Request for proposal for preparation of feasibility report for four laining with paved shoulder of Sidhi to Singrauli (NH-75E)<br />
Topographic Survey<br />
Attachment A to the TOR<br />
1. The field surveys would be sufficiently detailed to meet the following objectives:<br />
(i) Finalising the alignment including location of new bridges and other grade<br />
separated structures.<br />
(ii) Preliminary layout of intersections and grade separators.<br />
(iii) Preparation of Land Plans for acquisition of additional land where<br />
necessary.<br />
(iv) Plans for shifting and relocation of utilities.<br />
2. The field surveys shall be carried out using high precision instruments, i.e. total<br />
stations and would cover the following activities:<br />
(i) Running a continuous open traverse along the existing road and<br />
realignments, wherever required to improve geometrics.<br />
(ii) Collection of details for all features such as structures (bridges, culverts,<br />
etc.) utilities, existing roads, electric and telephone installations (both O/H<br />
as well as underground), huts, buildings, fencing, trees, oil and gas lines,<br />
etc. falling within the extent of survey.<br />
3. The width of survey corridor shall be as under:<br />
(i) The topographic surveys shall cover sufficient width beyond the centre line<br />
of the carriageway considering height of the embankment. The width of the<br />
survey corridor shall take into account the existing land width,<br />
realignments, service roads, if any, layout of intersections, extent of<br />
embankment and cut slopes and the general ground profile.<br />
(ii) In case need for bypassing the congested locations is felt and the feasibility<br />
study for the bypass is included in the TOR, preliminary survey would be<br />
carried out along the possible alignments in order to identify and select the<br />
most suitable alignment for the bypass. The final alignment shall be got<br />
approved by the Authority. Further surveys shall be carried out along the<br />
final alignment.<br />
(iii) Where existing roads cross the alignment, the survey shall extend to a<br />
minimum of 100 m on either side of the road centre line and shall be for<br />
sufficient width to allow improvements, including at grade intersection.<br />
4. The important features of the survey conducted and the reference points taken in<br />
consideration like GPS bench mark, temporary and permanent bench marks, etc.<br />
shall be listed in appropriate formats.