Request for proposal for preparation of feasibility report for four laining with paved shoulder of Sidhi to Singrauli (NH-75E)<br />
Key<br />
Date No.<br />
Description of Deliverables Week No £ . Payment<br />
KD1 Inception Report 2 --<br />
KD 2 Report on Alignment (including proposed<br />
geometric improvements) and first traffic survey<br />
KD3 Report on Land Plan Schedules and Utility<br />
Relocation<br />
8 15%<br />
12 10%<br />
KD4 Indicative GAD of structures (bridges, grade 13 10%<br />
separators, ROB/RUBs)<br />
KD5 Report on Environment and Social Impact 14 10%<br />
Assessment<br />
KD6 Draft Feasibility Report and Schedules to the 16 25%<br />
Concession Agreement and financial analysis<br />
KD7 Final Feasibility Report 18 $ 20%<br />
KD8<br />
(a) Project related clerances from concerned 52 10%<br />
departments<br />
(b) Completion of Services including assistance<br />
during Bid Process<br />
Total 100<br />
6.3 In the event that the TOR for the Consultant envisages assistance in the process of<br />
public hearings, etc. in respect of the Environment Impact Assessment (EIA) of the<br />
Project Highway specified in para 3.12 and the process cannot be completed within<br />
the period specified herein for completion of Final Feasibility Report, the EIA<br />
Report may be completed and submitted to the Authority within an extended<br />
period of 6 (six) weeks after submission of the Feasibility Report. A sum equal to<br />
5% (five percent) of the total payment due shall be withheld and paid to the<br />
Consultant upon submission of the EIA Report and environment management plan.<br />
7 Consultancy Team<br />
7.1 The Consultant shall form a multi-disciplinary team (the “Consultancy Team”)<br />
for undertaking this assignment. The following Key Personnel whose experience<br />
and responsibilities are briefly described herein would be considered for evaluation<br />
of the Technical Proposal. Other expertise such as that required for financial<br />
analysis, pavement design, material investigation characterisation, quantity survey,<br />
social impact assessment etc. for the Project highway shall be included in the Team<br />
either by way of Key Personnel or other Professional Personnel, as necessary.<br />
(a) Senior Highway Engineer-cum-Team Leader<br />
(i) Educational Qualifications Graduate in Civil Engineering<br />
(ii) Essential Experience 10 years in planning, project preparation<br />
and design of highway projects.<br />
(iii) Experience in Similar Capacity He should have worked as a Team Leader<br />
for preparation of DPR of 4-lane highway