17.01.2015 Views

Five – Year Capital Plan - San Francisco International Airport

Five – Year Capital Plan - San Francisco International Airport

Five – Year Capital Plan - San Francisco International Airport

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

<strong>Five</strong> – <strong>Year</strong> <strong>Capital</strong> <strong>Plan</strong><br />

Fiscal <strong>Year</strong> 2010/11 – Fiscal <strong>Year</strong> 2014/15<br />

Business and Finance Division


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

<strong>Five</strong>-<strong>Year</strong> <strong>Capital</strong> <strong>Plan</strong><br />

Fiscal <strong>Year</strong> 2010-11 – Fiscal <strong>Year</strong> 2014-15<br />

3


Table of Contents<br />

1. Executive Summary .........................................................................................................1<br />

2. <strong>Capital</strong> <strong>Plan</strong>ning Process ..................................................................................................2<br />

3. <strong>Plan</strong> of Finance ................................................................................................................2<br />

4. <strong>Capital</strong> <strong>Plan</strong> Overview .....................................................................................................3<br />

New <strong>Capital</strong> Projects ................................................................................................... 4<br />

Discrete Projects ......................................................................................................... 9<br />

Ongoing <strong>Capital</strong> Projects .......................................................................................... 14<br />

5. Appendices .....................................................................................................................23


1. Executive Summary<br />

The <strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong>’s <strong>Five</strong>-<strong>Year</strong> <strong>Capital</strong> <strong>Plan</strong> (the <strong>Plan</strong>) contains 49<br />

projects for a total of $768.2 million and covers FY 2010/11 through FY 2014/15. The<br />

<strong>Plan</strong> contains a description of the scope of each project, shows the full project costs, and<br />

outlines the funding sources. The <strong>Plan</strong> is based on a revised evaluation of projects<br />

included in previous capital plans as well as newly identified needs at the <strong>Airport</strong>. The<br />

<strong>Plan</strong> contains the last year of budget authority for the $383 million project to rebuild<br />

Terminal 2 into a 14-gate domestic terminal; it also includes eleven new projects, such as<br />

Terminal 3 Boarding Area E Renovations, Baggage Handling System and Passenger<br />

Boarding Bridges Upgrade, Common Use System Improvements, and Noise Insulation<br />

Program. A summary of the <strong>Plan</strong> sources and uses are presented below.<br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

<strong>Five</strong>-<strong>Year</strong> <strong>Capital</strong> <strong>Plan</strong><br />

(in millions)<br />

Funding Sources Amount Percentage<br />

Revenue Bonds $ 519.8 67.7 %<br />

Grants 209.9 27.3 %<br />

Passenger Facility Charges 38.5<br />

5.0 %<br />

Total Sources<br />

$768.2 100.0 %<br />

Uses Amount Percentage<br />

Airfield Projects $162.9 21.2 %<br />

<strong>Airport</strong> Support Projects 204.8 26.7 %<br />

Groundside Projects 65.0 8.5 %<br />

Terminal Projects 159.8 20.8 %<br />

Utility Projects 174.7 22.7 %<br />

West of Bayshore Projects 1.0<br />

0.1 %<br />

Total Uses<br />

$768.2 100.0%<br />

* Other funding sources include interest income, settlement revenue, and reprogrammed funds.<br />

1


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

2. <strong>Capital</strong> <strong>Plan</strong>ning Process<br />

The <strong>Airport</strong> is committed to long-term infrastructure planning. To create the <strong>Plan</strong>, <strong>Airport</strong><br />

staff review and evaluate all capital requirements for the five-year planning period,<br />

prioritize the proposed capital projects, and select projects that are the <strong>Airport</strong>’s highest<br />

priority needs. Finance staff allocate the available funding sources, including government<br />

grants, passenger facility charges (PFC), revenue bond funds, and determine the financial<br />

impact of the <strong>Plan</strong> on future operating costs, <strong>Airport</strong> rates and charges, and the cost per<br />

enplanement (CPE).<br />

The <strong>Plan</strong> allows staff to project future funding needs and choose the most appropriate<br />

timing for debt issuance. It also serves as the basis for development of the <strong>Airport</strong>’s Ten-<br />

<strong>Year</strong> <strong>Capital</strong> and Facilities Maintenance <strong>Plan</strong>, an annual compliance requirement by the<br />

<strong>San</strong> <strong>Francisco</strong> Administrative Code (§3.20 <strong>Capital</strong> Expenditure <strong>Plan</strong>).<br />

Staff prepares the <strong>Plan</strong> every fall and submits the annual appropriations request in<br />

February with the operating budget. The <strong>Plan</strong> is developed through an extensive review<br />

process involving senior <strong>Airport</strong> management, the <strong>Airport</strong> Director, the airlines, the<br />

<strong>Airport</strong> Commission, the City <strong>Capital</strong> <strong>Plan</strong>ning Committee, and the <strong>Airport</strong> Financial<br />

Advisory Committee, which includes financial officers from other departments of the<br />

City and County of <strong>San</strong> <strong>Francisco</strong> and members from the financial services industry.<br />

3. <strong>Plan</strong> of Finance<br />

The plan of finance includes the use of debt financing, the use of grant funds, the use of<br />

Passenger Facility Charges (PFC), and other sources. The funding sources for the <strong>Plan</strong><br />

are shown below.<br />

<strong>Plan</strong> of Finance<br />

(in millions)<br />

Funding Sources Amount Percentage<br />

Revenue Bonds $519.8 67.7 %<br />

Grants 209.9 27.3 %<br />

Passenger Facility Charges 38.5 5.0 %<br />

Total Sources<br />

$768.2 100.0 %<br />

* Other funding sources include interest income, settlements, and reprogrammed funds.<br />

The <strong>Plan</strong> includes $519.8 million in bond proceeds to fund projects. The <strong>Airport</strong> is<br />

currently in the third year of a five-year $593.5 million appropriation approved by the<br />

Mayor and the Board of Supervisors on May 23, 2008.<br />

2


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

The <strong>Plan</strong> grant amount of $209.9 million is $34.0 million less, or a 14% decrease, from<br />

the previous year’s capital plan. This reduction is the result of the end of the federal<br />

American Reinvestment and Recovery Act funding, which provided a one-time increase<br />

to available grant funds. The <strong>Plan</strong> shows the <strong>Airport</strong> will receive $26.7 million in <strong>Airport</strong><br />

Improvement Program (AIP) grant funds from the Federal Aviation Administration<br />

(FAA), $2.5 million from the Federal Highway Administration and the California<br />

Department of Transportation for the upper level viaduct roadway, and $20.7 million in<br />

Facilities and Equipment (F & E) grant funds from the FAA for construction of a new Air<br />

Traffic Control Tower.<br />

The <strong>Plan</strong> also includes $38.5 million in funding from Passenger Facility Charges.<br />

4. <strong>Capital</strong> <strong>Plan</strong> Overview<br />

The <strong>Plan</strong> has 49 capital projects that address a variety of needs, such as terminal<br />

renovation, system upgrades, and infrastructure improvements. The following table<br />

shows the distribution of all capital plan projects by <strong>Airport</strong> cost center.<br />

<strong>Plan</strong> Uses<br />

(in millions)<br />

Uses<br />

Number of<br />

Projects Amount<br />

Percentage of<br />

Amount<br />

Terminal Projects 11 $159.9 20.8 %<br />

Airfield Projects 6 162.9 21.2 %<br />

Utility Projects 6 174.6 22.7 %<br />

<strong>Airport</strong> Support Projects 16 204.8 26.7 %<br />

Groundside Projects 9 65.0 8.5 %<br />

West of Bayshore Projects 1 1.0<br />

0.1 %<br />

Total Uses<br />

49 $768.2 100 %<br />

The plan contains eleven new projects with a budget of $69.3 million and 38 continuing<br />

projects with a budget of $698.9 million. <strong>Airport</strong> staff has divided continuing capital<br />

projects into two categories: discrete projects and ongoing projects. Ongoing projects<br />

preserve, maintain and extend the useful life of critical <strong>Airport</strong> facilities and<br />

infrastructure. While the sub-projects contained within the larger project will have a<br />

beginning and an end, the assets that the project maintains will need continuous capital<br />

investment. Examples of such projects include runway reconstruction and major utility<br />

repairs. Discrete projects are one-time in nature and have a defined start and end date.<br />

Once it is completed, a discrete project will not be shown in the <strong>Plan</strong>. An example of this<br />

type of project is the new Air Traffic Control Tower.<br />

3


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

<strong>Plan</strong> Project Types<br />

(in millions)<br />

Project Type<br />

Number of<br />

Projects Amount<br />

Percentage of<br />

Amount<br />

New Projects 11 $69.3 9.0 %<br />

Discrete Projects 13 197.4 25.7 %<br />

Ongoing Projects 25 501.5 65.3 %<br />

Total<br />

49 $768.2 100.0 %<br />

New <strong>Capital</strong> Projects<br />

The <strong>Plan</strong> includes eleven new capital projects as shown on the table below.<br />

New <strong>Capital</strong> Projects<br />

(in thousands)<br />

No. Project Description <strong>Plan</strong> Total Project Total<br />

1 Terminal 3 Boarding Area E Renovations $22,500 $22,500<br />

Baggage Handling System Improvements and<br />

2 Passenger Boarding Bridges Upgrade 19,050 19,050<br />

3 Common Use System Improvements 13,550 13,550<br />

4 Noise Insulation Program 6,696 6,696<br />

5 Aviation Security System Improvements 2,850 2,850<br />

6 Property Management Billing System Phase 2 1,720 1,720<br />

7 Variable Message Signs 1,560 1,560<br />

8 Recycling Compactors in Courtyards 1 and 4 520 520<br />

9 AirTrain On Board CCTV 450 450<br />

10 Document Management System 250 250<br />

11 <strong>San</strong> Bruno Avenue On Ramp to Highway 101 202<br />

202<br />

Total Uses<br />

$69,348 $69,348<br />

A description of each project, a summary of the project budget and total funding needs<br />

are included on the following pages.<br />

4


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Terminal 3 Boarding Area E Renovations<br />

This project refurbishes and repairs Terminal 3 Boarding Area E, which will increase the<br />

service life of this area of the terminal by ten-years. This area will be mostly vacant due<br />

to the relocation of American Airlines to the newly renovated Terminal 2. The <strong>Airport</strong><br />

plans to spend $22.5 million on this project over the next two years.<br />

Terminal 3 Boarding Area E Renovations<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$17,136 $5,364 $ 0 $ 0 $ 0 $22,500 $22,500<br />

Baggage Handling System (BHS) Improvements and Passenger Boarding Bridges<br />

(PBB) Upgrade<br />

This project replaces the electrical, mechanical, monitoring, and control systems for the<br />

BHS and 48 <strong>Airport</strong>-owned PBB at Boarding Areas A and G of the <strong>International</strong><br />

Terminal. Like the CUTE enhancements, the BHS improvements and PBB upgrades will<br />

upgrade or replace the technology support systems in the <strong>International</strong> Terminal that were<br />

activated in 2000. The <strong>Airport</strong> plans to spend $19.05 million on this project over the next<br />

three years.<br />

BHS Improvements and PBB Upgrade<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$4,900 $9,090 $5,060 $ 0 $ 0 $19,050 $19,050<br />

Common Use System Improvements<br />

This project will upgrade and replace the Common Use Terminal Equipment (CUTE)<br />

passenger and baggage processing systems in the <strong>International</strong> Terminal. This project<br />

will enhance the technology support systems in the <strong>International</strong> Terminal, which were<br />

activated in 2000. The <strong>Airport</strong> plans to spend $13.55 million on this project over the next<br />

three years.<br />

Common Use System Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$600 $7,175 $5,775 $ 0 $ 0 $13,550 $13,550<br />

5


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Noise Insulation Program<br />

This project will provide noise insulation for recently purchased homes within the <strong>Airport</strong><br />

65db CNEL (Community Noise Equivalent Level) noise contour that did not participate<br />

in the earlier noise insulation projects. The <strong>Airport</strong> has previously expended more than<br />

$135 million on its Noise Insulation Program. The <strong>Airport</strong> plans to spend $6.7 million on<br />

this project over the next five years.<br />

Noise Insulation Program<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$1,247 $1,290 $1,470 $1,519 $1,170 $6,696 $6,696<br />

Aviation Security System Improvements<br />

This project will improve the <strong>Airport</strong> Security Operations Center (SOC) by upgrading the<br />

Closed Circuit Television system to Internet Protocol (IP) and replacing existing access<br />

controls. The <strong>Airport</strong> plans to spend $2.85 million on this project over the next five<br />

years.<br />

Aviation Security System Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$850 $600 $500 $900 $ 0 $2,850 $2,850<br />

Property Management Billing System (PMBS) Phase 2<br />

This project will fund the development of additional PMBS functionality to support<br />

integration new systems, such as the Ground Transportation Management System, the<br />

development of a PMBS dashboard, and additional connectivity to the <strong>Airport</strong> data<br />

warehouse. The <strong>Airport</strong> plans to spend $1.72 million on this project over the next two<br />

years.<br />

Property Management Billing System Phase 2<br />

Funding Requirements (in thousands)<br />

5-<strong>Year</strong> Project<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

Total Total<br />

$877 $843 $ 0 $ 0 $ 0 $1,720 $1,720<br />

6


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Variable Message Signs (VMS)<br />

This project replaces 23 VMS mounted on sign bridges above the freeway ramps near the<br />

<strong>Airport</strong> with new units that offer greater functionality and are less costly to operate and<br />

maintain. These signs will be centrally controlled by the <strong>Airport</strong> Communications<br />

Center. This project also funds VMS that will be installed at the Rental Car Center exit,<br />

Long-Term Parking exit, and at the Main Road R-1 outbound exit. The <strong>Airport</strong> plans to<br />

spend $1.56 million on this project over the next two years.<br />

Variable Message Signs<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$780 $780 $ 0 $ 0 $ 0 $1,560 $1,560<br />

Recycling Compactors in Courtyards 1 and 4<br />

This project installs two recycling compactors in Courtyard 1 and Courtyard 4. These<br />

new compactors will provide needed additional recycling capacity, as the recycling<br />

dumpsters in use are at capacity. The <strong>Airport</strong> plans to spend $520,000 to acquire these<br />

two compactors.<br />

Recycling Compactors in Courtyards 1, 4<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$520,000 $ 0 $ 0 $ 0 $ 0 $520,000 $520,000<br />

AirTrain On Board Closed Circuit Television (CCTV)<br />

This project will enhance the safety and security for <strong>Airport</strong> passengers and protect the<br />

<strong>Airport</strong>’s assets by installing a CCTV system in each AirTrain vehicle. CCTV units are<br />

presently in use on <strong>Airport</strong> shuttle buses. The <strong>Airport</strong> plans to spend $450,000 on this<br />

project.<br />

AirTrain On Board CCTV<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$450 $ 0 $ 0 $ 0 $ 0 $450 $450<br />

7


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Document Management System<br />

This project provides funding for the initial evaluation of an <strong>Airport</strong>-wide document<br />

management system to improve information access and organization. The <strong>Airport</strong> will<br />

undertake a requirements analysis in the first year to assess and identify the need, scope,<br />

project requirements and funding requirements before making a decision on whether to<br />

proceed with this project.<br />

Document Management System<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$250 $ 0 $ 0 $ 0 $ 0 $250 $250<br />

<strong>San</strong> Bruno Avenue On-Ramp to Highway 101<br />

This project constructs a grade-separated ramp near the <strong>Airport</strong> Rental Car Center to<br />

connect <strong>San</strong> Bruno Avenue southbound traffic to Hwy 101 as described in the agreement<br />

between the <strong>Airport</strong> and the California Department of Transportation. The <strong>Airport</strong> plans<br />

to spend $202,000 on this project next year.<br />

<strong>San</strong> Bruno Avenue On-Ramp to Highway 101<br />

Funding Requirements (in thousands)<br />

5-<strong>Year</strong> Project<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

Total Total<br />

$202 $ 0 $ 0 $ 0 $ 0 $202 $202<br />

8


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Discrete <strong>Capital</strong> Projects<br />

The <strong>Plan</strong> includes 13 discrete capital projects as shown in the table below.<br />

Discrete <strong>Capital</strong> Projects<br />

(in thousands)<br />

No. Project Description <strong>Plan</strong> Total Project Total<br />

1 Air Traffic Control Tower $103,977 $103,977<br />

2 Runway Safety Areas (RSA) 35,560 49,126<br />

3 Terminal 2 Boarding Area D Renovation and<br />

Ancillary Projects 18,672 18,672<br />

4 Viaduct Improvements 9,372 23,659<br />

5 Automated Vehicle Identification (AVI) System<br />

Replacement 7,000 8,113<br />

6 ITT Network Infrastructure Program 6,757 9,370<br />

7 Emergency Operations Services Improvements 6,650 6,650<br />

8 Fire Equipment Replacement Program 5,134 7,609<br />

9 <strong>International</strong> Terminal Complex (ITC) Flight<br />

Information Display Systems (FIDS) Upgrade 1,400 4,900<br />

10 Terminal 1 Boarding Area B <strong>Plan</strong>ning and Pre-<br />

Design 1,125 1,625<br />

11 Emergency Marine Response Facility 620 4,600<br />

12 Taxi Revenue System Improvements 600 800<br />

13 Telephone System Upgrade 515 1,030<br />

Total Uses<br />

$197,382 $240,131<br />

A description of each discrete project and a summary of the project budget are included<br />

on the following pages.<br />

Air Traffic Control Tower<br />

This project is for a new FAA Air Traffic Control Tower which will be designed and<br />

constructed between Terminal 1 and Terminal 2. The <strong>Airport</strong> anticipates that federal<br />

grants will cover 100% of the construction cost for the replacement facility. The <strong>Airport</strong><br />

will cover the demolition cost for the old control tower that will be dismantled after the<br />

replacement tower is activated.<br />

Air Traffic Control Tower<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$20,730 $27,973 $22,135 $11,310 $21,829 $103,977 $103,977<br />

9


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Runway Safety Area (RSA) Implementation<br />

This project will fund the initial planning effort to meet the FAA's 1,000 feet of runway<br />

end requirement and provide additional planning, design, and construction funds for the<br />

28/10 runways. The new safety areas will minimize the hazards of aircraft passing<br />

beyond the end of a runway during an aborted takeoff or while landing, preventing major<br />

damage to aircraft and injuries to passengers. This safety project is required to comply<br />

with FAA Safety and Security Requirements and must be completed by December 31,<br />

2015. Up to 75 percent of the total project cost is projected to be funded by the FAA.<br />

Runway Safety Area (RSA) Implementation<br />

Funding Requirements (in thousands)<br />

5-<strong>Year</strong> Project<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

Total Total *<br />

$17,730 $17,830 $ 0 $ 0 $ 0 $35,560 TBD<br />

* The full project cost had not been determined and FAA funding commitments were uncertain during the<br />

development cycle for this <strong>Capital</strong> <strong>Plan</strong>. The FY11/12 <strong>Capital</strong> <strong>Plan</strong> will include more complete project cost<br />

and funding information.<br />

Terminal 2 Boarding Area D Renovation and Ancillary Projects<br />

This project has been modified to include four additional ancillary projects that support<br />

and enhance the Terminal 2 Boarding Area D Renovation project. The Terminal 2<br />

Boarding Area D Renovations converts the 10 gate old international terminal to a 14 gate<br />

domestic terminal. These additional Terminal 2 projects will provide supplemental power<br />

capacity, widen pedestrian sidewalks, enhance escalators, and facilitate airline tenant<br />

improvements.<br />

Terminal 2 Boarding Area D Renovation and Ancillary Projects<br />

Funding Requirements (in thousands)<br />

5-<strong>Year</strong> Project<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

Total Total<br />

$18,672 $ 0 $ 0 $ 0 $ 0 $18,672 $18,672<br />

Viaduct Improvements<br />

This project continues the retrofit of the upper level viaduct roadway that serves the main<br />

terminal complex, bringing the viaduct into compliance with current roadway design<br />

criteria and seismic standards. This project also replaces vehicle barriers, upgrades<br />

column roadway supports, and resurfaces the upper level of the viaduct. Roadway<br />

lighting improvements and re-routing of underground utilities is also included in the<br />

project scope. This project is mandated by the Federal Highway Administration (FHWA).<br />

Federal grant funds will reimburse 68% of design and construction costs.<br />

10


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Viaduct Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$3,172 $1,500 $1,700 $250 $2,750 $9,372 $23,659<br />

Automated Vehicle Identification (AVI) System Replacement<br />

This project replaces the AVI hardware and system software used to support the <strong>Airport</strong>’s<br />

ground transportation operations. The replacement system will use technology to assess<br />

ground transportation trip fees and manage other fees paid by ground transportation<br />

permit holders.<br />

Automated Vehicle Identification System Replacement<br />

Funding Requirements (in thousands)<br />

5-<strong>Year</strong> Project<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

Total Total<br />

$7,000 $ 0 $ 0 $ 0 $ 0 $7,000 $8,113<br />

ITT Network Infrastructure Improvements<br />

This project improves the information technology network infrastructure through<br />

technology upgrades and replacement hardware and software.<br />

ITT Network Infrastructure Improvements<br />

Funding Requirements (in thousands)<br />

5-<strong>Year</strong> Project<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

Total Total<br />

$3,356 $2,711 $690 $ 0 $ 0 $6,757 $9,670<br />

Emergency Operations Services Improvements<br />

This project will fund the new 700 MHz digital radio system, replace the M212 command<br />

vehicle with a new mobile command center, and replace the logging recorder for the 911<br />

call center. The <strong>Airport</strong> plans to spend $6.55 million on this project.<br />

Emergency Operations Services Improvements<br />

Funding Requirements (in thousands)<br />

5-<strong>Year</strong> Project<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

Total Total<br />

$3,650 $1,000 $ 0 $ 0 $2,000 $6,650 $6,650<br />

11


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Fire Equipment Replacement Program<br />

This project will replace a 1991 Aircraft Rescue Fire Fighting (ARFF) Vehicle, which<br />

exceeds the FAA 15-year replacement recommendation. The new ARFF vehicle will be<br />

diesel powered with minimum agent capabilities of 4,000 usable gallons of water,<br />

delivery capability of aqueous film forming foam (AFFF) concentrate, dry chemical fire<br />

extinguishing and clean agents. This project also funds a replacement fire boat to enhance<br />

marine rescue operations, a structural engine replacement, an aerial ladder with pumper<br />

replacement, as well as enable the replacements for additional ARFF vehicles in future<br />

years. The <strong>Airport</strong> plans to spend $5.134 million on this project over the next five years.<br />

Fire Equipment Replacement Program<br />

Funding Requirements (in thousands)<br />

5-<strong>Year</strong><br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

Total<br />

Project<br />

Total<br />

$1,759 $ 0 $ 0 $1,650 $1,725 $5,134 $5,134<br />

<strong>International</strong> Terminal Complex (ITC) Flight Display Information System (FIDS)<br />

Upgrade<br />

This project provides technology upgrades to the ITC FIDS and integrates the system<br />

with the new FIDS system in Terminal 2 Boarding Area D.<br />

ITC FIDS and Peripheral Equipment Upgrade<br />

Funding Requirements (in thousands)<br />

5-<strong>Year</strong> Project<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

Total Total<br />

$1,400 $ 0 $ 0 $ 0 $ 0 $1,400 $1,400<br />

Terminal 1 Boarding Area B <strong>Plan</strong>ning and Predesign<br />

This project will fund initial activities by the <strong>Airport</strong>’s Bureau of Building Design and<br />

Construction and the Bureau of <strong>Plan</strong>ning and Environmental Affairs in the development<br />

of planning documents for the future renovation of Terminal 1 Boarding Area B. This<br />

project will include phasing plans, cost estimating, scheduling, seismic and geotechnical<br />

studies, building condition assessment, and procurement activities.<br />

Terminal 1 Board Area B <strong>Plan</strong>ning and Predesign<br />

Funding Requirements (in thousands)<br />

5-<strong>Year</strong> Project<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

Total Total<br />

$ 1,125 $ 0 $ 0 $ 0 $ 0 $1,125 $1,625<br />

12


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Emergency Marine Response Facility<br />

This project funds a Marine Response Facility to store and provide immediate launching<br />

of rescue vessels and patrol craft in response to emergency situations developing in the<br />

marine environment near the <strong>Airport</strong>. This facility would provide overhead and side<br />

coverage for the interim out-of-water storage of various water craft outfitted to perform<br />

rescue operations or patrol and would allow <strong>Airport</strong> staff to meet FAA emergency<br />

response mandates.<br />

Emergency Marine Response Facility<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$620 $ 0 $ 0 $ 0 $ 0 $620 $4,600<br />

Taxi Revenue System Improvements<br />

The project funds the replacement of the Taxi Revenue System. The <strong>Airport</strong> will replace<br />

taxi gate equipment, improve checkout locations, add handheld card readers, combine<br />

SFO Taxi Smart Card and CCSF A-Card, and upgrade or replace system software and<br />

hardware to ensure continued system operability and maintenance.<br />

Taxi Revenue System Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$600 $ 0 $ 0 $ 0 $ 0 $600 $600<br />

Telephone System Upgrade<br />

This project replaces the aging Avaya Primary Branch Exchange (PBX) telephone<br />

equipment and upgrades the network infrastructure to improve communications<br />

functionality in Terminal 1, Terminal 3, and the Rental Car Center. By 2011, the current<br />

PBX network infrastructure design and some equipment will be discontinued or will no<br />

longer be supported by Avaya. Replacing the older equipment and updating the current<br />

infrastructure design will ensure that the <strong>Airport</strong> will have product support and can<br />

purchase maintenance services.<br />

Telephone System Upgrade<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

Project<br />

Total<br />

$515 $ 0 $ 0 $ 0 $ 0 $515 $1,030<br />

13


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Ongoing <strong>Capital</strong> Projects<br />

The <strong>Plan</strong> includes 25 ongoing continuing capital projects as shown below.<br />

Ongoing <strong>Capital</strong> Projects<br />

(in thousands)<br />

No. Project Description <strong>Plan</strong> Total<br />

1 Airfield Improvements - Runways $57,715<br />

2 Power and Lighting System Improvements 52,450<br />

3 Wastewater System Improvements 48,042<br />

4 Airfield Improvements 43,560<br />

5 Central <strong>Plan</strong>t Improvements 34,153<br />

6 Safety and Security Improvements 34,050<br />

7 Terminal 3 Improvements 29,752<br />

8 Roadway Improvements 29,000<br />

9 Water System Improvements 22,300<br />

10 Terminal 1 Improvements 21,372<br />

11 Airfield Improvements – Taxiways 18,250<br />

12 <strong>Airport</strong> Support Facility Improvements 16,150<br />

13 Superbay Hangar Improvements 16,000<br />

14 Public Parking Lots / Garages Improvements 15,819<br />

15 Terminal Facility Renovations 13,681<br />

16 Terminal Safety Improvements 11,075<br />

17 Storm Drain Improvements 10,920<br />

18 Elevator, Moving Walks, Escalator Improvements 8,200<br />

19 Telecommunication System Improvements 6,800<br />

20 Airfield Improvements – Utilities 5,225<br />

21 Airfield <strong>Capital</strong> Equipment 2,605<br />

22 ADA Improvements 1,491<br />

23 West of Bayshore Improvements 1,000<br />

24 AirTrain Improvements 1,000<br />

25 Terminal – <strong>Capital</strong> Equipment<br />

Total Uses<br />

900<br />

$501,510<br />

A description of each ongoing continuing project and a summary of the project budget in<br />

the <strong>Plan</strong> are described on the following pages.<br />

14


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Airfield Improvements – Runways<br />

This project funds airfield pavement and infrastructure improvements to enhance the<br />

safety and efficiency of runway operations. This project funds the cyclical reconstruction<br />

of all four <strong>Airport</strong> runways, upgrades related utility infrastructure, and improves airfield<br />

markings in compliance with FAA requirements. Utility infrastructure includes<br />

associated sewage, drainage, industrial waste disposal, and electrical and lighting systems<br />

that affect the runways. This project also includes efforts to reduce ponding within the<br />

runway areas. The FY10/11 5-year capital plan commitment for this project is $57.7<br />

million. FAA grants are expected to fund 75% of the project budget.<br />

Airfield Improvements – Runways<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$6,115 $11,850 $950 $19,400 $19,400 $57,715<br />

Power and Lighting System Improvements<br />

This project will fund the planning, design, and construction of power and lighting<br />

systems to ensure reliable and redundant power supplies. This project includes the<br />

implementation of “green” initiatives, including the purchase and installation of energy<br />

efficient lighting systems throughout the <strong>Airport</strong>.<br />

Power and Lighting System Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$1,300 $5,700 $9,450 $19,200 $16,800 $52,450<br />

Wastewater System Improvements<br />

This project upgrades and replaces the sewage and industrial waste systems at the<br />

<strong>Airport</strong>. In the planning period the <strong>Airport</strong> will replace the sanitary sewage and industrial<br />

waste pump stations, construct a new wash down site, and install a new system valves on<br />

various utility systems. The <strong>Airport</strong> will also construct a new sewer outfall to South <strong>San</strong><br />

<strong>Francisco</strong>, repair the Industrial Waste Containment Basins upgrade pump stations at the<br />

Superbay hangar and off the runway, and upgrade the Mel Leong Treatment <strong>Plan</strong>t.<br />

Wastewater System Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$12,839 $13,863 $5,340 $8,900 $7,100 $48,042<br />

15


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Airfield Improvements<br />

This project will fund reconstruction and improvements for various airfield areas to<br />

comply with FAA requirements. The FAA requires airfield areas to be cleared, graded,<br />

and devoid of potentially hazardous ruts, humps, depressions, or other surface variations,<br />

including appropriate drainage to prevent water accumulation, ponding problems, and the<br />

creation of wetlands. This project also enhances perimeter security for the airfield with<br />

replacement security fencing, video surveillance systems, perimeter lighting and other<br />

security systems.<br />

Airfield Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$9,010 $11,967 $6,292 $7,591 $8,700 $43,560<br />

Central <strong>Plan</strong>t Improvements<br />

This project replaces large industrial capacity equipment and associated upgrades to<br />

control systems that monitor and regulate critical central plant operations for the <strong>Airport</strong>.<br />

These upgrades will improve energy efficiency and reduce power and fuel consumption.<br />

Central <strong>Plan</strong>t Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$820 $6,893 $5,578 $9,675 $11,187 $34,153<br />

Safety and Security Improvements<br />

This project funds investments to improve safety and security. In the planning period, the<br />

will invest in a new Airfield Operations facility, replace security gates at the Coast Guard<br />

facility, and implement a new Access Control System throughout the <strong>Airport</strong> to comply<br />

with TSR 1542 Regulations.<br />

Safety and Security Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$2,250 $8,820 $6,749 $4,908 $11,323 $34,050<br />

16


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Terminal 3 Improvements<br />

This project funds architectural enhancements, structural renovations and replacements of<br />

building infrastructure in Terminal 3. In the planning period, the <strong>Airport</strong> will install new<br />

HVAC systems, perform roof repair, and replace carpeting. The table below shows the<br />

five-year funding commitments for this project.<br />

Terminal 3 Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$1,000 $570 $5,399 $11,936 $10,847 $29,752<br />

Roadway Improvements<br />

This project reconstructs and resurfaces <strong>Airport</strong> bridges, circulation roads and roadways.<br />

In the planning period, the <strong>Airport</strong> will perform roadway and shoulder pavement releveling<br />

and structural upgrades for all transit routes within the <strong>Airport</strong> campus.<br />

Incidental work related to the subprojects such as roadway lighting and re-routing of<br />

underground utilities infrastructure are included in the project scope. The <strong>Airport</strong> plans to<br />

spend $29.0 million on this project over the next five years.<br />

Roadway Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$3,908 $2,434 $7,212 $9,126 $6,320 $29,000<br />

Water System Improvements<br />

This project replaces the potable and reclaimed water mains throughout the <strong>Airport</strong> and<br />

funds the development of infrastructure to expand the use of reclaimed water.<br />

Water System Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$7,500 $5,700 $7,000 $100 $2,000 $22,300<br />

17


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Terminal 1 Improvements<br />

This project funds architectural enhancements, structural renovations and replacements of<br />

building infrastructure in Terminal 1. In the planning period, the <strong>Airport</strong> will replace the<br />

heating, ventilation, and air conditioning (HVAC) systems, replace the lower level<br />

ceiling, perform re-roofing of the building, and renovate the restrooms. The table below<br />

shows the five-year funding commitments for this project.<br />

Terminal 1 Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$1,142 $5,120 $4,950 $6,160 $4,000 $21,372<br />

Airfield Improvements – Taxiways<br />

This project will reconstruction of airfield taxiways, vehicle service roads, and aprons,<br />

replace airfield utility infrastructure, and improve airfield markings in compliance with<br />

FAA requirements. Utility infrastructure includes sewage systems, drainage systems, and<br />

electrical and lighting systems. Taxiways scheduled for renovation and reconstruction in<br />

the planning period are: Taxiways G, H, and M; Taxiway S; and, Taxiways N and P. The<br />

FAA’s <strong>Airport</strong> Improvement Program (AIP) is expected to fund up to 75% of project<br />

costs.<br />

Airfield Improvements – Taxiways<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$550 $11,550 $6,150 $ 0 $ 0 $18,250<br />

<strong>Airport</strong> Support Facility Improvements<br />

This project funds improvements to upgrade <strong>Airport</strong> support facilities and to construct<br />

new facilities. The <strong>Airport</strong> plans to improve the <strong>Airport</strong> museum building, renovate the<br />

first floor of the Rental Car Center, construct a new shuttle bus maintenance facility, and<br />

build a new maintenance facility. This project also includes on-call consultant services to<br />

perform as-needed expert analysis, expert witness, material testing, design, and<br />

recommendations for geotechnical and other civil engineering work.<br />

<strong>Airport</strong> Support Facilities<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$2,500 $3,900 $3,800 $5,200 $750 $16,150<br />

18


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Superbay Hangar Improvements<br />

This project funds renovations to the Superbay Hangar facility. In the planning period,<br />

the <strong>Airport</strong> will replace of the fire alarm and suppression system, replace water storage<br />

tanks and renovate the pumping system, and the reconstruct the large hangar doors<br />

including upgrading door components, motor drives, gear boxes, wheels and related<br />

carriages, track guides, and the electrical infrastructure supplying power to the doors.<br />

The <strong>Airport</strong> plans to spend $16.0 million over the next five years on this project.<br />

Superbay Hangar Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$2,200 $7,550 $1,375 $3,000 $1,875 $16,000<br />

Public Parking Lots / Garages Improvements<br />

This project funds ongoing renovations and improvements to all <strong>Airport</strong> parking lots,<br />

garages, and garage lobby tunnels. The <strong>Airport</strong> plans to renovate structural building<br />

components, install a new vehicle entry canopy for the central garage, resurface the<br />

domestic garage, and replace the carbon monoxide monitoring system.<br />

Public Parking Lots / Garages Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$2,792 $6,255 $2,389 $3,288 $1,095 $15,819<br />

Terminal Facility Renovations<br />

This project covers the renewal of terminal support systems, architectural enhancements,<br />

and replacement of building components. In the planning period, the <strong>Airport</strong> will replace<br />

the lobby seating in the Domestic Terminals, develop new information booths in the<br />

Domestic Terminals, improve the Domestic Terminal Fire Protection System, and<br />

renovate Domestic Terminal exterior site furnishing. The table below shows the five-year<br />

funding requirements for this project.<br />

Terminal Facility Renovations<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$1,086 $1,275 $3,642 $5,678 $2,000 $13,681<br />

19


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Terminal Safety Improvements<br />

This project funds safety improvements for all <strong>Airport</strong> terminals. During the planning<br />

period, the <strong>Airport</strong> will upgrade the fire alarm system in the Domestic Terminals to<br />

comply with new fire and building codes, renovate exits at many Domestic Terminal<br />

Boarding Areas, and upgrade the automatic doors at Terminal 1.<br />

Terminal Safety Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$100 $1,000 $1,675 $6,550 $1,750 $11,075<br />

Storm Drain Improvements<br />

This project funds recurring, incremental upgrades to the storm drain systems, including<br />

the replacement of pump stations and slipline storm drain pipelines. The project also<br />

funds improvements to the storm drain systems adjacent to Taxiways and the Superbay<br />

Hangar.<br />

Storm Drain Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$580 $4,000 $4,000 $2,000 $340 $10,920<br />

Elevator, Moving Walks, Escalator Improvements<br />

This project funds the renovation of escalators, elevators and moving walkways. The<br />

<strong>Airport</strong> will rebuild and replace aged and worn mechanical and electrical components,<br />

resulting in a more reliable, safe and energy-efficient passenger transport system. The<br />

<strong>Airport</strong> plans to spend $8.2 million on this project over the next five years.<br />

Elevator, Moving Walks, Escalator Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$1,600 $1,600 $1,600 $1,600 $1,800 $8,200<br />

20


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Telecommunications Infrastructure Equipment<br />

This project will replace and upgrade aged telephone duct banks and data cabling<br />

throughout the <strong>Airport</strong> campus and expand the network infrastructure to provision<br />

telecommunications and data services from the Minimum Point of Entry (MPOE)<br />

facilities and core distribution points to outlying buildings. This project continues the<br />

implementation of the <strong>Airport</strong> Telecommunications Infrastructure <strong>Plan</strong>. The table below<br />

shows the five-year funding requirements for this project.<br />

Telecommunications Infrastructure Equipment<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$ 0 $ 0 $1,800 $2,000 $3,000 $6,800<br />

Airfield Improvements – Utilities<br />

This project funds improvements to the airfield utility infrastructure. The <strong>Airport</strong> will<br />

commit $5.23 million over the next five years to rebuild and improve sewage systems,<br />

drainage, industrial waste, electrical and lighting systems, and electrical substations and<br />

pump stations on the airfield.<br />

Airfield Improvements – Utilities<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$2,400 $ 0 $1,690 $1,136 $ 0 $5,226<br />

Airfield <strong>Capital</strong> Equipment<br />

This project funds heavy equipment and vehicle replacements such as backhoes, asphalt<br />

milling machines, dump trucks, and boom lifts that are essential to maintain the airfield<br />

and adjoining roadways. Many of the existing machines are old and do not meet the new<br />

diesel emissions standards. The <strong>Airport</strong> plans to spend $2.6 million on this project over<br />

the next five years.<br />

Airfield – <strong>Capital</strong> Equipment<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$680 $770 $265 $390 $500 $2,605<br />

21


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

ADA Improvements<br />

This project upgrades various <strong>Airport</strong> facilities to ensure compliance to Federal and State<br />

regulations in support of the Americans with Disabilities Act (ADA) for the safety and<br />

welfare of the disabled public. The <strong>Airport</strong> is committed to spend $1.5 million over the<br />

next five years on this project.<br />

ADA Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$300 $300 $391 $200 $300 $1,491<br />

West of Bayshore Improvements<br />

This project funds drainage improvements at the Lomita Canal and 7th Avenue Ditch on<br />

the West of Bayshore property. This project will reconstruct and widen the canal to<br />

reduce the potential for flooding in the winter and the amount of plant growth during the<br />

spring and summer. The <strong>Airport</strong> is committing to spend $1.0 million for this project over<br />

the next five years.<br />

West of Bayshore Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$500 $500 $ 0 $ 0 $ 0 $1,000<br />

AirTrain Improvements<br />

This project funds upgrades to the AirTrain system. The <strong>Airport</strong> plans to spend $1.0<br />

million to provide wind and rain protection improvements at the AirTrain stations, such<br />

as roof extensions and wind and rain breaks above barrier walls. The <strong>Airport</strong> will also<br />

replace aged and worn AirTrain cables and equipment to maintain high system reliability.<br />

AirTrain Improvements<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$ 0 $ 0 $1,000 $ 0 $ 0 $1,000<br />

22


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Terminal - <strong>Capital</strong> Equipment<br />

This project funds the purchases of heavy equipment needed to maintain and operate<br />

terminals and other <strong>Airport</strong> facilities. The <strong>Airport</strong> plans to spend $0.9 million over the<br />

next five years to acquire emergency generators, boom lifts, and a six-foot hydraulic<br />

press.<br />

Terminal <strong>Capital</strong> Equipment<br />

Funding Requirements (in thousands)<br />

FY10/11 FY11/12 FY12/13 FY13/14 FY14/15<br />

5-<strong>Year</strong><br />

Total<br />

$300 $300 $ 0 $200 $100 $900<br />

5. Appendices<br />

The following appendices provide summary information for the <strong>Plan</strong>:<br />

Appendix 1.<br />

Appendix 2.<br />

<strong>Capital</strong> <strong>Plan</strong> Uses Summary<br />

<strong>Capital</strong> <strong>Plan</strong> Sources Summary<br />

23


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Appendix 1. <strong>Capital</strong> <strong>Plan</strong> Uses Summary<br />

# Division<br />

Cost<br />

Center Project Title FY10/11 FY11/12 FY12/13 FY13/14 FY14/15 Total<br />

New Projects<br />

1 BDC T Terminal 3 Boarding Area E Renovations 17,136,250 5,363,750 0 0 0 22,500,000<br />

2 OPS T Baggage Handling System Imp. and Passenger Boarding Bridges Upgrade 4,900,000 9,090,000 5,060,000 0 0 19,050,000<br />

3 OPS T Common Use System Improvements 600,000 7,175,000 5,775,000 0 0 13,550,000<br />

4 B&F AS Noise Insulation Program 1,247,000 1,289,560 1,469,877 1,519,436 1,169,685 6,695,558<br />

5 OPS AS Aviation Security System Improvements 850,000 600,000 500,000 900,000 0 2,850,000<br />

6 ADM AS Property Management Billing System Phase 2 877,000 843,000 0 0 0 1,720,000<br />

7 BDC G Variable Message Signs 780,000 780,000 0 0 0 1,560,000<br />

8 BDC AS Recycling Compactors in Courtyards 1, 4 520,000 0 0 0 0 520,000<br />

9 OPS G AirTrain On Board Closed Circuit Television 450,000 0 0 0 0 450,000<br />

10 ADM AS Document Management System 250,000 0 0 0 0 250,000<br />

11 BDC G <strong>San</strong> Bruno Avenue On Ramp to Highway 101 202,000 0 0 0 0 202,000<br />

Discrete Projects<br />

12 BDC AS Air Traffic Control Tower 20,730,000 27,972,559 22,135,000 11,310,293 21,829,537 103,977,389<br />

13 FAC A Airfield Imp - Runway Safety Areas 17,730,000 17,830,000 0 0 0 35,560,000<br />

14 BDC T Terminal 2 Boarding Area D Renovation and Ancillary Projects 18,672,206 0 0 0 0 18,672,206<br />

15 FAC G Viaduct Improvements 3,172,261 1,500,000 1,700,000 250,000 2,750,000 9,372,261<br />

16 OPS G Automated Vehicle Identification System Replacement 7,000,000 0 0 0 0 7,000,000<br />

17 ADM AS ITT Network Infrastructure Improvements 3,356,000 2,711,000 690,000 0 0 6,757,000<br />

18 OPS AS Emergency Operations Services Improvements 3,650,000 1,000,000 0 0 2,000,000 6,650,000<br />

19 OPS AS Fire Equipment Replacement Program 1,759,000 0 0 1,650,000 1,725,000 5,134,000<br />

20 OPS AS ITC Flight Information Display Systems Upgrade 1,400,000 0 0 0 0 1,400,000<br />

21 BDC T Terminal 1 Boarding Area B Pre-Design 1,125,000 0 0 0 0 1,125,000<br />

22 OPS AS Emergency Marine Response Facility 620,000 0 0 0 0 620,000<br />

23 OPS G Taxi Revenue System Improvements 600,000 0 0 0 0 600,000<br />

24 ADM AS Telephone System Upgrade 515,000 0 0 0 0 515,000<br />

24


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

# Division<br />

Cost<br />

Center Project Title FY10/11 FY11/12 FY12/13 FY13/14 FY14/15 Total<br />

Ongoing Projects<br />

25 FAC A Airfield Imp – Runways 6,115,000 11,850,000 950,000 19,400,000 19,400,000 57,715,000<br />

26 FAC U Power and Lighting System Improvements 1,299,940 5,700,000 9,450,000 19,200,000 16,800,000 52,449,940<br />

27 FAC U Wastewater System Improvements 12,838,650 13,863,000 5,340,000 8,900,000 7,100,000 48,041,650<br />

28 FAC A Airfield Improvements 9,010,000 11,967,000 6,292,000 7,591,000 8,700,000 43,560,000<br />

29 FAC U Central <strong>Plan</strong>t Improvements 819,920 6,892,737 5,578,675 9,675,000 11,186,840 34,153,172<br />

30 FAC A Safety and Security Improvements 2,250,000 8,820,000 6,749,000 4,907,700 11,323,000 34,049,700<br />

31 FAC T Terminal 3 (T3) Improvements 1,000,000 570,000 5,399,125 11,935,875 10,846,750 29,751,750<br />

32 FAC G Roadway Improvements 3,907,750 2,433,750 7,212,050 9,126,250 6,320,200 29,000,000<br />

33 FAC U Water System Improvements 7,500,000 5,700,000 7,000,000 100,000 2,000,000 22,300,000<br />

34 FAC T Terminal 1 (T1) Improvements 1,142,000 5,120,000 4,950,000 6,160,000 4,000,000 21,372,000<br />

35 FAC A Airfield Imp - Taxiways 550,000 11,550,000 6,150,000 0 0 18,250,000<br />

36 FAC AS <strong>Airport</strong> Support Facility Improvements 2,500,000 3,900,000 3,800,000 5,200,000 750,000 16,150,000<br />

37 FAC T Superbay Hangar Improvements 2,200,000 7,550,000 1,375,000 3,000,000 1,875,000 16,000,000<br />

38 FAC G Public Parking Lots / Garages Improvements 2,791,500 6,255,000 2,389,500 3,287,500 1,095,000 15,818,500<br />

39 FAC T Terminal Facility Renovations 1,085,750 1,275,000 3,642,250 5,678,000 2,000,000 13,681,000<br />

40 FAC T Terminal Safety Improvements 100,000 1,000,000 1,675,000 6,550,000 1,750,000 11,075,000<br />

41 FAC U Storm Drain Improvements 580,000 4,000,000 4,000,000 2,000,000 340,000 10,920,000<br />

42 FAC T Elevator, Moving Walks, Escalator Improvements 1,600,000 1,600,000 1,600,000 1,600,000 1,800,000 8,200,000<br />

43 FAC U Telecommunication System Improvements 0 0 1,800,000 2,000,000 3,000,000 6,800,000<br />

44 FAC A Airfield Imp - Utilities 2,400,000 0 1,690,000 1,135,500 0 5,225,500<br />

45 FAC A Airfield <strong>Capital</strong> Equipment 680,000 770,000 265,000 390,000 500,000 2,605,000<br />

46 FAC AS ADA Improvements 300,000 300,000 391,000 200,000 300,000 1,491,000<br />

47 FAC WB West of Bayshore Improvements 500,000 500,000 0 0 0 1,000,000<br />

48 FAC G AirTrain Improvements 0 0 1,000,000 0 0 1,000,000<br />

49 FAC T Terminal – <strong>Capital</strong> Equipment 300,000 300,000 0 200,000 100,000 900,000<br />

TOTAL 169,612,227 188,071,356 126,028,477 143,866,554 140,661,012 768,239,626<br />

25


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

Appendix 2 – <strong>Capital</strong> <strong>Plan</strong> Sources Summary<br />

# Division<br />

Cost<br />

Center<br />

Project Title<br />

Revenue<br />

Bonds<br />

Grants<br />

Passenger<br />

Facility<br />

Charges<br />

New Projects<br />

1 B&F AS Noise Insulation Program 1,339,112 5,356,446 0 6,695,558<br />

2 BDC AS Recycling Compactors in Courtyards 1, 4 520,000 0 0 520,000<br />

3 OPS G AirTrain On Board Closed Circuit Television (CCTV) 450,000 0 0 450,000<br />

4 OPS AS Aviation Security System Improvements 2,850,000 0 0 2,850,000<br />

5 ADM AS Document Management System 250,000 0 0 250,000<br />

6 ADM AS Property Management Billing System (PMBS) Phase 2 1,720,000 0 0 1,720,000<br />

7 OPS T Common Use System Improvements 13,550,000 0 0 13,550,000<br />

8 OPS T Baggage Handling System Imp. and Passenger Boarding Bridges Upgrade 13,990,000 0 5,060,000 19,050,000<br />

9 BDC G <strong>San</strong> Bruno Avenue On Ramp to Highway 101 202,000 0 0 202,000<br />

10 BDC G Variable Message Signs 1,560,000 0 0 1,560,000<br />

11 BDC T Terminal 3 Boarding Area E Renovations 22,500,000 0 0 22,500,000<br />

Discrete Projects<br />

12 BDC AS Air Traffic Control Tower 22,867,037 81,110,352 0 103,977,389<br />

13 FAC A Airfield Imp - Runway Safety Areas (RSA) 8,890,000 26,670,000 0 35,560,000<br />

14 BDC T Terminal 2 Boarding Area D Renovation and Ancillary Projects 18,672,206 0 0 18,672,206<br />

15 FAC G Viaduct Improvements 4,491,880 4,880,381 0 9,372,261<br />

16 OPS G Automated Vehicle Identification (AVI) System Replacement 7,000,000 0 0 7,000,000<br />

17 ADM AS ITT Network Infrastructure Improvements 6,757,000 0 0 6,757,000<br />

18 OPS AS Emergency Operations Services Improvements 6,650,000 0 0 6,650,000<br />

19 OPS AS Fire Equipment Replacement Program 5,134,000 0 0 5,134,000<br />

20 OPS AS ITC FIDS and Peripheral Equipment Upgrade 1,400,000 0 0 1,400,000<br />

21 BDC T Terminal 1 Pre-Design 1,125,000 0 0 1,125,000<br />

22 OPS AS Emergency Marine Response Facility 620,000 0 0 620,000<br />

23 OPS G Taxi Revenue System Improvements 600,000 0 0 600,000<br />

24 ADM AS Telephone System Upgrade 515,000 0 0 515,000<br />

Total<br />

26


FY 2010/11 – FY 2014/15 <strong>Capital</strong> <strong>Plan</strong><br />

<strong>San</strong> <strong>Francisco</strong> <strong>International</strong> <strong>Airport</strong><br />

# Division<br />

Cost<br />

Center<br />

Project Title<br />

Revenue<br />

Bonds<br />

Grants<br />

Passenger<br />

Facility<br />

Charges<br />

Ongoing Projects<br />

25 FAC A Airfield Imp – Runways 15,790,000 41,925,000 0 57,715,000<br />

26 FAC U Power and Lighting System Improvements 52,449,940 0 0 52,449,940<br />

27 FAC U Wastewater System Improvements 48,041,650 0 0 48,041,650<br />

28 FAC A Airfield Improvements 11,201,250 32,358,750 0 43,560,000<br />

29 FAC U Central <strong>Plan</strong>t Improvements 34,153,172 0 0 34,153,172<br />

30 FAC A Safety and Security Improvements 19,749,700 0 14,300,000 34,049,700<br />

31 FAC T Terminal 3 (T3) Improvements 26,976,750 0 2,775,000 29,751,750<br />

32 FAC G Roadway Improvements 29,000,000 0 0 29,000,000<br />

33 FAC U Water System Improvements 22,300,000 0 0 22,300,000<br />

34 FAC T Terminal 1 (T1) Improvements 18,372,000 0 3,000,000 21,372,000<br />

35 FAC A Airfield Imp - Taxiways 4,562,500 13,687,500 0 18,250,000<br />

36 FAC AS <strong>Airport</strong> Support Facility Improvements 16,150,000 0 0 16,150,000<br />

37 FAC T Superbay Hangar Improvements 16,000,000 0 0 16,000,000<br />

38 FAC G Public Parking Lots / Garages Improvements 15,818,500 0 0 15,818,500<br />

39 FAC T Terminal Facility Renovations 13,681,000 0 0 13,681,000<br />

40 FAC T Terminal Safety Improvements 1,135,000 0 9,940,000 11,075,000<br />

41 FAC U Storm Drain Improvements 10,920,000 0 0 10,920,000<br />

42 FAC T Elevator, Moving Walks, Escalator Improvements 4,800,000 0 3,400,000 8,200,000<br />

43 FAC U Telecommunication System Improvements 6,800,000 0 0 6,800,000<br />

44 FAC A Airfield Imp - Utilities 1,306,375 3,919,125 0 5,225,500<br />

45 FAC A Airfield <strong>Capital</strong> Equipment 2,605,000 0 0 2,605,000<br />

46 FAC AS ADA Improvements 1,491,000 0 0 1,491,000<br />

47 FAC WB West of Bayshore Improvements 1,000,000 0 0 1,000,000<br />

48 FAC G AirTrain Improvements 1,000,000 0 0 1,000,000<br />

49 FAC T Terminal – <strong>Capital</strong> Equipment 900,000 0 0 900,000<br />

TOTAL 519,857,072 209,907,554 38,475,000 768,239,626<br />

Total<br />

27

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!