12. Approval of Delegated <strong>Procurement</strong> |—(1) If a Ministry, Division, Department, or<br />
Directorate does not posses adequate technical capability for certain procurements of Goods,<br />
Works or Services, in that case it may delegate the task to a Procuring Entity, hereafter referred<br />
to as executing agency, competent for such procurement..<br />
(2) <strong>The</strong> Head of the Procuring Entity and the Procuring Entity of the designated<br />
executing agency for such delegated procurement shall act as the Head of the Procuring Entity<br />
and the Procuring Entity respectively and shall perform as follows-<br />
(a) undertake the procurement in accordance with the provisions of these <strong>Rules</strong>;<br />
(b) give approvals as per the Delegation of Financial Powers;<br />
(c) administer the Contract and supervise the project implementation.<br />
(3) <strong>The</strong> owner Ministry, Division, Department, or Directorate shall designate officers to<br />
participate in the whole procurement and implementation process including Tender Evaluation<br />
and shall arrange for monitoring the proper implementation of the procurement and take over its<br />
authority from the Executing Agency upon completion.<br />
Example<br />
If the Ministry of Youth and Sports or Department of Youth Development delegates<br />
implementation of any work o the project to the PWD, in that case the Head of the<br />
Procuring Entity and the Procuring Entity of the PWD will act as the Head of the<br />
Procuring Entity and the Procuring Entity respectively and shall be its implementing<br />
party. <strong>The</strong> Ministry of Youth and Sports or Department of Youth Development, being the<br />
Owner, shall take over the authority from the PWD upon completion.<br />
(4) <strong>The</strong> Executing Agency shall obtain the approval of the owner Ministry, Division or<br />
Department or Directorate with regard to location of procurement, design, construction materials<br />
and other matters ancillary to such delegated work.<br />