Chapter 12<br />
Procurement Arrangements<br />
The <strong>NVBDCP</strong> envisages large scale procurement of pharmaceuticals,<br />
insecticides, long lasting insecticide treated nets, diagnostic kits, vehicles and<br />
services etc. while no civil works are planned under the project. About 85% of<br />
total project cost is estimated to be incurred on procurement of goods and<br />
services. The project will cover selected high burden districts among the<br />
diseases prone states. Initially the procurement under the project will only be<br />
handled at <strong>National</strong> level 29 . The proposed assessment of the procurement<br />
capacities of the states (which MOHFW is taking up in association with the<br />
World Bank and DFID) will determine the decision on decentralizing<br />
procurement to states or state agencies found to have satisfactory capacity.<br />
The details of items to be procured at <strong>NVBDCP</strong> level are indicated in the Table.<br />
12.1 Items to be procured at Central Level<br />
Pharmaceutica<br />
ls and Medical<br />
Supplies<br />
Other Goods Consultancy Services Non-<br />
Consultancy<br />
Services<br />
Procurement of Procurement of Hiring consultant agencies for: Service Printing and<br />
RDK, ACT, Drugs LLIN, Insecticides delivery, Procurement, BCC,<br />
publication of<br />
for severe for IRS and development and translation of training modules, etc.<br />
Malaria, Rapid<br />
diagnostic kits,<br />
Miltefosine or<br />
treatment of<br />
bednets, Vehicles,<br />
Furniture,<br />
manuals/modules, operational research,<br />
impact evaluation, Quality Assurance and<br />
improvement, Monitoring and Evaluation,<br />
other second line Computer<br />
MIS software updating and maintenance,<br />
drugs etc. hardware and<br />
software,<br />
laboratory<br />
equipment etc.<br />
Development and implementation of<br />
Geographic Information System, EMP<br />
implementation, supply chain<br />
management etc.<br />
Total (US$58 M) Total (US$ 76 M) Total (US$ 36 M) Total (US$ 1M)<br />
Rs 2320 Mn Rs 3040 million Rs1440 million Rs 40 million<br />
29 The recruitment of contractual staff at regional, state and district levels will be as per GoI<br />
procedure. Apart from expenditure on contractual staff, there will be some expenditure on training<br />
and mobility of staff at decentralized levels, which may involve a few very low value purchases of<br />
routine items. These expenditures (totaling to US$ 25.28 Million) will be monitored as per the<br />
procedure described in Chapter 10 and no procurement post review will be conducted for these<br />
transactions.<br />
123