(b)<br />

<strong>The</strong> Procuring Entity shall deduct liquidated damages from payments due to the<br />

Contractor.<br />

(28) Payment of liquidated damages shall not relieve the Contractor from its obligations.<br />

(29) <strong>The</strong> Project Manager shall certify the Final Payment within the period specified in<br />

Schedule II, if the payable amount claimed by the Contractor is correct and the corresponding<br />

works are completed provided that,<br />

(a) If it is not, the Project Manager shall issue a Defects Liability Schedule within<br />

the period specified in Schedule II , stating the scope of the corrections or<br />

additions that are necessary;<br />

(b) If the corrections or additions scheduled by the Project Manager has been<br />

completed, the Project Manager shall issue a Defects Correction Certificate;<br />

(c) If the Final Account of Works is unsatisfactory even after it has been<br />

resubmitted, the Project Manager shall decide on the amount payable to the<br />

Contractor and issue a payment certificate.<br />

(30) If “as built” Drawings or operating and maintenance manuals are required, the<br />

Contractor shall supply them by the dates specified in the contract.<br />

(31) If the Contractor does not supply the Drawings and manuals, under Sub-Rule 30 , by<br />

the dates specified in the contract, or they do not receive the Project Manager’s approval, the<br />

Project Manager shall withhold the amount stated in the contract from payments due to the<br />

Contractor.<br />

(32) A Certificate of Completion of the Works shall be issued by the Project Manager<br />

and the Project Manager shall do so upon deciding that the work is completed under Sub-Rule 29.<br />

(33) <strong>The</strong> Procuring Entity shall take over the Site and the Works within the period<br />

specified in schedule II.<br />

(34) <strong>The</strong> Contractor shall submit a detailed account of the total amount that the<br />

Contractor considers payable under the Contract to the Project Manager,before the end of the<br />

Defects Liability Period.<br />

40. Administration of Goods Contracts |— (1) <strong>The</strong> Project Manager shall check<br />

compliance with the technical specifications of Goods and arrange for inspection of its quality<br />

and quantity.<br />

(2) <strong>The</strong> Procuring Entity may engage an external agent for the purpose of conducting<br />

pre-shipment inspection of Goods.<br />

(3) <strong>The</strong> Project Manager shall check the compliance with delivery schedule and<br />

conditions and, arrange to settle delays.<br />

(4) <strong>The</strong> Project Manager shall arrange timely payments following the contract terms and<br />

irrevocable letter of credits;<br />

(5) <strong>The</strong> Project Manager shall ensure compliance of maintenance guarantee, after sales<br />

services and warranty obligations;<br />

(6) <strong>The</strong> Project Manager shall ensure the application of the General Conditions of<br />

Contract and other terms specified in the Particular Conditions of Contract 41. Administration<br />

of Consultancy Services Contracts. |— (1) For the purpose of controlling time, cost and quality;<br />

in the case of procurement of Services from inception to completion of the contract administration<br />

and management,, may include the following -<br />

(a) reviewing the quality of designs, studies and other Services provided for in the<br />

assignment;<br />

(b) monitoring the progress and timely completion of deliverables in the case of<br />

39