• On 19 October, an agreement on financing, logistics and other requirements for<br />

adaptation of the HPP Brežice construction to NPP Krško was signed.<br />

• On 30 October, TEŠ and Alstom concluded Annex 7, which comprises the agreement on<br />

installation works price.<br />

• SENG performed partial TI for the reconstruction of HPP Doblar I, stage II, turbine 2.<br />

• HESS signed Annex 5 to the Concession Agreement for Exploitation of the Energy<br />

Potential of the lower Sava River.<br />

• For the GPK road-header machine, PV won the Slovenian Chamber of Commerce silver<br />

award for the best innovations.<br />

• The 15 th Strategic Conference of the PV Group took place.<br />

November<br />

• On 1 November, the contract between Alstom and TEŠ was suspended, as TEŠ had not<br />

settled its financial liabilities.<br />

• On 24 August the <strong>HSE</strong> Supervisory Board appointed Blaž Košorok as the Managing<br />

Director of the company <strong>HSE</strong>. Mr. Košorok assumed his responsibilities on 5 November.<br />

• On 5 November, heavy rains caused the Drava River floods which caused material<br />

damage on the DME facilities, assessed to over EUR 10 million.<br />

• On 8 November, DEM successfully concluded the TI at small HPP Markovci.<br />

• On 28 November, as the representative of the founder at the <strong>HSE</strong> General Meeting,<br />

the Capital Assets Management Agency of the Republic of Slovenia (AUKN RS) was<br />

acquainted with the 2011 <strong>Annual</strong> Report of the company <strong>HSE</strong> and the <strong>HSE</strong> Group and<br />

adopted the decision that the accumulated profit in the amount of EUR 23,364,809.34<br />

be used for the following purposes: EUR 20,000,000.00 for participating in profit to the<br />

founder, EUR 3,364,809.34 for allocation to other revenue reserves.<br />

• On 30 November, TEŠ and the Republic of Slovenia entered into the contract regulating<br />

relationships regarding the replacement Unit 6 project and the contract on the manner<br />

and conditions regarding the guarantee by the Republic of Slovenia.<br />

• SENG carried out the first synchronisation of turbine 2 at HPP Doblar I and completion of<br />

the trial runs.<br />

• TET acquired energy permit for ecological reconstruction of Unit 4. Within the energy<br />

permit issuance procedure, the administrative body determined that the TET Unit 4<br />

reconstruction complies with the Slovenian energy policy and all the EU directives.<br />

December<br />

• On 3 December, TEŠ and Alstom concluded an Annex due to delayed acquisition of the<br />

government guarantee for the EIB loan for the replacement Unit 6 construction.<br />

• On 7 December, the Guarantee contract between the EIB and the Republic of Slovenian<br />

was signed.<br />

• On 19 December, <strong>HSE</strong> Invest obtained certificate 27001:2005 - Information Security<br />

Management System.<br />

• On 21 December, the National Assembly ratified the guarantee contract between the<br />

Republic of Slovenia and the EIB.<br />

• On 27 December, the Slovenian Sovereign Holding Act was published in the Official<br />

Gazette of the Republic of Slovenia which determined that with its implementation, the<br />

Capital Assets Management Agency of the Republic of Slovenia (AUKN RS) ceases to<br />

exist. The Slovenian Sovereign Holding Act became effective the next day. Management<br />

of assets owned by the Republic of Slovenia, which until then were managed by AUKN<br />

RS, is executed by SOD on the behalf and for the account of the Republic of Slovenia.<br />

• At HPP Krško, HESS successfully completed the installation and functional tests on all<br />

three turbines. In December, the last turbine was submitted to contractual trial operations.<br />

• Public presentation of NSP and ER for HPP Mokrice terminated.<br />

• SENG launched the contractual trial run of turbine 2 at HPP Doblar I.<br />

• Ministry of Finance determined that the RTH mine, as a receiver of government assistance<br />

for mine closing down, terminated the commercial production of coal and that it would<br />

carry out all closing down activities. As a legal entity, RTW will cease to exist, while<br />

there is a possibility that in the Brnice are a new commercial entity would exploit coal<br />

for commercial purposes and carry out an purchase the RTH assets. This means, that<br />

government assistance does not represent an obstacle for coal exploitation on the Brnice<br />

are, thus, TET could continue to use domestic coal for electricity production.<br />

• Ministry of Agriculture and the Environment classified the 125 MW TET Unit in the<br />

national transition plan of the RS for facilities, which will allow their operation as well as<br />

adaptation to new environmental norms in the transition period 2016-2020. The Republic<br />

of Slovenia submitted the document to the EC, which will give its feedback within a year.<br />

<strong>Annual</strong> Report <strong>HSE</strong> 2012<br />