Request for proposal for preparation of feasibility report for four laining with paved shoulder of Sidhi to Singrauli (NH-75E)<br />
(a)<br />
(b)<br />
An Index Plan of the Project Highway<br />
Plans, L-sections, and typical cross-sections showing the existing<br />
features within the ROW (e.g. carriageway, structures, drains, crash<br />
barriers, service roads, utilities, adjoining land use, intersecting<br />
roads/access roads, road side developments etc.) with the proposed<br />
improvements marked thereon (e.g. raising of embankment,<br />
widening of embankment, location of median, placement of new<br />
carriageway, geometric improvements, widening or reconstruction<br />
of structures, new subways/underpasses/grade separators, service<br />
roads, arrangements for merging/diverging, traffic circulation,<br />
relocation of utilities, etc.) (Refer para 3.3.2).<br />
(2) Investigation Reports<br />
(a) Report on traffic survey and demand assessment (Refer para 3.2).<br />
(b) Inventory survey report (Refer para 3.3.3).<br />
(c)<br />
<strong>Road</strong> and bridge condition survey report (Refer paras 3.3.4 and<br />
3.3.5).<br />
(d) Soil, geotechnical and drainage report (Refer para 3.3.6).<br />
(3) Preliminary designs<br />
Preliminary designs of the Project Highway including service roads,<br />
consistent with the existing facility and the additional requirements<br />
including:<br />
(a)<br />
Traffic and toll forecasting for 10 (ten), 15 (fifteen), 20 (twenty) and<br />
25 (twenty five) years.<br />
(b) Preliminary pavement design for new carriageway and<br />
strengthening of existing carriageway along with typical crosssections.<br />
(c)<br />
(d)<br />
(e)<br />
Options for retention of existing bridges and other structures or their<br />
replacement by new structures together with preliminary design. For<br />
new bridges, the length from abutment to abutment shall not be less<br />
than the length of the existing bridge and foundations need not be<br />
above the existing foundations unless soil conditions justify<br />
otherwise.<br />
Preliminary drainage assessment.<br />
Preliminary layout of inter-sections, grade separators and interchanges<br />
with ramps.<br />
(4) Preliminary costing<br />
(a)<br />
Indicative BOQ.