Volume 2-05, Chapter 3 - City of Wichita
Volume 2-05, Chapter 3 - City of Wichita Volume 2-05, Chapter 3 - City of Wichita
Section 3.4.2 - Underground Dry Detention Pond 3.4.2.1 General Description Detention vaults are box-shaped underground stormwater storage facilities typically constructed with reinforced concrete. Detention pipe/tank systems are underground storage facilities typically constructed with large diameter pipe or pre-cast concrete culvert sections. They serve as an alternative to surface dry detention for stormwater quantity control, particularly for space-limited areas where there is not adequate land for a detention basin. Underground detention systems can provide channel protection through extended detention of the CP v , and flood control through aboveground detention. Basic storage design and routing methods are the same as for detention basins except that a bypass for high flows may be included. Underground detention systems are not intended for water quality treatment and must be used in a treatment train approach with other structural controls that provide treatment of the WQ v . This will help prevent the underground vault or tank from becoming clogged with trash or sediment and significantly reduces the maintenance requirements for an underground detention system. Underground detention systems located in floodplains or backwater areas must perform as specified for peak flow control for any tailwater condition, up to the Base Flood Elevation (BFE). The potential for back flow into the pond must be addressed with flap gates or by providing sufficient volume to receive backflow up to the BFE, and still provide peak flow control surcharge volume in the pond (above the BFE). Prefabricated vaults are available from commercial vendors. In addition, several pipe manufacturers have developed packaged detention systems. 3.4.2.2 Design Criteria and Specifications Location • Underground detention systems are to be located downstream of other structural stormwater controls providing treatment of the WQ v . • The contributing drainage area to be served by a single underground detention vault or tank is typically less than 200 acres. General Design • Underground detention systems may be sized to provide extended detention of the CP V for 24 hours, and/or to temporarily store the volume of runoff required to provide the desired flood protection. • Routing calculations must be used to demonstrate that the storage volume is adequate. See Chapter 4 for procedures on the design of detention storage. • Detention Vaults: All construction joints must be provided with embedded waterstops. Page 3 - 188 Volume 2, Technical Guidance
Section 3.4.2 - Underground Dry Detention Pond • Detention Pipe/Tank Systems: The minimum pipe diameter for underground detention tanks is 36 inches. • Underground detention vaults and pipe/tank systems must meet structural requirements for external and internal loads, as applicable. • Adequate air venting above the maximum water surface is essential for proper operation of the detention system. • The local jurisdiction may require that the facility be placed in a reserve and/or establishment of a drainage easement the facility, which is accessible from a public road or other accessible easement. When required, the drainage easement should be at least 20 feet wide, provide a minimum traversable width of 15 feet, have a maximum slope of no more than 10%, and be appropriately stabilized to withstand maintenance equipment and vehicles. Access must be provided over the inlet pipe and outflow structure. Access openings can consist of a standard frame, grate and solid cover, or a removable panel. Vaults with widths of 10 feet or less should have removable lids. Inlet and Outlet Structures • A separate sediment sump or vault chamber with a volume of 0.1 inches per impervious acre of contributing drainage shall be provided at the inlet for on-line underground detention systems that are located downstream of an off-line water quality treatment control. • For CP v control, a low flow orifice capable of detaining the CP V for 24 hours must be provided. The channel protection orifice should have a minimum diameter of 3 inches and should be adequately protected from clogging by an acceptable external trash rack. The orifice diameter may be reduced to 1 inch if internal orifice protection is used (i.e., an overperforated vertical stand pipe with 0.5-inch orifices or slots that are protected by wirecloth and a stone filtering jacket). Adjustable gate valves can also be used to achieve this equivalent diameter. • For on-site flood control, an additional outlet is sized for control of the chosen return period (based on hydrologic routing calculations) and can consist of a weir, orifice, outlet pipe, combination outlet, or other acceptable control structure. • See Chapter 5 for more information on the design of outlet works. • Riprap, plunge pools or pads, or other energy dissipators are to be placed at the end of the outlet to prevent scouring and erosion. See Chapter 5 for more guidance. • An emergency spillway shall be included in the underground detention system design to safely pass the 100-year flood flow. 3.4.2.3 Inspection and Maintenance Requirements Regular inspection and maintenance is critical to the effective operation of stormwater management facilities. An operation and maintenance plan is required and shall include: Volume 2, Technical Guidance Page 3 - 189
- Page 143 and 144: Section 3.2.10 - Stormwater Wetland
- Page 145 and 146: Section 3.2.10 - Stormwater Wetland
- Page 147 and 148: Section 3.2.10 - Stormwater Wetland
- Page 149 and 150: Section 3.2.10 - Stormwater Wetland
- Page 151 and 152: Section 3.3 - Secondary TSS Treatme
- Page 153 and 154: Section 3.3.1 - Proprietary Treatme
- Page 155 and 156: Section 3.3.1 - Proprietary Treatme
- Page 157 and 158: Section 3.3.2 - Gravity (Oil-Water)
- Page 159 and 160: Section 3.3.2 - Gravity (Oil-Water)
- Page 161 and 162: Section 3.3.2 - Gravity (Oil-Water)
- Page 163 and 164: Section 3.3.3 - Alum Treatment 3.3.
- Page 165 and 166: Section 3.3.3 - Alum Treatment •
- Page 167 and 168: Section 3.3.4 - Underground Sand Fi
- Page 169 and 170: Section 3.3.4 - Underground Sand Fi
- Page 171 and 172: Section 3.3.4 - Underground Sand Fi
- Page 173 and 174: Section 3.3.4 - Underground Sand Fi
- Page 175 and 176: Section 3.3.4 - Underground Sand Fi
- Page 177 and 178: Section 3.3.4 - Underground Sand Fi
- Page 179 and 180: Section 3.3.4 - Underground Sand Fi
- Page 181 and 182: Section 3.3.5 - Organic Filter 3.3.
- Page 183 and 184: Section 3.3.5 - Organic Filter •
- Page 185 and 186: Section 3.4 - Other Stormwater Mana
- Page 187 and 188: Section 3.4.1 - Conventional Dry De
- Page 189 and 190: Section 3.4.1 - Conventional Dry De
- Page 191 and 192: Section 3.4.1 - Conventional Dry De
- Page 193: Section 3.4.2 - Underground Dry Det
- Page 197 and 198: Section 3.4.2 - Underground Dry Det
- Page 199 and 200: Section 3.4.3 - Porous Pavement 3.4
- Page 201 and 202: Section 3.4.3 - Porous Pavement The
- Page 203 and 204: Section 3.4.3 - Porous Pavement com
- Page 205 and 206: Section 3.4.3 - Porous Pavement Fig
- Page 207 and 208: Section 3.4.4 - Modular Porous Pave
- Page 209 and 210: Section 3.4.4 - Modular Porous Pave
- Page 211 and 212: Section 3.4.4 - Modular Porous Pave
- Page 213 and 214: Section 3.4.5 - Green Roof 3.4.5 Gr
- Page 215 and 216: Section 3.4.5 - Green Roof Signific
- Page 217 and 218: Section 3.4.5 - Green Roof 3.4.5.3
Section 3.4.2 - Underground Dry Detention Pond<br />
• Detention Pipe/Tank Systems: The minimum pipe diameter for underground detention<br />
tanks is 36 inches.<br />
• Underground detention vaults and pipe/tank systems must meet structural requirements<br />
for external and internal loads, as applicable.<br />
• Adequate air venting above the maximum water surface is essential for proper operation<br />
<strong>of</strong> the detention system.<br />
• The local jurisdiction may require that the facility be placed in a reserve and/or<br />
establishment <strong>of</strong> a drainage easement the facility, which is accessible from a public road<br />
or other accessible easement. When required, the drainage easement should be at least<br />
20 feet wide, provide a minimum traversable width <strong>of</strong> 15 feet, have a maximum slope <strong>of</strong> no<br />
more than 10%, and be appropriately stabilized to withstand maintenance equipment and<br />
vehicles. Access must be provided over the inlet pipe and outflow structure. Access<br />
openings can consist <strong>of</strong> a standard frame, grate and solid cover, or a removable panel.<br />
Vaults with widths <strong>of</strong> 10 feet or less should have removable lids.<br />
Inlet and Outlet Structures<br />
• A separate sediment sump or vault chamber with a volume <strong>of</strong> 0.1 inches per impervious<br />
acre <strong>of</strong> contributing drainage shall be provided at the inlet for on-line underground<br />
detention systems that are located downstream <strong>of</strong> an <strong>of</strong>f-line water quality treatment<br />
control.<br />
• For CP v control, a low flow orifice capable <strong>of</strong> detaining the CP V for 24 hours must be<br />
provided. The channel protection orifice should have a minimum diameter <strong>of</strong> 3 inches and<br />
should be adequately protected from clogging by an acceptable external trash rack. The<br />
orifice diameter may be reduced to 1 inch if internal orifice protection is used (i.e., an<br />
overperforated vertical stand pipe with 0.5-inch orifices or slots that are protected by<br />
wirecloth and a stone filtering jacket). Adjustable gate valves can also be used to achieve<br />
this equivalent diameter.<br />
• For on-site flood control, an additional outlet is sized for control <strong>of</strong> the chosen return period<br />
(based on hydrologic routing calculations) and can consist <strong>of</strong> a weir, orifice, outlet pipe,<br />
combination outlet, or other acceptable control structure.<br />
• See <strong>Chapter</strong> 5 for more information on the design <strong>of</strong> outlet works.<br />
• Riprap, plunge pools or pads, or other energy dissipators are to be placed at the end <strong>of</strong><br />
the outlet to prevent scouring and erosion. See <strong>Chapter</strong> 5 for more guidance.<br />
• An emergency spillway shall be included in the underground detention system design to<br />
safely pass the 100-year flood flow.<br />
3.4.2.3 Inspection and Maintenance Requirements<br />
Regular inspection and maintenance is critical to the effective operation <strong>of</strong> stormwater<br />
management facilities. An operation and maintenance plan is required and shall include:<br />
<strong>Volume</strong> 2, Technical Guidance Page 3 - 189