In 2012, the project was carried out in accordance with the plan, but with smaller intensity<br />
than expected. The procedure for HPPs Renke, Trbovlje and Suhadol NSP started, but<br />
was suspended at the spatial planning conference, due to unsigned concession contract.<br />
Despite considerable efforts of the concessionaire – <strong>HSE</strong>, the contract has not been signed<br />
yet. In the second half of 2012, the Ministry of Agriculture and the Environment presented<br />
its proposal on expanding the Nature 2000 programme as far as Kresnice.<br />
In 2012, two documents that should be signed along with the concession contract<br />
were prepared in collaboration with the Zasavje region municipalities: Agreement on<br />
Cooperation and Mutual Rights and Obligations Regarding Construction of HPP Suhadol,<br />
Hpp Trbovlje and HPP Renke, and as appendix, List of Projects and Financing Sources.<br />
The two documents define participation of individual municipalities in the project and all<br />
arrangements carried out within HPPs (due to their effect, as well as other arrangements<br />
that do not relate to HPPs). They include list of sources to fund individual project, as well<br />
as people responsible for them.<br />
In 2011, the company SRESA was established (with the partners on the project – SEL and<br />
GEN). In 2012, the company still did not operate in full extent, since the holder of concession<br />
is <strong>HSE</strong>; therefore, all activities are still managed by <strong>HSE</strong>.<br />
The project investor is the company <strong>HSE</strong>.<br />
2.9.4 PSP Kozjak<br />
The basic concept behind the construction of PSP on the Drava River is to exploit natural<br />
possibilities for electricity production in times of its peak consumption and to provide<br />
better exploitation of base load power plants. PSP will ensure back-up power in the event<br />
of major production outages in the Slovenian electricity system and will enable control<br />
over the network power and frequency.<br />
In 2012, activities for preparation of Environmental Impact Report and relating expert<br />
assessments in the area of electromagnetic radiation, noise and vibrations, and<br />
archaeology, were carried out.<br />
The project investor is the company DEM.<br />
2.9.5 Reconstruction of HPPs Doblar I,<br />
second stage<br />
The reconstruction of HPP Doblar, started in 2009, comprises a gradual replacement of all<br />
three turbines and ancillary systems. After a successful launch of operations on the third<br />
turbine, de-installation of the second turbine began in September 2011, with complete<br />
removal of turbine, generator, inlet penstock and other electronic equipment . Demolition<br />
works were performed, the new spiral case was concreted and new turbine generator<br />
and other equipment were installed. Technical inspection was carried out. After the<br />
first synchronisation in October 2012 and trial runs on the network, the contractual trial<br />
operation of turbine 2 began.<br />
The project investor is the company SENG.<br />
2.9.6 PV investments<br />
A major investment of the company PV, started in 2011, comprises establishment of<br />
connections to the opening parts of the pit centre and connections for extraction of the<br />
pillar of central part. PV continued with the construction of NOP II shaft and carried out the<br />
necessary maintenance of external facilities.<br />