dewatering facilities, 16 circular primary settling tanks, associated influent and effluent conduits,<br />

and other related facilities.<br />

Calumet TARP Pump Station Mechanically Cleaned Bar Screens, Calumet WRP<br />

To furnish, deliver and install devices to mechanically clean existing TARP bar screens.<br />

366<br />

366