Philippines<br />

Co-O expansion nears completion<br />

THE expansion work at Medusa Mining’s Co-<br />

O Gold Project is on schedule with the SAG<br />

mill and primary crusher expected to be commissioned<br />

during <strong>June</strong> following commissioning<br />

of the detoxification plant in April. <strong>The</strong><br />

phase 3 expansion will double annual production<br />

from 100,000 ounces of gold to<br />

200,000 ounces.<br />

Mill work completed in recent months includes<br />

conversion and commissioning of leach<br />

tanks from carbon-in-pulp to carbon-in-leach<br />

with six old, small leach tanks removed. <strong>The</strong><br />

Construction of the SAG mill at Medusa Mining’s Co-O Gold Project in eastern Mindanao.<br />

thickener upgrade and gold room upgrade<br />

have been completed and these facilities are<br />

in operation while the emergency feed facility<br />

has also been completed.<br />

<strong>The</strong> main sub-station as well as the mill and<br />

mine transformer stations are completed and<br />

electrified while 42km of electrical wiring at<br />

the new plant is progressing with expected<br />

completion in <strong>May</strong>. <strong>The</strong> mine is also being expanded<br />

and by mid-April in the Level 8 development<br />

about 200 metres of horizontal<br />

development measuring 3 x 3 metres had<br />

been completed and 4 veins intersected to<br />

the south of the Saga Shaft, with another 7<br />

veins to be intersected as work progresses.<br />

Development for infrastructure installation is<br />

ongoing and on-vein development is progressing<br />

on the East Agsao 13, 14, 15 and 16<br />

Veins with 7 headings active. By <strong>June</strong> 30 Medusa<br />

expects about 12 on-vein headings to be<br />

operational and producing development ore.<br />

<strong>The</strong> winze ore pass from Level 5 to Level 8 is<br />

expected to be connected to the level development<br />

in July. Two Alimak rise ore passes are in<br />

progress from Level 8 to Level 6 and are expected<br />

to be operational in August. Ore from these<br />

passes will be fed by conveyor to the ore bins.<br />

<strong>The</strong> company has received results from research<br />

conducted by the Centre for Exploration<br />

Targeting, School of Earth and<br />

Environment at <strong>The</strong> University of Western Australia.<br />

<strong>The</strong> research involved measurement<br />

of the temperatures of ore formation and salinity<br />

of the ore fluids with the aim to determine<br />

the trends and dimensions of gold<br />

potential in the system.<br />

Results show that there are no apparent<br />

trends to indicate that the margins of the epithermal<br />

gold zone have been reached. <strong>The</strong>y<br />

support the ‘potential exploration target size’<br />

of 3 million ounces in 9.8 million tonnes to 7<br />

million in 23.5 million tonnes.<br />

Agata North project on fast track<br />

AN updated and reclassified resource estimate<br />

for the Agata North nickel laterite resource has<br />

prompted a decision by joint venture partners<br />

Mindoro Resources and TVI Pacific, along with<br />

its Philippines operating subsidiary TVIRD, to<br />

fast-track direct shipping operation (DSO) development.<br />

This is likely to result in production<br />

commencing in late <strong>2013</strong>.<br />

Measured and indicated resources have increased<br />

to 33.9 million dry metric tonnes (dmt)<br />

@ 1.1% nickel compared to the previous 31.8<br />

million dmt @ 1.05% nickel. Inferred resources<br />

are 2.0 million dmt @ 1.04% nickel. At a cutoff<br />

grade of 44% iron, there are an estimated<br />

7.9 million dmt or about 10 million wmt @<br />

48.5% iron and 0.94% nickel, a DSO product<br />

grade much in demand in China<br />

<strong>The</strong> joint venture partners say the new resource<br />

provides a robust foundation for moving<br />

forward, initially, with a DSO of high-iron<br />

limonite (upper laterite horizon), followed by<br />

atmospheric leach processing of the underlying<br />

saprolite horizon. <strong>The</strong> resource forms<br />

part of an updated NI 43-101 technical report<br />

on the Agata North nickel laterite resource.<br />

<strong>The</strong> current estimate gives a superior<br />

grade-tonnage distribution to the previous<br />

Agata resource estimate which was carried<br />

out in 2011. Sufficient high-iron limonite has<br />

been defined for approximately 5 years of<br />

DSO production at an annual rate of about 2<br />

million dmt. During this period, it is expected<br />

that the processing plant will be in operation.<br />

TVI has reported to the JV that both the<br />

high-iron DSO and the limestone DSO are<br />

near-term opportunities that have the potential<br />

to generate strong cashflows beginning<br />

in late <strong>2013</strong>, contingent upon, among other<br />

things, receipt of permits in a timely manner.<br />

<strong>The</strong> high-iron laterite and limestone deposits<br />

occur 1km from the coast, which is expected<br />

to minimize transportation costs due to<br />

the proximity of the mine pit to the port. <strong>The</strong><br />

upper portions of the laterite profile comprise<br />

the ferruginous zone and limonite<br />

zone, both rich in iron. <strong>The</strong> deposit is expected<br />

to be developed as a surface mining<br />

operation with the high-iron material sold to<br />

the Chinese iron ore market.<br />

Beneath this zone is the higher nickel<br />

grade saprolite zone, which will be the dominant<br />

feed for a new processing facility<br />

under consideration by the Project Execution/Technology<br />

Development team. <strong>The</strong><br />

high-iron DSO operation is expected to generate<br />

early cashflow before the plant is<br />

built and put into operation.<br />

42 | <strong>ASIA</strong> <strong>Miner</strong> | <strong>May</strong>/<strong>June</strong> <strong>2013</strong>