1.5 Chronology of important events<br />

in 2012<br />

January<br />

• On 3 January, Alstom and TEŠ entered into an agreement regulating the method of<br />

liabilities settlement in the period before the issuance of the government guarantee for<br />

financing the construction of the TEŠ replacement Unit 6.<br />

• On 12 January, DEM presented the procedure of initiative for NSP of the HPP Hrastje-<br />

Mota to the Strategic Council of the Pomurje Development Institute Murska Sobota.<br />

• On 16 January, PV reached the most significant daily extraction progress in 2012 with 8.6<br />

meters at extraction site G3/B, despite challenging production circumstances.<br />

• SENG achieved an extension for the pilot operations in the PSP Avče facility until 6 January<br />

2014.<br />

• HESS obtained declarations for operations of the production units HPP Boštanj and HPP<br />

Arto-Blanca.<br />

February<br />

• On 2 February, a group of MPs submitted a proposal for the Act Regulating Guarantee<br />

of Republic of Slovenia for Liabilities under Long-Term Loan of 440 Million Euros<br />

Made to Termoelektrarna Šoštanj, d.o.o. by European Investment Bank for Financing<br />

Termoelektrarna Šoštanj 600 MW Replacement Unit-6 Installation Project (ZPODPTEŠ).<br />

• On 14 February, the PV miners achieved the most important daily progress at the<br />

construction site, i.e. 16.8 metres during a 4-shift work at k.-130/B site for haulage<br />

roadway.<br />

• On 15 February 2012, TEŠ handed over the area of boiler room of the replacement Unit 6<br />

to Alstom and Alstom started with the preparations for installation.<br />

• At its 3rd session on 23 February 2012, the Government of the Republic of Slovenia<br />

expressed its readiness to assume additional risk with issuing its guarantee and, therefore,<br />

its support to the ZPODPTEŠ proposal under certain conditions.<br />

• In February 2012, the Supreme Court dismissed the request by the TEŠ Trade Union<br />

to review the verdict of the Higher Labour and Social Court in Ljubljana, which had<br />

confirmed the verdict of the Labour Court in Celje that the strike in TEŠ in November 2010<br />

was illegal.<br />

• SENG obtained operating permit for the HPP Doblar I turbine 3.<br />

• PV became one of the first coal mines in Europe and worldwide to have mobile phones<br />

coverage underground.<br />

• Upon opening the new coal mine in Mariovo, Macedonia, PV entered into the contract<br />

on design and preparation of technical documentation.<br />

March<br />

• On 7 March, PV reached the most important general progress in pit roadways construction<br />

with 49.8 metres excavated.<br />

• On 13 March 2012, Alstom started with the main steel construction installation of the Unit<br />

6 boiler room.<br />

• On 15 March, formal opening of restructured boiler room in Planina in Kranj took place;<br />

the investor was the company Soenergetika.<br />

• On 20 March, the Supervisory Board was appointed at the first General Meeting of the<br />

company SRESA.<br />

• SENG took over the reconstructed turbine 3, the operations of which were launched at<br />

HPP Doblar I, and started with reconstruction works on turbine 2.<br />

April<br />

• On 19 April the National Assembly discussed on ZPODPTEŠ for the first time and voted<br />

for the guarantee granting.<br />

• SENG successfully completed technical inspection (hereinafter ‘TI’) of the left threesegment<br />

gate within the reconstruction of hydromechanical equipment at Jez Podsedlo<br />

and repairs of the PSP Avče generator, which enabled operations to be launched.<br />

May<br />

• On 17 May, the Government of the Republic of Slovenian amended Article 1 of the<br />

proposal for ZPODPTEŠ.<br />

• On 24 May, PV achieved the most important daily extraction production with 13,470<br />

tonnes of coal at mining site –65/A.<br />