39(4) Time for decision by the Procuring Entity to extend the Intended Completion<br />

Date<br />

• within twenty-one (21) days of the Contractor asking the Project Manager for<br />

an extension<br />

39(18)<br />

Amendment to the Contract by the Approving Authority<br />

• When increase on account of approved variations is within fifteen percent<br />

(15%) of the original Contract price but not exceeding Tk. 10 (ten) million<br />

39(22) Time for payment to the Contractor<br />

• Within twenty-eight (28) days of the date of each certificate<br />

39(29)<br />

39(29)(a)<br />

Certification of the Final Payment due to the Contractor<br />

• Within fifty-six (56) days of receiving the Contractor’s account if it is correct<br />

and complete<br />

Time Limit to issue Defects Liability Schedule<br />

• Within fifty-six (56) days from the Contractor’s request for Final Payment.<br />

39(33)<br />

43(1)<br />

46 (1)<br />

46 (1)&<br />

(6)<br />

46 (3)<br />

52(3) (b)<br />

52(3) (d)<br />

54(2)<br />

Time Limit for the Procuring Entity to take over the Site and the Works<br />

• Within seven (7) days of the Project Manager’s issuing a certificate of<br />

Completion.<br />

Records of <strong>Procurement</strong> to be Maintained by a Procuring Entity<br />

• For a minimum period of five (5) years<br />

• Longer than five (5) years in special cases with the approval of the Head of<br />

Procuring Entity or an authorized officer<br />

<strong>Procurement</strong> Post Review<br />

• When volume of <strong>Procurement</strong> of a Procuring Entity in one particular<br />

financial year is more than Tk.100 (one hundred) million<br />

Time for <strong>Procurement</strong> Post Review<br />

• Within nine (9) months of the end of each financial year<br />

Minimum Number & Percentage of Contracts for <strong>Procurement</strong> Post Review<br />

• Not less than fifteen percent (15%) of the number of contracts awarded in<br />

that year to be selected by the independent Consultant in such a manner as<br />

to cover at least thirty percent (30%) of the total contracts’ value.<br />

Formation of the Enlistment Committee<br />

Minimum of three (3) members, of which<br />

• One (1) member may represent the financial unit,<br />

• One (1) member may represent the technical units of the concerned<br />

Procuring Entity and<br />

• One (1) member may be from outside the Procuring Entity.<br />

Updating the Enlistment- Time by which the Procuring Entity shall notify<br />

Suppliers and Contractors of the annual meeting<br />

• at least seven (7) days in advance of the meeting through advertisement<br />

Value of non Judicial stamp for execution of contracts relating to JVCA<br />

• Tk. 300 (three hundred) or as required by the Government<br />