Part-B<br />

Annual <strong>Procurement</strong> Plan for Development & Revenue Budgets<br />

Time bound <strong>Procurement</strong> assists a Procuring Entity to effectively plan its <strong>Procurement</strong><br />

requirements and is an important and useful tool used to monitor the progress of<br />

<strong>Procurement</strong> (a) to ensure that it does not go astray; (b) to ensure that early problems with<br />

slippage can be dealt with promptly; and (c) can form a useful Annual Plan for <strong>Procurement</strong>.<br />

A separate Schedule, completed as follows, should be provided for Goods, Works and<br />

Services. Also a separate schedule should be used for Development or Revenue Budget.<br />

Col<br />

No<br />

1<br />

2<br />

3 /4<br />

5<br />

6<br />

7<br />

8<br />

Activity<br />

Package Number<br />

Description of<br />

<strong>Procurement</strong> Item<br />

Unit & Quantity<br />

<strong>Procurement</strong><br />

Method & Type<br />

Contract<br />

Approving<br />

Authority<br />

Source of Funds<br />

Estimated Cost<br />

In Tk million<br />

9 Time Code for<br />

Process<br />

10<br />

Not Used (Goods)<br />

Note<br />

)<br />

) To be copied from the Total <strong>Procurement</strong> Plan for Development<br />

) Project / Programme for those packages required in this financial<br />

year.<br />

)<br />

)<br />

) In the case of <strong>Procurement</strong> using funds from the Revenue Budget<br />

the<br />

)columns shall be completed based upon information in the Revenue<br />

Budget.<br />

)<br />

)<br />

)<br />

In the first row on each form examples have been given to assist the<br />

Procuring Entity in completion of the Forms<br />

Column 10 does not apply for Goods <strong>Procurement</strong><br />

10<br />

Pre-Qualification<br />

(Works)<br />

If Pre-Qualification is used then enter the anticipated process time in<br />

the “Planned Days” column 11. Include time for Advertising,<br />

Responding to Advert, Evaluation and Approval (this may be as high<br />

as 80-90 days in some cases).<br />

10<br />

Advertise EOI<br />

Determine the time it will take from issue of EOI, receiving responses,<br />

evaluation and approval to Issue of RFP date and enter the number of<br />

days in the “Planned Days” box in column 11.<br />

135