Appendix 2: Procurement disclosure Requirements as per World Bank’s<br />

Guidelines<br />

1. Contract Awards for ICB and LIB: Within two weeks of receiving the<br />

Bank’s No Objection to the recommendation of contract award, the Borrower<br />

shall publish in UNDB on-line and in dgMarket the results identifying the bid<br />

and lot numbers and the following information:<br />

(a) name of each bidder who submitted a bid;<br />

(b) bid prices as read out at bid opening;<br />

(c) name and evaluated prices of each bid that was evaluated;<br />

(d) name of bidders whose bids were rejected and the reasons for their<br />

rejection; and<br />

(e) name of the winning bidder, and the price it offered, as well as the<br />

duration and summary scope of the contract awarded.<br />

In the publication of Contract Award referred above, the Borrower shall specify<br />

that any bidder who wishes to ascertain the grounds on which its bid was not<br />

selected, should request an explanation from the Borrower. The Borrower shall<br />

promptly provide an explanation of why such bid was not selected, either in<br />

writing and / or in a debriefing meeting, at the option of the Borrower. The<br />

requesting bidder shall bear all the costs of attending such a debriefing.<br />

If after publication of the results of evaluation, the Borrower receives protest or<br />

complaints from bidders, a copy of the complaint and a copy of the Borrower's<br />

response shall be sent to the Bank for information. If as result of analysis of<br />

a protest the borrower changes its contract award recommendation, the<br />

reasons for such decision and a revised evaluation report shall be submitted to<br />

the Bank for no objection. The Borrower shall provide a republication of the<br />

contract award.<br />

2. Contract awards for <strong>National</strong> Competitive Bidding: Publication of results<br />

of evaluation and of the award of contract consisting of the same information<br />

as mentioned above for ICB and LIB.<br />

3. Contract Awards for Direct Contracting: After the contract signature,<br />

the Borrower shall publish in UNDB on-line and in dgMarket the:<br />

(a) name of the contractor<br />

(b) price<br />

(c) duration, and<br />

(d) summary scope of the contract.<br />

This publication may be done quarterly and in the format of a summarized<br />

table covering the previous period.<br />