Annual report - HSE
Annual report - HSE
Annual report - HSE
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Replacement Unit 6 in TEŠ has a clear economic effect, as it ensures lower electricity price<br />
compared to the prices currently achieved at TEŠ, as well as a significant ecological effect.<br />
After the Unit 6 is launched, we will decrease the emissions of sulphur oxide from 400 to<br />
100 mg/Nm3 and the emissions of nitrogen oxide from 500 to 150 mg/Nm3 relative to<br />
achieved emission of both pollutants in 2008.<br />
In 2012, the TEŠ Unit 6 project entered in its most active phase; main construction works<br />
in the boiler area and relevant preparation works were completed already in February.<br />
Therefore, TEŠ met the conditions for handing over the boiler room area to Alstom, which<br />
started installing the main steel construction in March, followed by secondary construction<br />
in May, to launch installation of pressure vessel in August.<br />
In 2012, most of construction in the boiler room area was carried out, including installation<br />
of main gantry crane in autumn. In April, the company completed construction of the<br />
cooling tower shell and continued with finishing works on the shell and the ground slab<br />
and began with preparations for installation of equipment. At the end of May, construction<br />
works on the flue gas desulphurisation plant were terminated, so the company could begin<br />
with installation of construction and equipment. The railway infrastructure for transport of<br />
the heaviest equipment was inspected and adjusted accordingly.<br />
In 2012, TEŠ carried out all procedures for selection of contractors for performance of other<br />
construction works, preparation and transport of products, preparation of cooling water,<br />
construction installation, ammonia water storage, GIS 400 kV substation, coal transport<br />
– phase 1 and 2 and technological connections. By the end of 2012, most contracts with<br />
contractors were concluded and engagements in the fields of other construction works,<br />
cooling water preparation and construction installations were launched.<br />
Due to delays in obtaining the government guarantee and subsequent lack of funds,<br />
project works performed by some major contractors were occasionally interrupted. In July,<br />
the National Assembly adopted the ZPODPTEŠ act; relative contracts with the Republic of<br />
Slovenia were concluded in November, followed by the National Assembly ratification of<br />
the guarantee contract in December.<br />
The project investor is the company TEŠ.<br />
2.9.2 Lower Sava HPPs<br />
Construction of HPP chain on the lower Sava River is one of the most important projects<br />
at the national level. This economically efficient project is the result of predominantly<br />
Slovenian expertise and will have a positive effect on energy sector (ensuring also RESbased<br />
electricity production) and flood protection, while giving local communities a<br />
constant contribution, i.e. concession, and promoting local economy.<br />
Besides already existing HPP Vrhovo (owned by SEL), HPP Boštanj and HPP Arto-Blanca,<br />
the lower Sava HPPs will comprise also HPP Krško, currently in course of trial operations,<br />
HPP Brežice and HPP Mokrice, both in the process of spatial planning.<br />
Basic technical data<br />
HPP HPP Boštanj HPP Arto-Blanca HPP Krško HPP Brežice HPP Mokrice<br />
Rated flow 500 m 3 /s 500 m 3 /s 500 m 3 /s 500 m 3 /s 500 m 3 /s<br />
Height of fall 7.74 m 9.19 m 9.23 m 11.07 m 7.47 m<br />
Maximum capacity 36 MW 42 MW 42 MW 54.1 MW 33.72 MW<br />
Average annual production 115 GWh 144 GWh 144 GWh 168 GWh 133.19 GWh<br />
Useful volume of reservoir 1,170,000 m 3 1,300,000 m 3 1,170,000 m 3 3,400,000 m 3 2,600,000 m 3<br />
Median annual flow 209 m 3 /s 215 m 3 /s 218 m 3 /s 231.3 m 3 /s 273 m 3 /s<br />
Construction period 2002 - 2006 2005 - 2009 2007 - 2012 2013 - 2016 2013/14 - 2017<br />
<strong>Annual</strong> Report <strong>HSE</strong> 2012<br />
2 Business Report<br />
65