<strong>Transformer</strong> <strong>life</strong> <strong>extension</strong><br />

Repair and refurbishment service<br />

Extend the <strong>life</strong> of your transformers and kiosks


<strong>Transformer</strong> <strong>life</strong> <strong>extension</strong><br />

<strong>Schneider</strong> <strong>Electric</strong> offers a range of refurbishment and repair services to extend<br />

the <strong>life</strong> of transformers and kiosks. By partnering with <strong>Schneider</strong> <strong>Electric</strong> you can<br />

gain full <strong>life</strong>cycle support for your electrical distribution equipment and maximise<br />

the return on your investment. Benefit from our expertise gained through 40<br />

years of transformer manufacturing in Australia.<br />

<strong>Transformer</strong> repair and refurbishment services<br />

Level 1<br />

Level 4<br />

On-site inspection and condition assessment<br />

Major repair<br />

Inspection of the transformer at your premises followed by a written report<br />

of our findings and recommendations. This includes:<br />

>> visual inspection of external condition for faults and signs of damage<br />

>> paint condition and corrosion<br />

>> oil leaks; identify point of origin and cause<br />

>> obtain samples of oil for testing (see oil testing options over the page).<br />

Level 2<br />

On-site repair<br />

Example services:<br />

>> Repair minor oil leaks in the tank or radiators.<br />

>> Replace gaskets (requires lowering of oil level).<br />

>> Touch-up paint work.<br />

>> Inspect tap changer.<br />

Level 3<br />

Intermediate repair<br />

The offer comprises the Intermediate repair, plus:<br />

>> remove transformer core and coils<br />

○ dry the core (to remove moisture from the<br />

insulating papers)<br />

○ carry out repairs to the core assembly<br />

(as required)<br />

>> replace failed components<br />

(bushings, ancillary devices, etc.).<br />

Level 5<br />

End-of-<strong>life</strong> disposal<br />

The offer ensures safe, environmentally friendly<br />

disposal of the equipment. Hazardous materials<br />

are extracted and disposed of by specialist<br />

partners approved by <strong>Schneider</strong> <strong>Electric</strong>.<br />

Maximum recycling of materials is achieved.<br />

This is demonstrated by our reporting system to<br />

provide confidence and assurance.<br />

Undertaken at our transformer refurbishment facility:<br />

>> Repair oil leaks in the tank or radiators.<br />

>> Replace gaskets.<br />

>> Re-paint using <strong>Schneider</strong> <strong>Electric</strong> approved paint system.<br />

>> Test and replace tap changer as required.<br />

>> Inspection and cleaning of bushings.<br />

>> <strong>Electric</strong>al testing.


Maximise your return on investment<br />

Oil testing services<br />

Test A<br />

PCBs<br />

<strong>Transformer</strong> oil must be tested for polychlorinated<br />

biphenyls (PCBs) before disposal.<br />

Test B<br />

Dissolved Gas Analysis (DGA)<br />

DGA testing evaluates the condition of the<br />

transformer by the presence of gasses dissolved<br />

in the oil. Whenever transformer oil is exposed to<br />

thermal of electrical faults, the natural breakdown<br />

process is greatly accelerated. During breakdown<br />

of the oil, certain hydrocarbon based<br />

gasses are produced in small quantities. The<br />

magnitude of the fault and surrounding materials<br />

will determine which gasses are produced.<br />

Test C<br />

Basic Condition Assessment<br />

This comprises a suite of oil tests to indicate<br />

the condition of the transformer. It includes<br />

DGA (Test B), plus:<br />

>> colour and visual examination<br />

>> moisture content<br />

>> interfacial tension<br />

>> acid number<br />

>> dielectric breakdown voltage.<br />

Test D<br />

Full Condition Assessment<br />

This comprises an exhaustive suite of oil tests<br />

to provide information on the overall condition<br />

of the transformer. Using a proven technique it<br />

interprets both the dissolved gas analysis and<br />

fluid information to aid the diagnosis and<br />

management of any faults. It includes Basic<br />

Condition Assessment (Test C), plus:<br />

>> dielectric dissipation factor<br />

>> oxidation inhibitor<br />

>> furans, with estimated degree<br />

of polymerisation<br />

>> particle profile.<br />

Kiosk substation refurbishment contracts<br />

Before<br />

After<br />

In addition to our transformer repair and refurbishment services, we also provide:<br />

CLIPCOM21650<br />

>> door-to-door kiosk refurbishment<br />

service contracts<br />

>> condition assessment<br />

>> kiosk enclosure repairs and re-paint<br />

>> MV and LV switchgear inspection and<br />

repairs or replacement<br />

>> upgrade transformer power capacity<br />

>> full re-testing of complete kiosk.


Value throughout your system <strong>life</strong>cycle<br />

Improve<br />

> <strong>Transformer</strong> <strong>life</strong> <strong>extension</strong><br />

Your performance<br />

Renew<br />

Improve<br />

Operate<br />

Design<br />

Build<br />

Other service<br />

offers include:<br />

> site audits<br />

> installation<br />

> pre-commissioning<br />

> maintenance contracts<br />

> spare parts management<br />

> diagnostic testing<br />

> retrofits<br />

> transformer refurbishments<br />

> end-of-<strong>life</strong> disposal<br />

> SF6 gas recovery.<br />

<strong>Schneider</strong> <strong>Electric</strong> (Australia) Pty Limited<br />

Head Office<br />

Australia Wide<br />

Postal Address: Tel: 1300 369 233<br />

Locked Bag 5500 Fax: 1300 369 288<br />

Baulkham Hills<br />

www.schneider-electric.com.au<br />

NSW 2153 Australia<br />

help@au.schneider-electric.com<br />

<strong>Electric</strong>al Contractors Licences<br />

<strong>Schneider</strong> <strong>Electric</strong> (Australia) Pty Limited is licensed under the<br />

relevant state electrical safety acts: QLD: 66116; NSW: 150195C;<br />

VIC: 17615; SA: PGE210184; WA: EC008813; NT: C2356<br />

For service call 1300 369 233<br />

As standards, specifications and designs change from time to time, always ask for confirmation of the<br />

information given in this publication.<br />

Printed with vegetable oil-based ink<br />

on<br />

Mega Recycled FSC<br />

100% FSC certified fibre<br />

50% FSC certified recycled (post consumer waste)<br />

50% FSC certified fibre - sustainable forestry<br />

ISO 14001 environmental management system in use at mill<br />

M-real purchase renewable energy to manufacture Mega Recycled FSC<br />

Information given in this publication was accurate at the time of printing.<br />

SERED1270710AU<br />

© <strong>Schneider</strong> <strong>Electric</strong> (Australia) Pty Limited

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!