117(19) • Minimum forty two (42) days for international <strong>Procurement</strong><br />

127(5)(b)<br />

127(5) (c)<br />

130(e)<br />

Time by which the Head of the Procuring Entity decides or forms committee<br />

on professional misconduct, offences etc.<br />

• Within (five) 5 working days from the date of receipt of the relevant report<br />

Time by which the Committee submits its report and recommendation to the<br />

HOPE.<br />

• Within (five) 5 working days from the date of receipt of the relevant report<br />

Delivery of Annual Report by CPTU to the Government<br />

• Within seven (7) months from the beginning of the current Fiscal Year<br />